Trenchless September 2021

Page 36

TUNNELLING & MICROTUNNELLING

Rob Carr in the driver’s seat for WA sewer project

Herrenknecht AVN currently being prepped for the tunnelling work.

In March, microtunnelling expert Rob Carr was awarded a contract to deliver the Quinns Main Sewer Extension for Water Corporation in Western Australia. In terms of scale, the project is one of the biggest the company has undertaken in the state.

W

ater Corporation of Western Australia awarded Rob Carr a design and construct contract to extend the Quinns Main Sewer, which allows conveyance of wastewater flows from Ellenbrook, running through Clarkson and Neerabup National Park to the Alkimos wastewater treatment plant. “The existing infrastructure can’t handle the expected calculated future flows in the area,” explains Rob Carr Western Australia General Manager Barry Crowley. Mr Crowley has worked with the company for 20 years, and, under his leadership, the team has installed hundreds of kilometres of main sewers throughout Western Australia. This project involves 2 km of 1,800 mm diameter sewer main. The extension adds on to Stage 1 of the Quinns Main Sewer project, which was completed more than ten years ago. “The purpose of Stage 2 is to extend across that area through the national park so development upstream of that area can occur, be it residential, commercial or industrial,” says Mr Crowley. The project will use a combination of microtunnelling and

36 TRENCHLESS AUSTRALASIA SEPTEMBER 2021

open trench techniques, with Rob Carr successful in making some innovative changes to the brief for the future delivery of works. “The preliminary design had a requirement for 764 m open trench and 1.173 km of tunnelling,” says Senior Project Manager Paul Lee. “We’ve changed that through the design to 1.4 km of tunnelling and 537 m of open trench.” This innovation combined with Rob Carr’s extensive capability in successfully delivering large diameter microtunnelling projects in challenging ground conditions were two of the reasons Rob Carr was awarded the contract. “During the bid process and design evolution, we’ve managed to get more tunnelling on the project and less opening trenching works, which results in less impact for surrounding resident street access. From a design aspect it made more sense to do it that way,” says Mr Crowley. “It reduces the volume of spoil, eliminates reinstatement works, and it’s friendlier to the overall community.” Much of the eliminated open trench work was to take place in residential areas, and Rob Carr wanted to minimise the potential impact to the community during the design phase and construction. The company was also successful in its suggestion to include local content. “When we put in our bid to Water Corporation, their preliminary design was based around the use of glass-reinforced plastic (GRP) jacking pipe and open trench installation,” says Mr Crowley. “We put in alternative bid for the use of reinforced concrete


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

ASTT Corporate Members

1min
pages 72-73

Breakthrough technology for drain blockages

3min
pages 70-71

Destigmatising poor mental health in construction

4min
pages 68-69

No-dig innovator takes service to new heights

5min
pages 66-67

Australia’s first online drain cleaning refresher

4min
pages 64-65

ImpulseRadar offers a different view

5min
pages 62-63

Hydro excavation in Brisbane’s Southbank

4min
pages 50-51

The future in pipeline rehabilitation

3min
pages 58-59

Ahead of the curve

3min
pages 56-57

KAISER forges new partnerships

3min
pages 54-55

The superior alternative in SMS rehab

2min
pages 60-61

SECA unveils eCityJet

2min
pages 52-53

The most powerful truck-mounted vacuum excavator yet

2min
pages 48-49

Boretech leading WA’s HDD utility installations

4min
pages 46-47

Getting the edge over the competition

4min
pages 40-41

Bohrtec machine guides sewer works

3min
pages 38-39

Good practices for HDD project management

5min
pages 42-43

Rob Carr in the driver’s seat in WA

4min
pages 36-37

HDI Lucas stays tuned in on Channel Island

3min
pages 32-33

Zipping past the competition

2min
pages 34-35

NSW rolls on through COVID storm

6min
pages 28-31

What to expect at No-Dig

0
pages 24-25

From the President

2min
pages 10-11

No-Dig Down Under postponed

1min
pages 20-21

News in brief

7min
pages 16-19

Councillor’s reports

3min
pages 14-15

Editor’s letter

4min
pages 8-9

From the ASTT Secretary

3min
pages 12-13

Herrenknecht becomes No-Dig Gold Sponsor

2min
pages 22-23
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.