The Australian Pipeliner October 21

Page 60

PROJECTS

Fast game’s a good game on the Sunshine Coast Accelerated works on the Sunshine Coast helped a Maroochydore community network get back online quicker with minimal disruption.

P

ipeline installations in developed areas are becoming more commonplace as populations grow. Unitywater, which provides essential services to the Moreton Bay, Noosa and Sunshine Coast regions of South East Queensland, was faced with this challenge when urgent work was required on a severely degraded sewer rising main at Fishermans Road in Maroochydore. The project was further complicated by the popular Sunday market, bustling sports precinct and the need to replace and realign the major sewer rising main installed in 1977. Unitywater Executive Manager for Sustainable Infrastructure Solutions Amanda Creevey says works were fast-tracked to reduce the impact on local business and recreators that access the Maroochy River. “The completion of this project ensures we can provide reliable sewage services to around 10,000 customers and many more into the future, while also improving the efficiency of our network more broadly,” she says.

“By accelerating these works, the pipeline could also be brought online prior to the 20212022 wet season, when demand is at its peak.” Unitywater contractor Pipeline Drillers Group helped make it possible with a horizontal direction drilling (HDD) project designed and delivered without delay. Director John Whitbread says HDD was the natural choice to install approximately 550 m of new pipework by drilling 20 m underground to minimise disruption to the community and safeguard the new asset. “We had the Maroochydore Multi Sports Complex, busy Fishermans Road, additional under and above ground services, and residential areas near the pipeline, so a trenchless option was a must,” says Mr Whitbread. “With those factors, along with the pressing need to complete the project on a tight turnaround, we had for-construction HDD designs completed within a week of contract award. We knew the significance of this project and the importance of getting the HDD works

Approximately 550 m of new pipework was installed by drilling 20 m underground to minimise disruption to the community in South East Queensland.

done to allow for completion of the tie-ins and other larger project works, so timing was vital.” As well as being time-sensitive, several other project-specific factors added to the complexity of the project, explains Pipeline Drillers Group Business Development Manager Paul Tredenick. “We had building infrastructure and lighting services right in the middle of the alignment,” says Mr Tredenick. “Additionally, ground conditions were challenging – penetration boreholes and diffraction surveys were taken in the project area, and they were demonstrating variable results. One area would show rock conditions at particular depths, while not far away, we’d get results of very low-strength, other-thanrock geology.” Pipeline Drillers Group tackled these complexities with a risk-based approach. “We minimised settlement, vibration, and construction risk to existing infrastructure by incorporating a significant horizontal radius into the design,” explains Mr Tredenick. “And given the uncertainty in ground conditions, we included risk mitigation measures such as adding exit side casing into the design, and a set of lightweight tooling as well as rock tooling. With this approach, we could minimise risk of hydrofracture at shallow depths, but at the same time, we knew we could confidently handle any harder geology we might encounter.” Pipeline Drillers Group mobilised its Herrenknecht 250T rig, along with a variety of auxiliary and standby equipment, to ensure minimal downtime during the seven-day schedule. Supported by classic Sunshine Coast weather, the 550 m, 450 mm HDPE crossing was completed ahead of schedule, within four weeks of project commencement. Ms Creevey says the project was a testament to the benefits of trenchless methods. “By using HDD to replace and realign the Fishermans Road Sewer Pipeline, we were able to bring this important piece of infrastructure online quickly and efficiently, with minimal closures and disruption to our residents and local community,” she says.

For more information visit www.pdgroup.com.au

60

The Australian Pipeliner | October 2021


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

CCE expands its corrosion management offering Corrosion inhibiting grease for equipment 72 Anode offers GreenAmp for cathodic protection 74

41min
pages 70-92

Futureproofing gas detection in a hydrogen future

4min
pages 68-69

Super Emitters no match for Picarro solution

3min
pages 66-67

Remote operation on pipeline isolation

6min
pages 62-63

Intelligent pigging and emissions reduction technologies

6min
pages 64-65

Fast game’s a good game on the Sunshine Coast

3min
pages 60-61

Spiecapag makes mark on pipeline history

5min
pages 58-59

HDD installations on the Parmelia Gas Pipeline

3min
pages 56-57

Queensland hits peak production

3min
pages 54-55

Enhanced solutions for your ESG Program

1min
page 52

Sentanil CMS supports pipeline construction

1min
page 53

Tracer wire system ensures safe utility location

2min
pages 48-49

kwik-ZIP’s simple spacer solutions

2min
pages 50-51

Supporting projects from the ground up

4min
pages 46-47

More reach for Vermeer Australia customers

2min
pages 40-41

PER teams with trusted name

4min
pages 44-45

Nacap’s approach keeps Arrow on target

5min
pages 36-37

HDD construction methodology insights

5min
pages 38-39

Unconscious bias in recruitment

6min
pages 32-33

Pollard's leaves competition in the dust

3min
pages 42-43

Supporting projects from concept to completion

2min
pages 34-35

Breaking down barriers in the pipeline industry

10min
pages 28-31

Convention goes virtual in 2021

3min
pages 18-19

VEGA equipment keeps Santos gas on track

3min
pages 24-25

Survey finds widespread support for hydrogen

2min
pages 16-17

Registration for pipeline engineers

3min
pages 14-15

APGA establishes women’s forum

1min
pages 26-27

CEO's report

10min
pages 8-11

Gas and energy policy

3min
pages 12-13

President's Message

3min
pages 6-7
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.