┘
└
Project Package PROJECT NAME: PROJECT VALUE:
4 Bed_Project Package_Rev.0 US$
117,265.45
PROJECT DURATION:
3.0 Month Timeline
PROJECT LOCATION:
Harare, Zimbabwe
PROJECT BRIEF:
4 Bed House, with floor area of; 424 m²
Summary of basic materials, further details available inside Package Cement 977 bags ¾ Stones 73.2 m³ R/Sand 59.3 m³ Bricks 54,246 bricks P/Sand 61.4 m³ 230 B/Force 54 rolls 115 B/Force 33 rolls 230 DPC 7 rolls 115 DPC 3 rolls
┐
┌
┘
└
Contents Page a) Materials Procurement in Stages …………1 Consists of builders materials in construction stages, from the sub-structure to the superstructure and any waste management system. b) Bill of Quantities | Interface (Summary) …………2 Consists of the summary of a 14 paged Bill of Quantities priced in USD, full version available upon request. c) Resources | Console
…………3
Consists of the Quantity and Monetary Value of Requirements for payment and procurement, which are Man-hours for Labour, Plant-hours for Machines & Equipment and a detailed Material Schedule of Quantities for every item to be installed on site. d) Construction Schedule | Baseline …………6 This document shows the sequence of operations to be executed on site in a safe manner, indicating durations of activities calculated from the measured quantity of work and determined by the productivity expected in each day, and it's linked to the Bill of Quantities.
┐
(i)
┌
NB: Materials shown in Monetary Terms will have to be viewed in the Resources Console For any clarifications, feel free to contact the undersigned Agent for assistance
DWG Ref 4 Bed_Project Package_Rev.0 Materials in Construction Stages Item
Description
Cement
¾ Stones
R/Sand
Bricks
P/Sand
230 B/Force
115 B/Force
230 DPC
115 DPC
others as described
SUBSTRUCTURE (UP TO SLAB) a) b) c) d) e) f)
Clearing & / Setting Out Trench Excavations Blinding Concrete Footing Substructure Brickwork Concrete Slab
g) h) i) j) k) l) m) n) o) p) q) r)
Doors with frame c/w hinges, screws & locksets Windows & Handles c/w nuts, bolts & washer Superstructure Brickwork, Window Level Superstructure Brickwork, Wall Plate Level Ring Beam Plaster External Plaster Internal Rhinoset Paint PVA High Gloss (Steel Frames) Sush Putty (N/A to Aluminium Frames) Wall Plate
s) t) u) v) w)
Roof Trusses (aggregates where gable ends exist) Purlins & Brandering Roof Covering (900 x 2,400 Chromadek) Ceiling & Cornice Rainwater Goods
antkill- 4.6ℓ bags 180 bags 48 bags 296 bags
0.0 m³ 21.2 m³
0.0 m³ 17.2 m³ 10,457 bricks
8.6 m³
11 rolls
6 rolls
7 rolls
3 rolls
35.0 m³ 28.3 m³ SUPER STRUCTURE (UP TO WALL PLATE)
rebar- kgs 300m 339 m² S.193- 23 sheets $ 733.62 $ 4,404.91
113 bags 54 bags 144 bags 27 bags 70 bags
25,584 bricks 13,204 bricks 17.0 m³
20.4 m³ 9.7 m³
25 rolls 12 rolls
19 rolls 9 rolls
13.8 m³
rebar 976 kgs 4.9 m³ 12.5 m³ 69 bags 183 ℓ 7ℓ kgs 117 m
41 bags
ROOF (TRUSSES, COVERING & CEILING) 5,000 bricks
4.9 m³
7 rolls
$ 18,505.29 1,566 m 217 sheets $ 2,131.65 $ 2,362.20
SERVICES (WATER & ELECTRICITY) x) y)
Plumbing & Fittings Electricals & Fittings
Created on 25/6/2020 @ 8:00 PM
Column Totals for Material Headings
$ $ 977 bags
73.2 m³
WASTE MANAGEMENT 59.3 m³ 54,246 bricks
4 Bed_Project Package_Rev.0.xlsx Materials Procurement in Stages Page 1 of 6
61.4 m³
54 rolls
33 rolls
7 rolls
7,040.80 1,329.76
3 rolls
+263 77 192 7337 jeffstar@presageprojects.co.zw Presage Projects (Pvt) Ltd © 2020 All Rights Reserved
RICS NRM 2 Adoption 25/6/2020
PPHBQ2020_Rev.0
DWG Ref 4 Bed_Project Package_Rev.0 Elemental Bill of Quantities Item №
Pay Ref
$
Bill Description
Unit
Quantity
Rate (US$)
-
Amount (US$)
Quick Stats building $/m² =$296.09/m²
Summary
building $/m³ =$95.51/m³ 0.00% $
Bill No. 1 Preliminaries (Main Contract)
-
Bill No. 2 Substructure
15.40% $
15,467.69
Bill No. 3 Superstructure
60.45% $
60,699.54
Bill No. 4 Finishes
6.87% $
6,899.88
Bill No. 5 Fittings, Furnishings and Equipment
7.76% $
7,796.37
Bill No. 6 Services
9.50% $
9,543.62
Bill No. 7 External Works
0.00% $
-
Subtotal
$
100,407.10
Plus 2.00% Contingency Sum
$
2,008.14
Subtotal
$
102,415.24
Add Vat @ 14.50%
$
14,850.21
Total Amount
$
117,265.45
4 Bed_Project Package_Rev.0.xlsx Bill of Quantities|Interface Page 2 of 6
+263 77 192 7337 jeffstar@presageprojects.co.zw Presage Projects (Pvt) Ltd © 2020 All Rights Reserved
┌
Created on 25/6/2020 @ 8:00 PM┐
Confidential Resource Usage
DWG Ref 4 Bed_Project Package_Rev.0 Bill of Resources Cost Code L L01 L03 L04 L05 L06 L07 L09 L14 L16 L17
Resource Description Payroll Budget Information @ 9 Man-hours/Day General Hand Carpenter (C) Builder (B) Painter (T) Steel Fixer (X) Glazier (G) Electrician (E) Plumber (P) Light Plant/Equipment Operator (L) Heavy Plant Operator (H)
P F01 P02 P03 P04 P16 P17 P18 P19 M BM
Plant Hire Hours @ 8 Plant-hours/Day Diesel (Information only, already included in Plant Rates) 140H Grader (b) 3CX TLB (c) Plate Compactor (d) 750/500 Concrete Mixer (n) Concrete Dumper (o) Concrete Vibrator Set (p) Power Trowel Machine (q) Bill of Materials (BoM) Procurement Building Materials Cements Tile Adhesive (20kg) Tile Grout (5kg) 32,5 (PC 15) Cement Aggregates 19mm Stone Washed Riversand (Cash - Pre-Payment at the Quarry) Pitsand Rhino Products Rhinoset Masonry Beta Common Bricks Cement air bricks/vents (pair) Window Cills Galvanised wall ties Reinforcement Deformed Reinforcement Bars (Cut & Bent) Tying Wire 1.6mm ø MeshRef S193 Brickforce 230 (@ every 4th course) Brickforce 115 (@ every 4th course) Shuttering Formwork for lintels Moisture Protection DPC 2 Ply 230 DPC 2 Ply 115 Polythene Sheets (2Ply) Paints & Products Dulux Universal Undercoat Dulux Int - Ext PVA White Dulux Ceiling White Dulux Steel Prime Dulux Gloss White Dulux Pink Wood Primer Dulux Tinters (Shelf price selling @ $5.00/50ml tube) Door Frames Standard 230 single door frame Standard 115 single door frame
CMT01 CMT02 CMT04 BM003 BM004 BM005 RP01 MAS01 MAS06 MAS07 MAS08 RNF01 RNF02 RNF03 RNF06 RNF07 SH01 MP01 MP02 MP03 DP01 DP02 DP03 DP04 DP05 DP06 DP10 DF03 DF04 No No AWF01 AWF02 AWF03 AWF04 AWF05 AWF06 AWF07 AWF08 AWF09 AWF10 AWF11
DR02 DR03 SWD01 SWD02 TT01 J01 J02 J03 J04 J07 IM01 IM05 IM06
18.05% Bill Mark-Up @ 0.00% ≡ 2.43% 3.0 Month Timeline ≡ 79.52% US$ 100,407.10 80% 1 0 Excluding VAT Cost Usage Amount (US$) (All in Labour Rates) 10,064.0 hours $ 18,123.06 $ 1.57/hour 7,628.8 hours $ 11,992.80 $ 2.50/hour 319.5 hours $ 800.01 $ 2.50/hour 1,563.0 hours $ 3,913.29 $ 2.50/hour 155.0 hours $ 388.05 $ 2.50/hour 10.2 hours $ 25.54 $ 2.50/hour 01.4 hours $ 3.55 $ 2.50/hour 97.2 hours $ 243.42 $ 2.50/hour 225.4 hours $ 564.32 $ 2.85/hour 51.6 hours $ 147.13 $ 3.78/hour 11.9 hours $ 44.95 18% 2%
(Plant Charges) $ 1.13/ℓ $ 71.81/hour $ 32.74/hour $ 7.93/hour $ 29.66/hour $ 23.77/hour $ 4.06/hour $ 18.78/hour (Material Costs)
105.9 hours 497.84 ℓ 4.5 hours 5.5 hours 2.2 hours 34.1 hours 21.9 hours 21.9 hours 15.7 hours Order Quantity
$ $ $ $ $ $ $ $ $ $
$ $
2,440.60 561.54 325.89 180.04 17.83 1,012.83 520.76 88.89 294.37 79,843.44 79,795.57 9,610.96 144.65 51.50 9,414.81 4,925.28 2,558.07 1,294.26 1,072.94 910.03 910.03 8,822.19 8,527.71 35.37 250.48 8.63 5,367.70 3,409.60 4.01 1,776.97 118.93 58.18 96.72 96.72 177.21 23.34 5.79 148.08 980.42 468.65 346.08 88.85 20.03 19.66 15.34 21.82 200.87 52.40 148.47
$ $ $ $ $ $ $ $ $ $ $
4,375.22 709.24 661.96 315.22 141.85 630.43 23.64 401.90 204.89 94.57 964.57 226.96
$ $ $5.24/sack $5.24/sack $9.78/sack
27.60 bags 9.83 bags 962 bags
$ $ $ $
$34.93/m³ $21.83/m³ $17.47/m³
73.2 m³ 59.3 m³ 61.4 m³
$ $ $ $
$13.10/sack
69 bags
$ $
$0.16/brick $0.66 ea $0.87 ea $0.17 ea
54,246 bricks 54 no 287 cills 49 no
$ $ $ $ $
$3,493.45/ton $2.36/kg $5.24/m² $2.18/roll $1.75/roll
0.976 tons 1.70 kgs 339 m² 54 rolls 33 rolls
$ $ $ $ $ $
$3.93/m
25 m
$ $
$3.49/roll $1.75/roll $0.22/m²
7 rolls 3 rolls 678 m²
$ $ $ $
$5.68/ℓ $5.24/ℓ $2.62/ℓ $9.61/ℓ $10.48/ℓ $5.68/ℓ $87.34/ℓ
83 66 34 2.1 1.9 2.7 0.25
$ $ $ $ $ $ $
ℓ ℓ ℓ ℓ ℓ ℓ ℓ $
$26.20 ea $14.85 ea
Yes Yes Aluminium Window Frames 2500×1800 1750×1200 1000×1000 1000×900 2000×1000 1000×150 1700×1500 1300×1000 600×1000 1700×1200 600×1200
1st Choice/Option $709.24 $330.98 $157.61 $141.85 $315.22 $23.64 $401.90 $204.89 $94.57 $321.52 $113.48
US$ ea ea ea ea ea ea ea ea ea ea ea
Doors Solid standard single door to suit frame $87.34 ea Hollow standard single door to suit frame $17.47 ea Sliding Doors Double Sliding Doors $209.61 ea Single sliding doors $174.67 ea Trusses Roof Trusses to detail $749.20 ea Joinery 114mm × 38mm sw wall plate $4.37/m 38mm × 38mm sw purlins $2.62/m 38mm × 38mm sw brandering $0.87/m 9mm Plaster Board Ceiling (Supply Dimension - 2.4m × 1.2m) $4.80/m² Rhinocove Cornice $1.31/m Iron Mongery Locksets 3 Lever $13.97 ea Hinges c.w. screws for doors $1.31 ea 4 Bed_Project Package_Rev.0.xlsx Window handle c/w nut, bolt & washer $1.75 ea Resources|Console Page 3 of 6
2 no 10 no
540.00 1 no 2 no 2 no 1 no 2 no 1 no 1 no 1 no 1 no 3 no 2 no
$
$ 2 no 10 no
$ $ $
5 no 1 no
$ $ $
25 no
$ $
117 m 604 m 962 m 339.1 m² 384 m
$ $ $ $ $ $
12 sets 12 no 17 no
$ $ $
349.34 174.67 174.67 1,222.71 1,048.03 174.67 18,505.29 18,505.29 5,068.29 512.93 1,583.48 840.23 1,628.89 502.76 213.10 167.69 15.72 29.69 +263 77 192 7337 info@presageprojects.co.zw Presage Projects (Pvt) Ltd © 2020 All Rights Reserved
┌
Created on 25/6/2020 @ 8:00 PM┐
Confidential Resource Usage
DWG Ref 4 Bed_Project Package_Rev.0 Bill of Resources
18% 2%
≡ ≡ 1
Cost Code RG03 RG07 RG10 RG11 RG12 RG13 RG14 KF01 KF03 KF04
HVAC02
Resource Description Rainwater Goods PVC Rainwater Gutters ½ round 125 × 87 Rainwater Downpipe 80mm Drip stones 0.9 x 2.4 Chromadek Roof Sheets Concrete Roof Tiles 25mm × 220mm sw Fascia Galvanised Roof Ridge Galvanised Valley Kitchen Fittings Kitchen sink 1.2m drop in Cupboards under sink Cupboards on walls
TL01 TL02
PCI01 PCI02
Pre-Cast Items Double Cam Concrete Sink Pre-cast lintels
PVCSP01 PVCSP02 GP01 CP01 GF01 GF02 GF03 GF04 GF05 CF01 CF02 CF03 PVCFT01 PVCFT02 PVCFT03 PVCFT04 PVCFT05 PVCFT06 PVCFT07 PVCFT08 PVCFT09 TM01 TM02 TM06 RF01 WMS01
CN01 CNF01 CNF02 CB02 CB05 SW01 SW04 ST01 ST02 ST03 ST04 ST05 ST07 B01 B02 EMS01 EMS02 EMS04
Cost
$61.14 ea $1353.71 ea $1222.71 ea
$ $56.77 ea
3 no
170.31 170.31
$ $
$52.40 $22.71 $78.60 $34.93 $131.00 $65.50 $4.37
ea ea ea ea ea ea ea
3 3 3 3 3 1 1
no no no no no no no
1,028.82 157.21 68.12 235.81 104.80 393.01 65.50 4.37 867.92 134.83 733.09
$ $ $ $ $ $ $ $
$1.89 ea $0.63 ea
71 no 1,166 no
$ $ $
$78.60 ea $1.75/m
Plumbing PVC Sewer Pipes ø110mm sewer pipe ø60mm sewer pipe Galvanised Pipes ø20mm GI pipe Copper Pipes ø20mm copper pipe Galvanised Fittings ø20mm Gi elbow ø20mm Gi tee ø20mm Gi sleeve ø35mm brass p-trap for bath ø35mm Gate Valve Copper Fittings ø20mm copper elbow ø20mm copper tee ø20mm copper sleeve PVC Fittings ø160mm to ø110mm reducer ø110mm x 90° bend ø110mm x 45° bend ø110mm equal tees ø110mm end caps ø110mm p-trap ø110mm sieve ø110mm × 2m pvc vent pipe ø110mm fly trap over vent pipe Taps & Mixers ø15mm basin taps (Cobra) Sink Mixer ø35mm brass tap Rubber Fittings ø35mm rubber p-trap Water Main Supply ZINWA flow meter Electricals Conduits ø19mm pvc conduit Conduit Fittings ø20mm pvc sleeve Junction box (6 × 6) Cables 2.5mm² triple core copper conductors armoured cable Switches Single gang switch Cooker switch Sockets single electric socket double electric socket Cooker terminal Shaver socket Lamp holder (Brass) Fluorescent socket Bulbs/Lights Bulkhead c/w gland seal Osram 11watt fluorescent bulb Electrical Main Supply 3 Phase meter board Generator/Solar change over switch Distribution board 16 Way c/w Breakers
80%
Usage $4.37/m $3.91/m $13.10 ea $7.42 ea $10.48/m $5.24/m $3.50/m
HVAC Ceiling fan Bathroom Fittings Wall mounted cabinet with mirror Towel rack Water Closet Ceramic wash basin & pedestal Shower Cubicle 950 × 950 × 2000mm corner type Bath tub (Acrylic) Ceramic Soap Dish Tiles Floor tiles 600 x 600 Wall tiles 600 x 200
BF01 BF02 BF03 BF09 BF10 BF11 BF13
0
18.05% Bill Mark-Up @ 0.00% 2.43% 3.0 Month Timeline 79.52% US$ 100,407.10 Excluding VAT Amount (US$) $ 3,973.66 123 m $ 536.26 25 m $ 97.04 8 no $ 104.80 217 no $ 1,611.46 123 m $ 1,287.03 52 m $ 274.06 18 m $ 63.00 $ 3,860.26 1 no $ 61.14 1 no $ 1,353.71 2 no $ 2,445.41
1 no 25 m
$ $ $ $
$9.61/m $1.75/m
18 m 11 m
$ $ $
$21.83/m
78 m
$ $
$21.83/m
78 m
$ $
$7.86 $14.85 $13.10 $3.49 $4.80
ea ea ea ea ea
24 24 24 4 11
no no no no no
$ $ $ $ $ $
$8.73 ea $16.59 ea $14.85 ea
24 no 24 no 24 no
$ $ $ $
$31.44 $31.70 $34.93 $17.47 $4.37 $30.57 $5.24 $7.42 $2.18
ea ea ea ea ea ea ea ea ea
1 10 10 10 1 10 10 3 3
no no no no no no no no no
$ $ $ $ $ $ $ $ $ $
$6.99 ea $48.03 ea $4.37 ea
10 no 1 no 2 no
$ $ $ $
$1.75 ea
4 no
$ $
$33.19 ea
1 no
$ $ $
$1.75/m
120 m
$ $
$0.44 ea $0.87 ea
60 no 23 no
$ $ $
$0.26/m $3.49/m
360 m 40 m
$ $ $
$1.92 ea $8.73 ea
23 no 1 no
$ $ $
$2.62 $5.24 $30.57 $3.06 $1.75 $4.80
ea ea ea ea ea ea
23 8 1 2 23 4
no no no no no no
$ $ $ $ $ $ $
$6.99 ea $3.06 ea
2 no 23 no
$ $ $
$34.93 ea $48.03 ea 4 Bed_Project Package_Rev.0.xlsx $388.65 ea Resources|Console Page 4 of 6
1 no 1 no 1 no
$ $ $
121.59 78.60 42.99 7,040.80 192.14 172.93 19.21 1,703.06 1,703.06 1,703.06 1,703.06 926.20 188.65 356.33 314.41 13.97 52.84 964.19 209.61 398.25 356.33 1,263.76 31.44 317.03 349.34 174.67 4.37 305.68 52.40 22.27 6.55 126.64 69.87 48.03 8.73 6.99 6.99 33.19 33.19 1,329.76 209.87 209.87 46.32 26.23 20.09 234.18 94.44 139.74 52.93 44.19 8.73 198.25 60.26 41.92 30.57 6.11 40.17 19.21 84.28 13.97 70.31 503.93 34.93 48.03 388.65 +263 77 192 7337 info@presageprojects.co.zw Presage Projects (Pvt) Ltd © 2020 All Rights Reserved
┌
Created on 25/6/2020 @ 8:00 PM┐
Confidential Resource Usage
DWG Ref 4 Bed_Project Package_Rev.0 Bill of Resources
≡ ≡ 1
Cost Code EMS05
GT02 ACC ACC01 ACC02 ACC03 ACC08 ACC11
18% 2%
Resource Description ZETDC Prepaid meter
0 Cost
80%
Usage $32.31 ea
Gates Lazyman Door
18.05% Bill Mark-Up @ 0.00% 2.43% 3.0 Month Timeline 79.52% US$ 100,407.10 Excluding VAT Amount (US$) 1 no $ 32.31 $
$349.34 ea
Accessories Diesel (Information only, already included in Plant Rates) Petrol (Information only, already included in Plant Rates) 4" wire nails Termite Poison (app rate @ 5ℓ/m² of 5ℓ/95ℓ termicide/water mix) PVC Solvent Cement (100mℓ)
$ $1.07/ℓ $1.18/ℓ $1.75/packet $0.61/ℓ $2.62 ea
4 Bed_Project Package_Rev.0.xlsx Resources|Console Page 5 of 6
2 no $
273.51 ℓ 224.33 ℓ 24 packets 4.62 ℓ 1.4 no
$ $ $ $ $
698.69 698.69 47.87 293.81 264.50 41.35 2.83 3.69
+263 77 192 7337 info@presageprojects.co.zw Presage Projects (Pvt) Ltd © 2020 All Rights Reserved
Conditions of Contract 3rd Edition 1977 (International) Clause 14.1 Program
Created on 25/6/2020 @ 8:00 PM
WBS ID Operation % Complete % Planned 1 4 Bed_Project Package_Rev.0 0.00% 0.00% 2 Mobilisation/Procurement 0.00% 0.00% 2.1 Mobilise cabin and security fence c/w gate to site 0.00% 0.00% 2.2 Set-up temporary perimeter security 0.00% 0.00% 2.3 Set-up storeroom on site 0.00% 0.00% 2.4 Procure cement and aggregates 0.00% 0.00% 2.5 Mobilise tools and small equipment 0.00% 0.00% 3 Substructure 0.00% 0.00% 3.1 Earthworks 0.00% 0.00% 3.1.1 Clear site 0.00% 0.00% 3.1.2 Remove turf 0.00% 0.00% 3.1.3 Excavate topsoil & cartaway 0.00% 0.00% 3.1.4 Excavate trenches 0.00% 0.00% 3.1.5 Compact trench bases 0.00% 0.00% 3.2 Strip Footing 0.00% 0.00% 3.2.2 Pour footing 0.00% 0.00% 3.3 Foundation Wall 0.00% 0.00% 3.3.1 Build external foundation wall 0.00% 0.00% 3.3.2 Build internal foundation walls 0.00% 0.00% 3.3.4 Fill foundation with hardcore 0.00% 0.00% 3.4 Foundation Slab 0.00% 0.00% 4 4.1 4.1.1 4.1.2 4.1.3 4.1.4 4.1.6 4.1.7 4.2 4.2.1 4.2.2 4.3 4.3.2 4.3.5 4.3.6 4.3.7 4.3.10
Superstructure 0.00% Masonry 0.00% Build external walls up to window level 0.00% Build internal walls not exceeding 1.5m high 0.00% Build-in door frames 0.00% Build-in window frames 0.00% Build internal walls up to wall plate 0.00% Build external walls up to wall plate with air bricks 0.00% Plastering 0.00% Plaster walls internally 0.00% Plaster walls externally 0.00% Roof 0.00% Supply and fix trusses by specialist 0.00% Install roof covering 0.00% Fix ridge on roof 0.00% Install ceiling 0.00% Fix gutters 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Start 5-Jul-20 5-Jul-20 5-Jul-20 7-Jul-20 7-Jul-20 7-Jul-20 9-Jul-20 7-Jul-20 7-Jul-20 7-Jul-20 9-Jul-20 11-Jul-20 13-Jul-20 15-Jul-20 19-Jul-20 20-Jul-20 23-Jul-20 23-Jul-20 25-Jul-20 29-Jul-20 5-Aug-20
Duration 88 Days 5 days 1 day 2 days 1 day 2 days 1 day 34 days 11 days 1 day 1 day 1 day 1 day 1 day 3 days 2 days 11 days 3 days 1 day 6 days 5 days
Finish 1-Oct-20 10-Jul-20 6-Jul-20 9-Jul-20 8-Jul-20 9-Jul-20 10-Jul-20 10-Aug-20 18-Jul-20 8-Jul-20 10-Jul-20 12-Jul-20 14-Jul-20 16-Jul-20 22-Jul-20 22-Jul-20 4-Aug-20 26-Jul-20 26-Jul-20 4-Aug-20 10-Aug-20
11-Aug-20 11-Aug-20 11-Aug-20 13-Aug-20 11-Aug-20 13-Aug-20 18-Aug-20 16-Aug-20 20-Aug-20 20-Aug-20 21-Aug-20 18-Aug-20 19-Aug-20 1-Sep-20 5-Sep-20 1-Sep-20 6-Sep-20
32 days 21 days 7 days 3 days 7 days 19 days 1 day 2 days 21 days 21 days 8 days 25 days 6 days 3 days 4 days 11 days 4 days
12-Sep-20 1-Sep-20 18-Aug-20 16-Aug-20 18-Aug-20 1-Sep-20 19-Aug-20 18-Aug-20 10-Sep-20 10-Sep-20 29-Aug-20 12-Sep-20 25-Aug-20 4-Sep-20 9-Sep-20 12-Sep-20 10-Sep-20
30-May-20
29-Jun-20
29-Jul-20
28-Aug-20
27-Sep-20
5-Jul-20
88 Days
5-Jul-20
5 days
Duration
5-Jul-20
1 days
% Complete
7-Jul-20
2 days
7-Jul-20
1 days
7-Jul-20
2 days
9-Jul-20 7-Jul-20
1 days
1 days
9-Jul-20
1 days
11-Jul-20
1 days
13-Jul-20
1 days
15-Jul-20
1 days
20-Jul-20
2 days
23-Jul-20
3 days
25-Jul-20
1 days
29-Jul-20
6 days
11-Aug-20
32 days
11-Aug-20
21 days
11-Aug-20
7 days
13-Aug-20 11-Aug-20
3 days
7 days
13-Aug-20
19 days
18-Aug-20 16-Aug-20
1 days
2 days
20-Aug-20
21 days
20-Aug-20
21 days
21-Aug-20 18-Aug-20 19-Aug-20
8 days
25 days 6 days 1-Sep-20
3 days
5-Sep-20 1-Sep-20
6 6.1 6.2 6.4 6.6 6.7 6.8 6.9 7 7.3 7.4 7.5 7.6 7.7 8 9 9.1
Finishes Wall & Floor Finishes Rhinoset finish on internal walls Rhinoset finish on ceiling Painting Paint internal walls Paint ceiling Tiling Wall tiles to bathrooms and kitchen Fittings and Equipment Fit doors Locksets & window handles Install water closet for bathroom Install wash basin for bathroom Fix bathroom cabinet and towel rack Install kitchen sink complete with mixer Install kitchen cupboards Services Fix PVC sewer piping including all fittings Test and commission all pipes Installation of flex conduits and cables Installation of electrical fittings Test and commission electrical installations External Works Project Completion Furnish & Commission Building
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
29-Aug-20 4-Sep-20 11-Sep-20 14-Sep-20 29-Aug-20 10-Sep-20 23-Sep-20 21-Sep-20 21-Sep-20
32 days 21 days 14 days 10 days 32 days 11 days 6 days 7 days 6 days
29-Sep-20 24-Sep-20 24-Sep-20 23-Sep-20 29-Sep-20 21-Sep-20 29-Sep-20 28-Sep-20 27-Sep-20
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
10-Sep-20 21-Sep-20 23-Sep-20 11-Sep-20 12-Sep-20 13-Sep-20 12-Sep-20 21-Sep-20 11-Aug-20 11-Aug-20 13-Aug-20 5-Sep-20 6-Sep-20 14-Sep-20 10-Sep-20 29-Sep-20 29-Sep-20
20 days 2 days 1 day 1 day 1 day 1 day 1 day 1 day 35 days 1 day 1 day 1 day 7 days 1 day 2 days 2 days 2 days
29-Sep-20 23-Sep-20 24-Sep-20 12-Sep-20 13-Sep-20 14-Sep-20 13-Sep-20 22-Sep-20 15-Sep-20 12-Aug-20 14-Aug-20 6-Sep-20 13-Sep-20 15-Sep-20 12-Sep-20 1-Oct-20 1-Oct-20
4 days
11 days
6-Sep-20
29-Aug-20
4 days
32 days 4-Sep-20
5 5.1 5.1.1 5.1.2 5.3 5.3.1 5.3.2 5.4 5.4.1
21 days 11-Sep-20
14 days
14-Sep-20 29-Aug-20
10 days
32 days 10-Sep-20
11 days 23-Sep-20
10-Sep-20
7 days
21-Sep-20
6 days
20 days 2 days
23-Sep-20 11-Sep-20
1 days
13-Sep-20 12-Sep-20
1 days 1 days 21-Sep-20
35 days
11-Aug-20
1 days
13-Aug-20
1 days
1 days 5-Sep-20 6-Sep-20
1 days 7 days 14-Sep-20
10-Sep-20
Page 6 of 6
1 days
1 days
12-Sep-20
11-Aug-20
6 days
21-Sep-20
21-Sep-20
4 Bed_Project Package_Rev.0.xlsx Construction Schedule|Baseline
27-Oct-20
1 days
2 days 29-Sep-20
2 days
29-Sep-20
2 days
+263 77 192 7337 info@presageprojects.co.zw Presage Projects (Pvt) Ltd Š 2020 All Rights Reserved
┘
└
Special Note 4 Bed_Project Package_Rev.0 While every care has been exercised in preparing the information contained herein, Presage Projects will not be held responsible for material discrepancies that may occur when changes are made to the design without notification, or materials that are procured without following the quantities calculated in this document. We encourage records of materials received and issued for construction to be kept by Site Security and the Site Agent on behalf of the Client
+263 77 192 7337 Presage Projects P/L info@presageprojects.co.zw Central Business District, Harare, Zimbabwe © 2020 All Rights Reserved
┐
┌