The Australian Pipeliner October 21

Page 38

CONTRACTORS

HDD construction methodology Insights Maxibor prepares an HDD construction methodology which provides a comprehensive overview of the processes involved in the physical delivery of the project and to demonstrate to stakeholders how key activities and issues specific to the project are to be managed.

T

his article provides an insight into reaming, hole conditioning, product pipe installation and testing for a typical 500 m large bore project installing OD500 HDPE pipe.

Pilot hole construction, reaming and hole conditioning The expected ground conditions based on the geotechnical investigation is: • Drill set up for 60 m – OTR Clay • 60 to 140 m – bluestone with quartz (hard rock) • 140 to 207 m – transition from bluestone to mudstone/siltstone • 207 to 450 m – mudstone/siltstone

• 450 m to exit at 500 m – transition from mudstone/siltstone to OTR As the pilot hole will encounter both OTR and rock, the key bottom hole assembly (BHA) tooling will include: • 6.5 inch (165 mm) pilot hole drill bit • Jetting assembly • Orientation sub for mounting survey probe • P2 pressure module • 4 inch (101 mm) non-magnetic drill collar • 4.5 inch (114 mm) 5:6 motor for the rock sections Following completion of the pilot hole, the BHA

will be removed at the exit location and the first reamer attached. The proposed reaming sequence for the pipeline will be conducted as follows: • 500 mm back-ream • 750 mm back-ream • 750 mm hole conditioning pass The hole conditioning passes will confirm the bore is in a condition to accept the product pipe. The driller will monitor and record drilling pressures, and the mud technician will monitor and record fluid properties so an accurate assessment can be made of the hole condition prior to installation. Detailed bore logs will be maintained throughout the drilling processes. A drilling summary will be provided detailing the tooling used at each stage and relevant commentary particularly around the bore hole cleaning processes.

Product pipe installation and testing

Excavator support operation during HDD installation.

Maxibor drilling at the Logan Water Project.

38

The Australian Pipeliner | October 2021

Following hole opening and the completion of any required cleaning passes, pipeline installation will take place. As this is one of the most critical phases of construction, a site-specific installation plan will be developed which will cover daily schedules, pipe stress analysis, over bend dimensions, risk analysis and contingency and emergency procedures. This will be reviewed and approved by Maxibor management prior to installation taking place. The pulling head on the pipeline will be connected to the drill string using a 150 t rated maxi dub swivel. Attached to the swivel will be a 30 inch (750 mm) barrel reamer. The drill string and barrel reamer will be free to rotate during the subsequent pipeline installation operation. The jets on the barrel reamer will allow bentonite drilling fluid to be pumped through the borehole during the installation operation. The gravel shield will be installed over the rear of the reamer, swivel joint and the leading edge of the carrier pipe to prevent loose material falling in behind the reamer. This provides a smooth transition between the rotating and non-rotating parts of the assembly. For buoyancy control, water will be pumped into the pipeline from the rear of the pipe string using a 50 mm pipeline and fill pump located at the rear of the site. A meter will be used to ensure that only the section of pipe below ground is filled so as not to cause excessive loads and stress on the above ground section of pipe.


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

CCE expands its corrosion management offering Corrosion inhibiting grease for equipment 72 Anode offers GreenAmp for cathodic protection 74

41min
pages 70-92

Futureproofing gas detection in a hydrogen future

4min
pages 68-69

Super Emitters no match for Picarro solution

3min
pages 66-67

Remote operation on pipeline isolation

6min
pages 62-63

Intelligent pigging and emissions reduction technologies

6min
pages 64-65

Fast game’s a good game on the Sunshine Coast

3min
pages 60-61

Spiecapag makes mark on pipeline history

5min
pages 58-59

HDD installations on the Parmelia Gas Pipeline

3min
pages 56-57

Queensland hits peak production

3min
pages 54-55

Enhanced solutions for your ESG Program

1min
page 52

Sentanil CMS supports pipeline construction

1min
page 53

Tracer wire system ensures safe utility location

2min
pages 48-49

kwik-ZIP’s simple spacer solutions

2min
pages 50-51

Supporting projects from the ground up

4min
pages 46-47

More reach for Vermeer Australia customers

2min
pages 40-41

PER teams with trusted name

4min
pages 44-45

Nacap’s approach keeps Arrow on target

5min
pages 36-37

HDD construction methodology insights

5min
pages 38-39

Unconscious bias in recruitment

6min
pages 32-33

Pollard's leaves competition in the dust

3min
pages 42-43

Supporting projects from concept to completion

2min
pages 34-35

Breaking down barriers in the pipeline industry

10min
pages 28-31

Convention goes virtual in 2021

3min
pages 18-19

VEGA equipment keeps Santos gas on track

3min
pages 24-25

Survey finds widespread support for hydrogen

2min
pages 16-17

Registration for pipeline engineers

3min
pages 14-15

APGA establishes women’s forum

1min
pages 26-27

CEO's report

10min
pages 8-11

Gas and energy policy

3min
pages 12-13

President's Message

3min
pages 6-7
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.