Project Package PROJECT NAME: PROJECT VALUE:
Daniel & Michelle Fisher_Project Package_Rev.0 US$
97,539.51
PROJECT DURATION:
3.7 Month Timeline
PROJECT LOCATION:
Harare, Zimbabwe
PROJECT BRIEF:
3 Bed Bungalow, with floor area of; 306 m²
Summary of basic materials, further details available inside Package Cement 873 bags ¾ Stones 82.3 m³ R/Sand 55.2 m³ Bricks 44,163 bricks P/Sand 52.2 m³ 230 B/Force 40 rolls 115 B/Force 36 rolls 230 DPC 5 rolls 115 DPC 4 rolls
┐
┌
┘
└
Contents Page a) Materials Procurement in Stages …………1 Consists of builders materials in construction stages, from the sub-structure to the superstructure and any waste management system. b) Bill of Quantities | Interface (Summary) …………2 Consists of the summary of a 14 paged Bill of Quantities priced in USD, full version available upon request. c) Resources | Console
…………3
Consists of the Quantity and Monetary Value of Requirements for payment and procurement, which are Man-hours for Labour, Plant-hours for Machines & Equipment and a detailed Material Schedule of Quantities for every item to be installed on site. d) Construction Schedule | Baseline …………6 This document shows the sequence of operations to be executed on site in a safe manner, indicating durations of activities calculated from the measured quantity of work and determined by the productivity expected in each day, and it's linked to the Bill of Quantities.
(i)
┐
┌
NB: Materials shown in Monetary Terms will have to be viewed in the Resources Console For any clarifications, feel free to contact the undersigned Agent for assistance
DWG Ref - 3.20 Daniel & Michelle Fisher_Project Package_Rev.0 Materials in Construction Stages Item
Description
Cement
¾ Stones
R/Sand
Bricks
P/Sand
230 B/Force
115 B/Force
230 DPC
115 DPC
others as described
SUBSTRUCTURE (UP TO SLAB) a) b) c) d) e) f)
Clearing & / Setting Out Trench Excavations Blinding Concrete Footing Substructure Brickwork Concrete Slab
g) h) i) j) k) l) m) n) o) p) q) r)
Doors with frame c/w hinges, screws & locksets Windows & Handles c/w nuts, bolts & washer Superstructure Brickwork, Window Level Superstructure Brickwork, Wall Plate Level Ring Beam Plaster External Plaster Internal Rhinoset Paint PVA High Gloss (Steel Frames) Sush Putty (N/A to Aluminium Frames) Wall Plate
s) t) u) v) w)
Roof Trusses (aggregates where gable ends exist) Purlins & Brandering Roof Covering Ceiling & Cornice Rainwater Goods
antkill- 3.3ℓ bags 166 bags 40 bags 281 bags
0.0 m³ 19.6 m³
0.0 m³ 15.9 m³ 9,019 bricks
7.2 m³
9 rolls
7 rolls
5 rolls
4 rolls
33.1 m³ 26.8 m³ SUPER STRUCTURE (UP TO WALL PLATE)
rebar- kgs 300m 224 m² S.193- 15 sheets $ 975.98 $ 3,678.42
100 bags 33 bags 110 bags 18 bags 67 bags
23,277 bricks 8,568 bricks 13.0 m³
18.0 m³ 6.0 m³
20 rolls 7 rolls
22 rolls 7 rolls
10.5 m³
rebar 745 kgs 3.2 m³ 12.1 m³ 60 bags 165 ℓ 7ℓ kgs 93 m
bags
ROOF (TRUSSES, COVERING & CEILING) bricks
0.0 m³
rolls
$ 11,248.40 1,482 m 157 tiles $ 1,544.44 $ 1,829.06
SERVICES (WATER & ELECTRICITY) x) y) z)
Plumbing & Fittings Electricals & Fittings Septic Tank Column Totals for Material Headings
Created on 6/6/2020 @ 1:09 PM
$ $ 54 bags 873 bags
16.6 m³ 82.3 m³
WASTE MANAGEMENT 2.0 m³ 3,300 bricks 55.2 m³ 44,163 bricks
3.20_Daniel & Michelle Fisher_Project Package_Rev.0.xlsx Materials Procurement in Stages Page 1 of 7
5.3 m³ 52.2 m³
4 rolls 40 rolls
6,946.48 1,302.80
300m 12.5 m² 36 rolls
5 rolls
4 rolls
+263 77 192 7337 jeffstar@presageprojects.co.zw Presage Projects (Pvt) Ltd © 2020 All Rights Reserved
RICS NRM 2 Adoption 6/6/2020
PPHBQ2020_Rev.0
DWG Ref - 3.20 Daniel & Michelle Fisher_Project Package_Rev.0 Elemental Bill of Quantities Item №
Pay Ref
$
Bill Description
Unit
Quantity
Rate (US$)
-
Amount (US$)
Quick Stats building $/m² =$371.47/m²
Summary
building $/m³ =$132.67/m³ 0.00% $
Bill No. 1 Preliminaries (Main Contract)
-
Bill No. 2 Substructure
16.72% $
13,892.57
Bill No. 3 Superstructure
53.04% $
44,081.77
Bill No. 4 Finishes
7.51% $
6,237.76
Bill No. 5 Fittings, Furnishings and Equipment
9.22% $
7,662.89
11.10% $
9,223.94
2.42% $
2,010.68
Subtotal
$
83,109.61
Plus 2.50% Contingency Sum
$
2,077.74
Subtotal
$
85,187.35
Add Vat @ 14.50%
$
12,352.17
Total Amount
$
97,539.51
Bill No. 6 Services Bill No. 7 External Works
3.20_Daniel & Michelle Fisher_Project Package_Rev.0.xlsx Bill of Quantities|Interface Page 2 of 7
+263 77 192 7337 jeffstar@presageprojects.co.zw Presage Projects (Pvt) Ltd © 2020 All Rights Reserved
┌
Created on 6/6/2020 @ 1:09 PM┐
Confidential Resource Usage
DWG Ref - 3.20 Daniel & Michelle Fisher_Project Package_Rev.0 Bill of Resources Cost Code
Resource Description
L L01 L03 L04 L05 L06 L07 L09 L14 L16 L17
Payroll Budget Information @ 9 Man-hours/Day General Hand Carpenter (C) Builder (B) Painter (T) Steel Fixer (X) Glazier (G) Electrician (E) Plumber (P) Light Plant/Equipment Operator (L) Heavy Plant Operator (H)
P F01 P02 P03 P04 P16 P17 P18 P19 M BM CMT01 CMT02 CMT03 CMT04 BM003 BM004 BM005 RP01 MAS01 MAS06 MAS07 MAS08 RNF01 RNF02 RNF03 RNF04 RNF06 RNF07 SH01 MP01 MP02 MP03 DP01 DP02 DP03 DP04 DP05 DP06 DP10 DF01 DF02 DF03
AWF01 AWF02 AWF03 AWF04 AWF05 AWF06 AWF07 DR01 DR02 DR03 SWD01 SWD02 TT01 J01 J02 J03 J04 J07 IM01 IM05 IM06
18.87% Bill Mark-Up @ 0.00% ≡ 2.61% 3.7 Month Timeline ≡ 78.52% US$ 83,109.61 78% 1 0 Excluding VAT Cost Usage Amount (US$) $ (All in Labour Rates) 8,733.5 hours $ 15,684.88 $ 1.57/hour 6,663.2 hours $ 10,474.91 $ 2.50/hour 260.9 hours $ 653.23 $ 2.50/hour 1,301.7 hours $ 3,258.90 $ 2.50/hour 134.7 hours $ 337.20 $ 2.50/hour 07.3 hours $ 18.26 $ 2.50/hour 00.9 hours $ 2.30 $ 2.50/hour 92.8 hours $ 232.40 $ 2.50/hour 212.5 hours $ 531.99 $ 2.85/hour 53.1 hours $ 151.56 $ 3.78/hour 06.4 hours $ 24.14 19% 3%
Plant Hire Hours @ 8 Plant-hours/Day Diesel (Information only, already included in Plant Rates) 140H Grader (b) 3CX TLB (c) Plate Compactor (d) 750/500 Concrete Mixer (n) Concrete Dumper (o) Concrete Vibrator Set (p) Power Trowel Machine (q) Bill of Materials (BoM) Procurement Building Materials Cements Tile Adhesive (20kg) Tile Grout (5kg) 22,5 (Masonry) Cement 32,5 (PC 15) Cement Aggregates 19mm Stone Washed Riversand (Cash - Pre-Payment at the Quarry) Pitsand Rhino Products Rhinoset Masonry Beta Common Bricks Cement air bricks/vents (pair) Window Cills Galvanised wall ties Reinforcement Deformed Reinforcement Bars (Cut & Bent) Tying Wire 1.6mm ø MeshRef S193 MeshRef S245 Brickforce 230 (@ every 4th course) Brickforce 115 (@ every 4th course) Shuttering Formwork for lintels Moisture Protection DPC 2 Ply 230 DPC 2 Ply 115 Polythene Sheets (2Ply) Paints & Products Dulux Universal Undercoat Dulux Int - Ext PVA White Dulux Ceiling White Dulux Steel Prime Dulux Gloss White Dulux Pink Wood Primer Dulux Tinters (Shelf price selling @ $5.00/50ml tube) Door Frames Standard 230 double door frame Standard 230 single door frame Standard 115 single door frame No Yes No Yes Aluminium Window Frames 2100×1500 1800×900 1200×900 600×900 2100×1800 2400×1800 600×2095 Doors External quality standard double door to suit frame Solid standard single door to suit frame Hollow standard single door to suit frame Sliding Doors Double Sliding Doors Single sliding doors Trusses Roof Trusses to detail Joinery 114mm × 38mm sw wall plate 38mm × 38mm sw purlins 38mm × 38mm sw brandering 9mm Plaster Board Ceiling (Supply Dimension - 2.4m × 1.2m) Rhinocove Cornice Iron Mongery Locksets 3 Lever Hinges c.w. screws for doors Window handle c/w nut, bolt & washer
(Plant Charges) $ 1.13/ℓ $ 71.81/hour $ 32.74/hour $ 7.93/hour $ 29.66/hour $ 23.77/hour $ 4.06/hour $ 18.78/hour (Material Costs)
101.1 hours 429.40 ℓ 0.3 hours 9.2 hours 2.1 hours 32.2 hours 20.9 hours 20.9 hours 15.5 hours Order Quantity
$ $ $ $ $ $ $ $ $ $ $ $
$5.24/sack $5.24/sack $8.30/sack $9.78/sack
29.94 10.66 7 852
bags bags bags bags
$ $ $ $ $
$34.93/m³ $21.83/m³ $17.47/m³
67.8 m³ 55.2 m³ 50.4 m³
$ $ $ $
$13.10/sack
60 bags
$ $
$0.16/brick $0.66 ea $0.87 ea $0.17 ea
44,163 bricks 28 no 212 cills 48 no
$ $ $ $ $
$3,493.45/ton $2.36/kg $5.24/m² $10.48/m² $2.18/roll $1.75/roll
0.745 tons 1.12 kgs 224 m² 38 m² 40 rolls 36 rolls
$ $ $ $ $ $ $
$3.93/m
32 m
$ $
$3.49/roll $1.75/roll $0.22/m²
5 rolls 4 rolls 460 m²
$ $ $ $
$5.68/ℓ $5.24/ℓ $2.62/ℓ $9.61/ℓ $10.48/ℓ $5.68/ℓ $87.34/ℓ
79 63 22 2.4 2.2 2.1 0.21
$ $ $ $ $ $ $
ℓ ℓ ℓ ℓ ℓ ℓ ℓ $
$52.40 ea $26.20 ea $14.85 ea
1st Choice/Option $496.47 $255.33 $170.22 $85.11 $595.76 $680.87 $198.11
1 no 2 no 10 no
US$ ea ea ea ea ea ea ea
540.00 2 no 3 no 2 no 1 no 1 no 1 no 1 no
$ $ $
$ $ $ $ $ $ $ $ $
$174.67 ea $87.34 ea $17.47 ea
1 no 2 no 10 no
$ $ $ $
$209.61 ea $174.67 ea
1 no 1 no
$ $ $
$473.62 ea
24 no
$ $
$4.37/m $2.62/m $0.87/m $4.80/m² $1.31/m
93 m 571 m 911 m 223.7 m² 359 m
$ $ $ $ $ $
$13.97 ea $1.31 ea $1.75 ea
3.20_Daniel & Michelle Fisher_Project Package_Rev.0.xlsx Resources|Console Page 3 of 7
13 sets 13 no 11 no
$ $ $
2,167.72 484.34 21.48 302.38 16.44 954.91 496.95 84.82 290.74 65,257.00 65,220.86 8,603.98 156.91 55.86 59.82 8,331.40 4,454.88 2,369.63 1,205.14 880.10 780.89 780.89 7,154.85 6,942.71 18.34 185.50 8.30 4,321.51 2,603.33 2.65 1,172.40 393.01 87.12 63.01 126.20 126.20 125.55 18.04 7.09 100.43 914.81 448.35 331.09 58.62 23.28 22.85 11.95 18.68 253.28 52.40 52.40 148.47
3,659.20 992.93 765.98 340.43 85.11 595.76 680.87 198.11 524.02 174.67 174.67 174.67 384.28 209.61 174.67 11,248.40 11,248.40 4,241.75 406.11 1,495.21 795.99 1,074.70 469.74 217.90 181.66 17.03 19.21 +263 77 192 7337 info@presageprojects.co.zw Presage Projects (Pvt) Ltd © 2020 All Rights Reserved
┌
Created on 6/6/2020 @ 1:09 PM┐
Confidential Resource Usage
DWG Ref - 3.20 Daniel & Michelle Fisher_Project Package_Rev.0 Bill of Resources
19% 3%
≡ ≡ 1
Cost Code
Resource Description
Cost
TL01 TL02
Rainwater Goods PVC Rainwater Gutters ½ round 125 × 87 Rainwater Downpipe 80mm Drip stones 0.9 x 2.4 Chromadek Roof Sheets Concrete Roof Tiles 25mm × 220mm sw Fascia Galvanised Roof Ridge Galvanised Valley Kitchen Fittings Kitchen sink 1.2m drop in Cupboards under sink Cupboards on walls HVAC Ceiling fan Bathroom Fittings Wall mounted cabinet with mirror Towel rack Water Closet Ceramic wash basin & pedestal Shower Cubicle 950 × 950 × 2000mm corner type Bath tub (Acrylic) Ceramic Soap Dish Tiles Floor tiles 600 x 600 Wall tiles 600 x 200
PCI01 PCI02
Pre-Cast Items Double Cam Concrete Sink Pre-cast lintels
RG03 RG07 RG10 RG11 RG12 RG13 RG14 KF01 KF03 KF04 HVAC02 BF01 BF02 BF03 BF09 BF10 BF11 BF13
PVCSP01 PVCSP02 GP01 CP01 GF01 GF02 GF03 GF04 GF05 CF01 CF02 CF03 PVCFT01 PVCFT02 PVCFT03 PVCFT04 PVCFT05 PVCFT06 PVCFT07 PVCFT08 PVCFT09 TM01 TM02 TM06 RF01 SD01 WMS01
CN01 CNF01 CNF02 CB02 CB05 SW01 SW04 ST01 ST02 ST03 ST04 ST05 ST07 B01 B02 EMS01 EMS02
0
Usage
$4.37/m $3.91/m $13.10 ea $5.66 ea $10.48/m $5.24/m $3.50/m $61.14 ea $1353.71 ea $1222.71 ea $56.77 ea $52.40 $22.71 $78.60 $34.93 $131.00 $65.50 $4.37
ea ea ea ea ea ea ea
$1.89 ea $0.63 ea
$ $78.60 ea $1.75/m
Plumbing PVC Sewer Pipes ø110mm sewer pipe ø60mm sewer pipe Galvanised Pipes ø20mm GI pipe Copper Pipes ø20mm copper pipe Galvanised Fittings ø20mm Gi elbow ø20mm Gi tee ø20mm Gi sleeve ø35mm brass p-trap for bath ø35mm Gate Valve Copper Fittings ø20mm copper elbow ø20mm copper tee ø20mm copper sleeve PVC Fittings ø160mm to ø110mm reducer ø110mm x 90° bend ø110mm x 45° bend ø110mm equal tees ø110mm end caps ø110mm p-trap ø110mm sieve ø110mm × 2m pvc vent pipe ø110mm fly trap over vent pipe Taps & Mixers ø15mm basin taps (Cobra) Sink Mixer ø35mm brass tap Rubber Fittings ø35mm rubber p-trap Sewer Disposal (Septic Tank) Square Manhole Cover & Frame Water Main Supply ZINWA flow meter Electricals Conduits ø19mm pvc conduit Conduit Fittings ø20mm pvc sleeve Junction box (6 × 6) Cables 2.5mm² triple core copper conductors armoured cable Switches Single gang switch Cooker switch Sockets single electric socket double electric socket Cooker terminal Shaver socket Lamp holder (Brass) Fluorescent socket Bulbs/Lights Bulkhead c/w gland seal Osram 11watt fluorescent bulb Electrical Main Supply 3 Phase meter board Generator/Solar change over switch
78%
18.87% Bill Mark-Up @ 0.00% 2.61% 3.7 Month Timeline 78.52% US$ 83,109.61 Excluding VAT Amount (US$) $ $ 2,719.07 96 m $ 417.76 14 m $ 54.78 5 no $ 65.50 157 no $ 890.01 96 m $ 1,002.63 46 m $ 242.88 13 m $ 45.50 $ 5,213.97 1 no $ 61.14 2 no $ 2,707.42 2 no $ 2,445.41 $ 170.31 3 no $ 170.31 $ 915.28 2 no $ 104.80 3 no $ 68.12 3 no $ 235.81 3 no $ 104.80 2 no $ 262.01 2 no $ 131.00 2 no $ 8.73 $ 941.44 119 no $ 224.70 1,140 no $ 716.74
1 no 32 m
$ $ $ $
$9.61/m $1.75/m
30 m 11 m
$ $ $
$21.83/m
72 m
$ $
$21.83/m
72 m
$ $
$7.86 $14.85 $13.10 $3.49 $4.80
ea ea ea ea ea
24 24 24 4 11
no no no no no
$ $ $ $ $ $
$8.73 ea $16.59 ea $14.85 ea
24 no 24 no 24 no
$ $ $ $
$31.44 $31.70 $34.93 $17.47 $4.37 $30.57 $5.24 $7.42 $2.18
ea ea ea ea ea ea ea ea ea
1 10 10 10 1 10 10 3 3
no no no no no no no no no
$ $ $ $ $ $ $ $ $ $
$6.99 ea $48.03 ea $4.37 ea
10 no 1 no 2 no
$ $ $ $
$1.75 ea
4 no
$ $
$39.30 ea
1.0 no
$ $
$33.19 ea
1 no
$ $ $
$1.75/m
116 m
$ $
$0.44 ea $0.87 ea
58 no 21 no
$ $ $
$0.26/m $3.49/m
348 m 40 m
$ $ $
$1.92 ea $8.73 ea
21 no 1 no
$ $ $
$2.62 $5.24 $30.57 $3.06 $1.75 $4.80
ea ea ea ea ea ea
21 9 1 2 21 4
no no no no no no
$ $ $ $ $ $ $
$6.99 ea $3.06 ea
2 no 21 no
$ $ $
$34.93 ea 3.20_Daniel & Michelle Fisher_Project Package_Rev.0.xlsx $48.03 ea Resources|Console Page 4 of 7
1 no 1 no
$ $
134.69 78.60 56.09 6,946.48 307.42 288.21 19.21 1,572.05 1,572.05 1,572.05 1,572.05 926.20 188.65 356.33 314.41 13.97 52.84 964.19 209.61 398.25 356.33 1,263.76 31.44 317.03 349.34 174.67 4.37 305.68 52.40 22.27 6.55 126.64 69.87 48.03 8.73 6.99 6.99 39.30 39.30 33.19 33.19 1,302.80 202.40 202.40 43.64 25.30 18.34 230.82 91.08 139.74 49.08 40.35 8.73 194.76 55.02 47.16 30.57 6.11 36.68 19.21 78.17 13.97 64.19 503.93 34.93 48.03 +263 77 192 7337 info@presageprojects.co.zw Presage Projects (Pvt) Ltd © 2020 All Rights Reserved
┌
Created on 6/6/2020 @ 1:09 PM┐
Confidential Resource Usage
DWG Ref - 3.20 Daniel & Michelle Fisher_Project Package_Rev.0 Bill of Resources
19% 3%
≡ ≡ 1
Cost Code EMS04 EMS05
ACC ACC01 ACC02 ACC03 ACC08 ACC11
Resource Description
0 Cost
Distribution board 16 Way c/w Breakers ZETDC Prepaid meter
Usage $388.65 ea $32.31 ea
Accessories Diesel (Information only, already included in Plant Rates) Petrol (Information only, already included in Plant Rates) 4" wire nails Termite Poison (app rate @ 5ℓ/m² of 5ℓ/95ℓ termicide/water mix) PVC Solvent Cement (100mℓ)
$ $1.07/ℓ $1.18/ℓ $1.75/packet $0.61/ℓ $2.62 ea
3.20_Daniel & Michelle Fisher_Project Package_Rev.0.xlsx Resources|Console Page 5 of 7
78%
18.87% Bill Mark-Up @ 0.00% 2.61% 3.7 Month Timeline 78.52% US$ 83,109.61 Excluding VAT Amount (US$) $ 1 no $ 388.65 1 no $ 32.31
216.35 ℓ 213.05 ℓ 17 packets 3.33 ℓ 1.4 no
$ $ $ $ $
36.14 232.41 251.19 30.41 2.03 3.69
+263 77 192 7337 info@presageprojects.co.zw Presage Projects (Pvt) Ltd © 2020 All Rights Reserved
Conditions of Contract 3rd Edition 1977 (International) Clause 14.1 Program
Created on 6/6/2020 @ 1:09 PM
WBS ID Operation % 1 Daniel & Michelle Fisher_Project Package_Rev.0 2 Mobilisation/Procurement 3 Substructure 3.1 Earthworks 3.1.1 Clear site 3.1.2 Remove turf 3.1.3 Excavate topsoil & cartaway 3.1.4 Excavate trenches 3.1.5 Compact trench bases 3.1.6 Termite treatment to surface of excavations 3.2 Strip Footing 3.2.1 Blinding to trench bases 3.2.2 Pour footing 3.3 Foundation Wall 3.3.1 Build external foundation wall 3.3.2 Build internal foundation walls 3.3.3 Backfill around external wall 3.3.4 Fill foundation with hardcore 3.4 Foundation Slab 3.4.1 Lay DPM 3.4.2 Prepare meshref S193 3.4.3 Pour slab
Complete % Planned 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Start 16-Jun-20 16-Jun-20 18-Jun-20 18-Jun-20 18-Jun-20 27-Jun-20 8-Jul-20 10-Jul-20 12-Jul-20 14-Jul-20 16-Jul-20 16-Jul-20 17-Jul-20 19-Jul-20 19-Jul-20 21-Jul-20 22-Jul-20 23-Jul-20 29-Jul-20 29-Jul-20 30-Jul-20 1-Aug-20
Duration 108 Days 5 days 46 days 27 days 8 days 10 days 1 day 1 day 1 day 1 day 2 days 0 days 1 day 9 days 2 days 1 day 0 days 5 days 5 days 0.10 days 1 day 2 days
Finish 2-Oct-20 21-Jun-20 3-Aug-20 15-Jul-20 26-Jun-20 7-Jul-20 9-Jul-20 11-Jul-20 13-Jul-20 15-Jul-20 18-Jul-20 16-Jul-20 18-Jul-20 28-Jul-20 21-Jul-20 22-Jul-20 22-Jul-20 28-Jul-20 3-Aug-20 29-Jul-20 31-Jul-20 3-Aug-20
4 4.1 4.1.1 4.1.2 4.1.3 4.1.4 4.1.5 4.1.6 4.1.7 4.1.8 4.2 4.2.1 4.2.2 4.3
Superstructure 0.00% Masonry 0.00% Build external walls up to window level 0.00% Build internal walls not exceeding 1.5m high 0.00% Build-in door frames 0.00% Build-in window frames 0.00% Install lintels 0.00% Build internal walls up to wall plate 0.00% Build external walls up to wall plate with air bricks 0.00% Build external walls at gable ends 0.00% Plastering 0.00% Plaster walls internally 0.00% Plaster walls externally 0.00% Roof 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4-Aug-20 4-Aug-20 4-Aug-20 6-Aug-20 4-Aug-20 6-Aug-20 18-Aug-20 11-Aug-20 9-Aug-20 11-Aug-20 12-Aug-20 13-Aug-20 12-Aug-20 10-Aug-20
28 days 14 days 5 days 3 days 7 days 12 days 0 days 1 day 1 day 0 days 21 days 20 days 5 days 22 days
2-Sep-20 19-Aug-20 9-Aug-20 9-Aug-20 11-Aug-20 18-Aug-20 19-Aug-20 12-Aug-20 10-Aug-20 11-Aug-20 2-Sep-20 2-Sep-20 17-Aug-20 2-Sep-20
5 5.1 5.1.1 5.1.2 5.3 5.3.1 5.3.2 5.3.3 5.4 5.4.1 5.4.2
Finishes Wall & Floor Finishes Rhinoset finish on internal walls Rhinoset finish on ceiling Painting Paint internal walls Paint ceiling High gloss paint steel to frames Tiling Wall tiles to bathroom and kitchen Floor tiles to bathroom and kitchen
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
17-Aug-20 27-Aug-20 3-Sep-20 6-Sep-20 17-Aug-20 2-Sep-20 18-Sep-20 17-Aug-20 12-Sep-20 12-Sep-20 18-Sep-20
44 days 34 days 27 days 12 days 36 days 10 days 4 days 0 days 7 days 6 days 1 day
30-Sep-20 30-Sep-20 30-Sep-20 18-Sep-20 22-Sep-20 12-Sep-20 22-Sep-20 17-Aug-20 19-Sep-20 18-Sep-20 19-Sep-20
0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00%
1-Sep-20 4-Aug-20 1-Sep-20 30-Sep-20 30-Sep-20
21 days 34 days 3 days 2 days 2 days
22-Sep-20 7-Sep-20 4-Sep-20 2-Oct-20 2-Oct-20
6 7 8 9 9.1
Fittings and Equipment Services External Works Project Completion Furnish home and move in
31-Mar-20
30-Apr-20
30-May-20
29-Jun-20
16-Jun-20
108 Days
16-Jun-20
5 days
18-Jun-20
29-Jul-20
28-Aug-20
27-Sep-20
26-Dec-20 Duration % Complete
10 days 8-Jul-20
1 days
10-Jul-20
1 days
12-Jul-20
1 days
14-Jul-20
1 days
16-Jul-20
0 days
17-Jul-20
1 days
19-Jul-20
2 days
21-Jul-20
1 days
22-Jul-20
0 days
23-Jul-20
5 days
29-Jul-20
0.10 days
30-Jul-20
1 days
1-Aug-20
2 days
4-Aug-20
28 days
4-Aug-20
14 days
4-Aug-20
5 days
6-Aug-20 4-Aug-20
3 days 7 days
6-Aug-20
12 days 18-Aug-20
11-Aug-20 9-Aug-20
1 days 0 days
12-Aug-20
21 days
13-Aug-20 12-Aug-20 10-Aug-20
0 days
1 days
11-Aug-20
20 days 5 days
22 days
17-Aug-20
44 days
27-Aug-20
34 days
3-Sep-20
27 days
6-Sep-20 17-Aug-20
12 days
36 days
2-Sep-20
10 days 18-Sep-20
17-Aug-20
4-Aug-20
4 days
0 days 12-Sep-20
7 days
12-Sep-20
6 days
18-Sep-20
Page 6 of 7
26-Nov-20
8 days
27-Jun-20
3.20_Daniel & Michelle Fisher_Project Package_Rev.0.xlsx Construction Schedule|Baseline
27-Oct-20
1-Sep-20
21 days
1-Sep-20
3 days
1 days
34 days
30-Sep-20
2 days
30-Sep-20
2 days
+263 77 192 7337 info@presageprojects.co.zw Presage Projects (Pvt) Ltd © 2020 All Rights Reserved
┘
└
Disclaimer Daniel & Michelle Fisher_Project Package_Rev.0 While every care has been exercised in preparing the information contained herein, Presage Projects will not be held responsible for material descripancies that may occure when changes are made to the design without notification, or materials that are procured without following the quantities calculated in this document. We ecourage records of materials received and issued for construction to be kept by Site Security and the Site Agent on behalf of the Client