Project Package PROJECT NAME: PROJECT VALUE:
S Shaped Classroom Block_Project Package_Crazy_Architecturee_Rev.0
US$
222,677.28
PROJECT DURATION:
5.2 Month Timeline
PROJECT LOCATION:
Harare, Zimbabwe
PROJECT BRIEF:
S Shaped Classroom Block, with floor area of; 1,125 m²
Summary of basic materials, further details available inside Package Cement 2,301 bags ¾ Stones 165.0 m³ R/Sand 133.5 m³ Bricks 148,835 bricks P/Sand 161.8 m³ 230 B/Force 174 rolls 115 B/Force 45 rolls 230 DPC 20 rolls 115 DPC 5 rolls
┐
┌
┘
└
Contents Page a) Materials Procurement in Stages …………1 Consists of builders materials in construction stages, from the sub-structure to the superstructure and any waste management system. b) Bill of Quantities | Interface (Summary) …………2 Consists of the summary of a 14 paged Bill of Quantities priced in USD, full version available upon request. c) Resources | Console
…………3
Consists of the Quantity and Monetary Value of Requirements for payment and procurement, which are Man-hours for Labour, Plant-hours for Machines & Equipment and a detailed Material Schedule of Quantities for every item to be installed on site. d) Construction Schedule | Baseline …………6 This document shows the sequence of operations to be executed on site in a safe manner, indicating durations of activities calculated from the measured quantity of work and determined by the productivity expected in each day, and it's linked to the Bill of Quantities.
┐
(i)
┌
NB: Materials shown in Monetary Terms will have to be viewed in the Resources Console For any clarifications, feel free to contact the undersigned Agent for assistance
DWG Ref - IG S Shaped Classroom Block_Project Package_Crazy_Architecturee_Rev.0 Materials in Construction Stages Item
Description
Cement
¾ Stones
R/Sand
Bricks
P/Sand
230 B/Force
115 B/Force
230 DPC
115 DPC
others as described
SUBSTRUCTURE (UP TO SLAB) a) b) c) d) e) f)
Clearing & / Setting Out Trench Excavations Blinding Concrete Footing Substructure Brickwork Concrete Slab
g) h) i) j) k) l) m) n) o) p) q) r)
Doors with frame c/w hinges, screws & locksets Windows & Handles c/w nuts, bolts & washer Superstructure Brickwork, Window Level Superstructure Brickwork, Wall Plate Level Ring Beam Plaster External Plaster Internal Rhinoset Paint PVA High Gloss (Steel Frames) Sush Putty (N/A to Aluminium Frames) Wall Plate
s) t) u) v) w)
Roof Trusses (aggregates where gable ends exist) Purlins & Brandering Roof Covering (900 x 2,400 Chromadek) Ceiling & Cornice Rainwater Goods
antkill- 12.4ℓ bags 465 bags 135 bags 701 bags
0.0 m³ 54.9 m³
0.0 m³ 44.4 m³ 28,981 bricks
24.4 m³
34 rolls
9 rolls
20 rolls
5 rolls
82.8 m³ 67.0 m³ SUPER STRUCTURE (UP TO WALL PLATE)
rebar- kgs 300m 918 m² S.193- 62 sheets $ 5,572.93 $ 651.78
424 bags 121 bags 231 bags 46 bags 162 bags
90,711 bricks 27,757 bricks 27.3 m³
76.3 m³ 21.8 m³
107 rolls 31 rolls
28 rolls 8 rolls
22.1 m³
rebar 1,569 kgs 8.4 m³ 29.2 m³ 171 bags 434 ℓ 10 ℓ kgs 212 m
11 bags
ROOF (TRUSSES, COVERING & CEILING) 1,386 bricks
1.4 m³
2 rolls
$ 19,328.17 3,840 m 557 sheets $ 5,502.93 $ 3,811.65
SERVICES (WATER & ELECTRICITY) x) y) z)
Plumbing & Fittings Electricals & Fittings Septic Tank Column Totals for Material Headings
Created on 23/6/2020 @ 8:48 PM
$ 12,766.14 $ 2,658.21 bags 2,301 bags
0.0 m³ 165.0 m³
WASTE MANAGEMENT 0.0 m³ bricks 133.5 m³ 148,835 bricks
S Shaped Classroom Block_Project Package_Crazy_Architecturee_Rev.0.xlsx Materials Procurement in Stages Page 1 of 5
0.0 m³ 161.8 m³
rolls 174 rolls
300m 12.5 m² 45 rolls
20 rolls
5 rolls
+263 77 192 7337 jeffstar@presageprojects.co.zw Presage Projects (Pvt) Ltd © 2020 All Rights Reserved
RICS NRM 2 Adoption 23/6/2020
PPHBQ2020_Rev.0
DWG Ref - IG S Shaped Classroom Block_Project Package_Crazy_Architecturee_Rev.0 Elemental Bill of Quantities Item №
Pay Ref
Bill Description
$ Unit
Quantity
Rate (US$)
-
Amount (US$)
Quick Stats building $/m² =$207.79/m²
Summary
building $/m³ =$76.96/m³ 0.00% $
Bill No. 1 Preliminaries (Main Contract)
-
Bill No. 2 Substructure
20.75% $
39,568.87
Bill No. 3 Superstructure
58.39% $
111,326.13
Bill No. 4 Finishes
8.37% $
15,966.09
Bill No. 5 Fittings, Furnishings and Equipment
2.89% $
5,515.10
Bill No. 6 Services
9.59% $
18,288.49
Bill No. 7 External Works
0.00% $
-
Subtotal
$
190,664.68
Plus 2.00% Contingency Sum
$
3,813.29
Subtotal
$
194,477.98
Add Vat @ 14.50%
$
28,199.31
Total Amount
$
222,677.28
S Shaped Classroom Block_Project Package_Crazy_Architecturee_Rev.0.xlsx Bill of Quantities|Interface Page 2 of 5
+263 77 192 7337 jeffstar@presageprojects.co.zw Presage Projects (Pvt) Ltd © 2020 All Rights Reserved
┌
Created on 23/6/2020 @ 8:48 PM┐
Confidential Resource Usage
DWG Ref - IG S Shaped Classroom Block_Project Package_Crazy_Architecturee_Rev.0 Bill of Resources Cost Code L L01 L03 L04 L05 L06 L07 L09 L14 L16 L17
Resource Description Payroll Budget Information @ 9 Man-hours/Day General Hand Carpenter (C) Builder (B) Painter (T) Steel Fixer (X) Glazier (G) Electrician (E) Plumber (P) Light Plant/Equipment Operator (L) Heavy Plant Operator (H)
P F01 P02 P03 P04 P16 P17 P18 P19 M BM
Plant Hire Hours @ 8 Plant-hours/Day Diesel (Information only, already included in Plant Rates) 140H Grader (b) 3CX TLB (c) Plate Compactor (d) 750/500 Concrete Mixer (n) Concrete Dumper (o) Concrete Vibrator Set (p) Power Trowel Machine (q) Bill of Materials (BoM) Procurement Building Materials Cements Tile Adhesive (20kg) Tile Grout (5kg) 32,5 (PC 15) Cement Aggregates 19mm Stone Washed Riversand (Cash - Pre-Payment at the Quarry) Pitsand Rhino Products Rhinoset Masonry Beta Common Bricks Cement air bricks/vents (pair) Window Cills Galvanised wall ties Reinforcement Deformed Reinforcement Bars (Cut & Bent) Tying Wire 1.6mm ø MeshRef S193 Brickforce 230 (@ every 4th course) Brickforce 115 (@ every 4th course) Shuttering Formwork for lintels Moisture Protection DPC 2 Ply 230 DPC 2 Ply 115 Polythene Sheets (2Ply) Paints & Products Dulux Universal Undercoat Dulux Int - Ext PVA White Dulux Ceiling White Dulux Steel Prime Dulux Gloss White Dulux Pink Wood Primer Dulux Tinters (Shelf price selling @ $5.00/50ml tube) Door Frames Standard 230 swivle door frame Standard 115 single door frame
CMT01 CMT02 CMT04 BM003 BM004 BM005 RP01 MAS01 MAS06 MAS07 MAS08 RNF01 RNF02 RNF03 RNF06 RNF07 SH01 MP01 MP02 MP03 DP01 DP02 DP03 DP04 DP05 DP06 DP10 DF02 DF04 No No AWF01 AWF02 AWF03
DR03 TT01 J01 J02 J03 J04 J07 IM01 IM05 IM06 RG03 RG07 RG10 RG11 RG12 RG13 KF01 KF03 KF04
21.97% Bill Mark-Up @ 0.00% ≡ 3.23% 5.2 Month Timeline ≡ 74.80% US$ 190,664.68 75% 1 0 Excluding VAT Cost Usage Amount (US$) (All in Labour Rates) 23,271.0 hours $ 41,895.19 $ 1.57/hour 17,679.8 hours $ 27,793.53 $ 2.50/hour 781.2 hours $ 1,955.96 $ 2.50/hour 3,649.3 hours $ 9,136.46 $ 2.50/hour 373.8 hours $ 935.76 $ 2.50/hour 27.6 hours $ 69.02 $ 2.50/hour 00.4 hours $ 1.04 $ 2.50/hour 244.4 hours $ 611.85 $ 2.50/hour 342.7 hours $ 858.05 $ 2.85/hour 125.5 hours $ 358.18 $ 3.78/hour 46.3 hours $ 175.33 22% 3%
(Plant Charges) $ 1.13/ℓ $ 71.81/hour $ 32.74/hour $ 7.93/hour $ 29.66/hour $ 23.77/hour $ 4.06/hour $ 18.78/hour (Material Costs)
255.6 hours 1,251.55 ℓ 11.9 hours 28.0 hours 5.8 hours 78.7 hours 47.1 hours 47.1 hours 37.1 hours Order Quantity
$ $ $ $ $ $ $ $ $ $
$ $
6,155.53 1,411.68 851.51 915.53 46.03 2,334.84 1,119.92 191.15 696.54 142,613.96 142,497.84 22,957.68 354.72 126.28 22,476.68 11,508.81 5,763.07 2,915.84 2,829.91 2,236.65 2,236.65 23,486.86 23,397.68 13.10 44.02 32.06 10,757.79 5,480.35 10.84 4,808.38 380.04 78.18 64.51 64.51 481.44 71.29 9.45 400.70 2,249.76 1,077.88 795.98 240.42 28.24 27.73 26.31 53.20 4,983.41 4,716.16 267.25
$ $ $
643.04 283.70 189.13 170.22
$ $ $5.24/sack $5.24/sack $9.78/sack
67.69 bags 24.10 bags 2,298 bags
$ $ $ $
$34.93/m³ $21.83/m³ $17.47/m³
165.0 m³ 133.5 m³ 162.0 m³
$ $ $ $
$13.10/sack
171 bags
$ $
$0.16/brick $0.66 ea $0.87 ea $0.17 ea
148,835 bricks 20 no 50 cills 184 no
$ $ $ $ $
$3,493.45/ton $2.36/kg $5.24/m² $2.18/roll $1.75/roll
1.569 tons 4.60 kgs 918 m² 174 rolls 45 rolls
$ $ $ $ $ $
$3.93/m
16 m
$ $
$3.49/roll $1.75/roll $0.22/m²
20 rolls 5 rolls 1,835 m²
$ $ $ $
$5.68/ℓ $5.24/ℓ $2.62/ℓ $9.61/ℓ $10.48/ℓ $5.68/ℓ $87.34/ℓ
190 152 92 2.9 2.6 4.6 0.61
$ $ $ $ $ $ $
ℓ ℓ ℓ ℓ ℓ ℓ ℓ $
$65.50 ea $14.85 ea
Yes Yes Aluminium Window Frames 1000×900 1000×1200 600×900
1st Choice/Option US$ $141.85 ea $189.13 ea $85.11 ea
Doors Hollow standard single door to suit frame Trusses Roof Trusses to detail Joinery 114mm × 38mm sw wall plate 38mm × 38mm sw purlins 38mm × 38mm sw brandering 9mm Plaster Board Ceiling (Supply Dimension - 2.4m × 1.2m) Rhinocove Cornice Iron Mongery Locksets 3 Lever Hinges c.w. screws for doors Window handle c/w nut, bolt & washer Rainwater Goods PVC Rainwater Gutters ½ round 125 × 87 Rainwater Downpipe 80mm Drip stones 0.9 x 2.4 Chromadek Roof Sheets Concrete Roof Tiles 25mm × 220mm sw Fascia Galvanised Roof Ridge Kitchen Fittings Kitchen sink 1.2m drop in Cupboards under sink Cupboards on walls
72 no 18 no
540.00 2 no 1 no 2 no
$
$ $17.47 ea
18 no
$ $
$210.64 ea
92 no
$ $
$4.37/m $2.62/m $0.87/m $4.80/m² $1.31/m
212 m 1,546 m 2,294 m 917.6 m² 836 m
$ $ $ $ $ $
$13.97 ea $1.31 ea $1.75 ea
18 sets 18 no 5 no
$ $ $ $
$4.37/m $3.91/m $13.10 ea $7.42 ea $10.48/m $5.24/m
211 m 22 m 8 no 557 no 211 m 94 m
$ $ $ $ $ $ $
$61.14 ea $1353.71 ea $1222.71 ea
S Shaped Classroom Block_Project Package_Crazy_Architecturee_Rev.0.xlsx Resources|Console Page 3 of 4
1 no 1 no 1 no
$ $ $
314.41 314.41 19,328.17 19,328.17 12,481.84 923.67 4,051.74 2,003.49 4,407.69 1,095.25 283.84 251.53 23.58 8.73 7,947.72 919.96 84.52 104.80 4,136.07 2,207.90 494.46 2,637.55 61.14 1,353.71 1,222.71 +263 77 192 7337 info@presageprojects.co.zw Presage Projects (Pvt) Ltd © 2020 All Rights Reserved
┌
Created on 23/6/2020 @ 8:48 PM┐
Confidential Resource Usage
DWG Ref - IG S Shaped Classroom Block_Project Package_Crazy_Architecturee_Rev.0 Bill of Resources
22% 3%
≡ ≡ 1
Cost Code HVAC02
Resource Description HVAC Ceiling fan
TL01 TL02
Bathroom Fittings Wall mounted cabinet with mirror Towel rack Water Closet Ceramic wash basin & pedestal Tiles Floor tiles 600 x 600 Wall tiles 600 x 200
PCI01 PCI02
Pre-Cast Items Double Cam Concrete Sink Pre-cast lintels
BF01 BF02 BF03 BF09
PVCSP01 PVCSP02 GP01 CP01 GF01 GF02 GF03 GF05 CF01 CF02 CF03 PVCFT01 PVCFT02 PVCFT03 PVCFT04 PVCFT05 PVCFT06 PVCFT07 PVCFT08 PVCFT09 TM01 TM02 TM06 RF01 WMS01
CN01 CNF01 CNF02 CB02 CB05 SW01 SW04 ST01 ST02 ST03 ST04 ST05 ST07 B01 B02 EMS01 EMS02 EMS04 EMS05
ACC ACC01 ACC02 ACC03 ACC08 ACC11
0 Cost
75%
Usage $56.77 ea
21.97% Bill Mark-Up @ 0.00% 3.23% 5.2 Month Timeline 74.80% US$ 190,664.68 Excluding VAT Amount (US$) $ 567.69 10 no $ 567.69 $
$52.40 $22.71 $78.60 $34.93
ea ea ea ea
8 6 15 8
no no no no
2,013.97 419.21 136.24 1,179.04 279.48 2,128.34 754.59 1,373.75
$ $ $ $ $
$1.89 ea $0.63 ea
400 no 2,185 no
$ $ $
$78.60 ea $1.75/m
Plumbing PVC Sewer Pipes ø110mm sewer pipe ø60mm sewer pipe Galvanised Pipes ø20mm GI pipe Copper Pipes ø20mm copper pipe Galvanised Fittings ø20mm Gi elbow ø20mm Gi tee ø20mm Gi sleeve ø35mm Gate Valve Copper Fittings ø20mm copper elbow ø20mm copper tee ø20mm copper sleeve PVC Fittings ø160mm to ø110mm reducer ø110mm x 90° bend ø110mm x 45° bend ø110mm equal tees ø110mm end caps ø110mm p-trap ø110mm sieve ø110mm × 2m pvc vent pipe ø110mm fly trap over vent pipe Taps & Mixers ø15mm basin taps (Cobra) Sink Mixer ø35mm brass tap Rubber Fittings ø35mm rubber p-trap Water Main Supply ZINWA flow meter
1 no 16 m
$ $ $ $
$9.61/m $1.75/m
90 m 24 m
$ $ $
$21.83/m
108 m
$ $
$21.83/m
108 m
$ $
$7.86 $14.85 $13.10 $4.80
ea ea ea ea
50 50 50 17
no no no no
$ $ $ $ $
$8.73 ea $16.59 ea $14.85 ea
50 no 50 no 50 no
$ $ $ $
$31.44 $31.70 $34.93 $17.47 $4.37 $30.57 $5.24 $7.42 $2.18
ea ea ea ea ea ea ea ea ea
1 23 23 23 1 23 23 15 15
no no no no no no no no no
$ $ $ $ $ $ $ $ $ $
$6.99 ea $48.03 ea $4.37 ea
16 no 1 no 2 no
$ $ $ $
$1.75 ea
9 no
$ $
$33.19 ea
Electricals Conduits ø19mm pvc conduit Conduit Fittings ø20mm pvc sleeve Junction box (6 × 6) Cables 2.5mm² triple core copper conductors armoured cable Switches Single gang switch Cooker switch Sockets single electric socket double electric socket Cooker terminal Shaver socket Lamp holder (Brass) Fluorescent socket Bulbs/Lights Bulkhead c/w gland seal Osram 11watt fluorescent bulb Electrical Main Supply 3 Phase meter board Generator/Solar change over switch Distribution board 16 Way c/w Breakers ZETDC Prepaid meter
1 no
$ $ $
$1.75/m
422 m
$ $
$0.44 ea $0.87 ea
211 no 38 no
$ $ $
$0.26/m $3.49/m
1,266 m 40 m
$ $ $
$1.92 ea $8.73 ea
38 no 1 no
$ $ $
$2.62 $5.24 $30.57 $3.06 $1.75 $4.80
ea ea ea ea ea ea
38 65 1 2 38 2
no no no no no no
$ $ $ $ $ $ $
$6.99 ea $3.06 ea
10 no 38 no
$ $ $
$34.93 $48.03 $388.65 $32.31
Accessories Diesel (Information only, already included in Plant Rates) Petrol (Information only, already included in Plant Rates) 4" wire nails Termite Poison (app rate @ 5ℓ/m² of 5ℓ/95ℓ termicide/water mix) PVC Solvent Cement (100mℓ)
ea ea ea ea
no no no no
$ $ $ $
$ $1.07/ℓ $1.18/ℓ $1.75/packet $0.61/ℓ $2.62 ea
S Shaped Classroom Block_Project Package_Crazy_Architecturee_Rev.0.xlsx Resources|Console Page 4 of 4
1 1 1 1
738.92 ℓ 512.63 ℓ 57 packets 12.38 ℓ 3.7 no
$ $ $ $ $
107.27 78.60 28.67 12,766.14 906.55 864.63 41.92 2,358.08 2,358.08 2,358.08 2,358.08 1,872.05 393.01 742.36 655.02 81.66 2,008.73 436.68 829.69 742.36 2,937.90 31.44 729.17 803.49 401.75 4.37 703.06 120.52 111.35 32.75 168.56 111.79 48.03 8.73 15.72 15.72 33.19 33.19 2,658.21 736.98 736.98 125.31 92.12 33.19 471.38 331.64 139.74 81.75 73.01 8.73 552.84 99.56 340.61 30.57 6.11 66.38 9.61 186.03 69.87 116.16 503.93 34.93 48.03 388.65 32.31
116.12 793.78 604.41 98.83 7.57 9.72
+263 77 192 7337 info@presageprojects.co.zw Presage Projects (Pvt) Ltd © 2020 All Rights Reserved
Conditions of Contract 3rd Edition 1977 (International) Clause 14.1 Program
Created on 23/6/2020 @ 8:48 PM
WBS ID Operation % Complete % Planned Start 1 S Shaped Classroom Block_Project Package_Crazy_Architecturee_Rev.0 0.00% 0.00% 3-Jul-20 2 Mobilisation/Procurement 0.00% 0.00% 3-Jul-20 2.1 Mobilise cabin and security fence c/w gate to site 0.00% 0.00% 3-Jul-20 2.2 Set-up temporary perimeter security 0.00% 0.00% 5-Jul-20 2.3 Set-up storeroom on site 0.00% 0.00% 5-Jul-20 2.4 Procure cement and aggregates 0.00% 0.00% 5-Jul-20 2.5 Mobilise tools and small equipment 0.00% 0.00% 7-Jul-20 3 Substructure 0.00% 0.00% 5-Jul-20 3.1 Earthworks 0.00% 0.00% 5-Jul-20 3.1.1 Clear site 0.00% 0.00% 5-Jul-20 3.1.2 Remove turf 0.00% 0.00% 7-Jul-20 3.1.3 Excavate topsoil & cartaway 0.00% 0.00% 9-Jul-20 3.1.4 Excavate trenches 0.00% 0.00% 11-Jul-20 3.1.5 Compact trench bases 0.00% 0.00% 14-Jul-20 3.1.6 Termite treatment to surface of excavations 0.00% 0.00% 16-Jul-20 3.2 Strip Footing 0.00% 0.00% 20-Jul-20 3.2.2 Pour footing 0.00% 0.00% 21-Jul-20 3.3 Foundation Wall 0.00% 0.00% 26-Jul-20 3.3.1 Build external foundation wall 0.00% 0.00% 26-Jul-20 3.3.2 Build internal foundation walls 0.00% 0.00% 28-Jul-20 3.3.3 Backfill around external wall 0.00% 0.00% 4-Aug-20 3.3.4 Fill foundation with hardcore 0.00% 0.00% 6-Aug-20 3.4 Foundation Slab 0.00% 0.00% 9-Aug-20 3.4.1 Lay DPM 0.00% 0.00% 9-Aug-20 3.4.2 Prepare meshref S193 0.00% 0.00% 10-Aug-20 3.4.3 Pour slab 0.00% 0.00% 14-Aug-20 4 4.1 4.1.1 4.1.2 4.1.3 4.1.4 4.1.6 4.1.7 4.1.8 4.2 4.2.1 4.2.2 4.3 4.3.1 4.3.2 4.3.3 4.3.4 4.3.5 4.3.6 4.3.7 4.3.8 4.3.9 4.3.10 4.3.11 5 5.1 5.1.1 5.1.2 5.3 5.3.1 5.3.2 5.3.3 5.4 5.4.1 5.4.2
Superstructure 0.00% Masonry 0.00% Build external walls up to window level 0.00% Build internal walls not exceeding 1.5m high 0.00% Build-in door frames 0.00% Build-in window frames 0.00% Build internal walls up to wall plate 0.00% Build external walls up to wall plate with air bricks 0.00% Build external walls at gable ends 0.00% Plastering 0.00% Plaster walls internally 0.00% Plaster walls externally 0.00% Roof 0.00% Install wall plate 0.00% Supply and fix trusses by specialist 0.00% Fix purlins 0.00% Fix brandering 0.00% Install roof covering 0.00% Fix ridge on roof 0.00% Install ceiling 0.00% Install cornice 0.00% Fix fascia/barge board 0.00% Fix gutters 0.00% Install downpipes complete with shoes and dripstones 0.00% Finishes Wall & Floor Finishes Rhinoset finish on internal walls Rhinoset finish on ceiling Painting Paint internal walls Paint ceiling High gloss paint steel to frames Tiling Wall tiles to bathrooms and kitchen Floor tiles to bathrooms and kitchen
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
20-Aug-20 20-Aug-20 20-Aug-20 22-Aug-20 20-Aug-20 22-Aug-20 27-Aug-20 25-Aug-20 1-Sep-20 29-Aug-20 29-Aug-20 3-Sep-20 31-Aug-20 31-Aug-20 2-Sep-20 26-Sep-20 28-Sep-20 5-Oct-20 15-Oct-20 5-Oct-20 8-Oct-20 14-Oct-20 17-Oct-20 25-Oct-20 17-Sep-20 14-Oct-20 18-Oct-20 21-Oct-20 17-Sep-20 17-Oct-20 16-Nov-20 17-Sep-20 11-Nov-20 11-Nov-20 23-Nov-20
Duration 154 Days 5 days 1 day 2 days 1 day 2 days 1 day 45 days 14 days 1 day 1 day 1 day 2 days 1 day 3 days 5 days 4 days 13 days 8 days 1 day 1 days 2 days 11 days 0.50 days 3 days 5 days
Finish 4-Dec-20 8-Jul-20 4-Jul-20 7-Jul-20 6-Jul-20 7-Jul-20 8-Jul-20 19-Aug-20 19-Jul-20 6-Jul-20 8-Jul-20 10-Jul-20 13-Jul-20 15-Jul-20 19-Jul-20 25-Jul-20 25-Jul-20 8-Aug-20 3-Aug-20 29-Jul-20 5-Aug-20 8-Aug-20 19-Aug-20 9-Aug-20 13-Aug-20 19-Aug-20
75 days 25 days 25 days 3 days 10 days 6 days 1 day 6 days 1 day 49 days 49 days 14 days 64 days 1 day 23 days 4 days 6 days 9 days 7 days 29 days 3 days 2 days 8 days 1 days
3-Nov-20 14-Sep-20 14-Sep-20 25-Aug-20 30-Aug-20 28-Aug-20 28-Aug-20 31-Aug-20 2-Sep-20 17-Oct-20 17-Oct-20 17-Sep-20 3-Nov-20 1-Sep-20 25-Sep-20 30-Sep-20 4-Oct-20 14-Oct-20 22-Oct-20 3-Nov-20 11-Oct-20 16-Oct-20 25-Oct-20 26-Oct-20
76 days 36 days 32 days 26 days 76 days 25 days 16 days 1 day 17 days 12 days 5 days
30-May-20
29-Jun-20
29-Jul-20
3-Jul-20
154 Days
3-Jul-20
5 days
3-Jul-20
1 days 2 days
5-Jul-20
1 days
5-Jul-20
2 days
5-Jul-20
27-Sep-20
27-Oct-20
6.1 6.2 6.4 6.6 6.7 6.8 6.9 7 7.1 7.2 7.3 7.4 7.5 7.6 7.7 8 9 9.1
Fittings and Equipment 0.00% Fit doors 0.00% Locksets & window handles 0.00% Install water closet for bathroom 0.00% Install wash basin for bathroom 0.00% Fix bathroom cabinet and towel rack 0.00% Install kitchen sink complete with mixer 0.00% Install kitchen cupboards 0.00% Services 0.00% Fix galvnised piping for cold water supply including 0.00% all fittings Fix copper piping for hot water supply including all0.00% fittings Fix PVC sewer piping including all fittings 0.00% Test and commission all pipes 0.00% Installation of flex conduits and cables 0.00% Installation of electrical fittings 0.00% Test and commission electrical installations 0.00% External Works 0.00% Project Completion 0.00% Furnish & Commission Building 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
17-Oct-20 11-Nov-20 13-Nov-20 17-Oct-20 18-Oct-20 19-Oct-20 18-Oct-20 11-Nov-20 20-Aug-20 1-Sep-20 1-Sep-20 20-Aug-20 22-Aug-20 16-Oct-20 17-Oct-20 5-Nov-20 25-Oct-20 2-Dec-20 2-Dec-20
46 days 2 days 2 days 1 day 1 day 1 day 1 day 1 day 78 days 1 day 1 day 1 day 1 day 1 day 18 days 1 day 2 days 2 days 2 days
1 days 1 days
7-Jul-20
1 days
9-Jul-20 11-Jul-20
1 days 2 days
14-Jul-20 16-Jul-20
1 days 3 days
21-Jul-20
4 days
26-Jul-20
8 days
28-Jul-20
1 days
4-Aug-20
1 days
6-Aug-20
2 days
9-Aug-20 10-Aug-20
0.50 days 3 days
14-Aug-20
5 days
20-Aug-20
75 days
20-Aug-20
25 days
20-Aug-20
25 days
22-Aug-20 20-Aug-20
3 days
10 days
22-Aug-20
6 days
27-Aug-20 25-Aug-20
1 days 6 days
1-Sep-20
1 days
29-Aug-20
49 days
29-Aug-20
49 days
3-Sep-20
14 days
31-Aug-20
64 days
31-Aug-20
1 days
2-Sep-20
23 days 26-Sep-20
4 days
28-Sep-20
6 days
5-Oct-20
9 days 15-Oct-20
5-Oct-20
7 days
29 days
8-Oct-20
3 days
14-Oct-20
2 days
17-Oct-20
8 days
25-Oct-20
17-Sep-20
2-Dec-20 19-Nov-20 19-Nov-20 16-Nov-20 2-Dec-20 11-Nov-20 2-Dec-20 18-Sep-20 28-Nov-20 23-Nov-20 28-Nov-20
36 days
18-Oct-20
32 days
21-Oct-20 17-Sep-20
1 days
76 days 14-Oct-20
26 days
76 days 17-Oct-20
25 days 16-Nov-20
17-Sep-20
16 days
1 days 11-Nov-20
17 days
11-Nov-20
12 days 23-Nov-20
2-Dec-20 13-Nov-20 15-Nov-20 18-Oct-20 19-Oct-20 20-Oct-20 19-Oct-20 12-Nov-20 6-Nov-20 2-Sep-20 2-Sep-20 21-Aug-20 23-Aug-20 17-Oct-20 4-Nov-20 6-Nov-20 27-Oct-20 4-Dec-20 4-Dec-20
13-Nov-20
17-Oct-20
1 days 1 days 11-Nov-20
1 days
78 days
20-Aug-20 22-Aug-20
1-Sep-20
1 days
1-Sep-20
1 days
1 days 1 days 16-Oct-20
1 days
17-Oct-20
18 days 5-Nov-20
25-Oct-20
S Shaped Classroom Block_Project Package_Crazy_Architecturee_Rev.0.xlsx Construction Schedule|Baseline
2 days
1 days
19-Oct-20
20-Aug-20
2 days
1 days
18-Oct-20
18-Oct-20
5 days
46 days 11-Nov-20
Page 5 of 5
26-Dec-20
% Complete
17-Oct-20
6
26-Nov-20
Duration
5-Jul-20
7-Jul-20
28-Aug-20
1 days
2 days 2-Dec-20
2 days
2-Dec-20
2 days
+263 77 192 7337 info@presageprojects.co.zw Presage Projects (Pvt) Ltd © 2020 All Rights Reserved
┘
└
Special Note S Shaped Classroom Block_Project Package_Crazy_Architecturee_Rev.0 While every care has been exercised in preparing the information contained herein, Presage Projects will not be held responsible for material discrepancies that may occur when changes are made to the design without notification, or materials that are procured without following the quantities calculated in this document. We encourage records of materials received and issued for construction to be kept by Site Security and the Site Agent on behalf of the Client
+263 77 192 7337 Presage Projects P/L info@presageprojects.co.zw Central Business District, Harare, Zimbabwe © 2020 All Rights Reserved
┐
┌