SMED Presentation

Page 1

SINGLE MINUTE EXCHANGE OF DIES (SMED)

OM
15-01-2023

What is a Changeover?

The amount of time taken to change a piece of equipment from producing the last good piece of a production lot to the first good piece of the next production lot.

OM
15-01-2023

Total elapsed changeover time, Tc =Run-down period + Set-up period + Run-up period

15-01-2023

3
OM

What is SMED?

Single Minute Exchange of Dies

Developed by Shigeo Shingo

Asystem designed to radically reduce the amount of time to perform a changeover or setup

OM
15-01-2023

History

The concept arose in the late 1950s and early 1960s, when Shigeo Shingo, was consulting to a variety of companies including Toyota, and was contemplating their inability to eliminate bottlenecks at car body-moulding presses.

• 1950-Forms first stage of SMED : Involves splitting a setup operation into internal and external set ups

• 1956-58—Worked for Mitsubishi Ship buildings

• Invents a new system for hull assembly of 65,000 ton supertanker

• Cut time from four months down to three and than two months

• 1970-Originated SMED system at Toyota

• Wrote more than 14 books

• Including Toyota Production System

15-01-2023 OM

Pit stop in F1 Race

The reduction of time in pit stops during F1 races is one of the beautiful example of SMED.

15-01-2023

OM

Reducing Set-Up Time

OM
15-01-2023

Stages Of SMED

Segregate Internal External Elements

STAGE II

80 MINS 40 MINS

Convert some Internal Elements or parts of those to External Elements

STAGE III

7 MINS

TOTAL SET UP TIME INTERNAL SET UP TIME 120 MINS
STAGE I
Reduce times of residual Internal Elements 15-01-2023 OM

The SMED Process

 Observe the current methodology.

 Separate internal and external Operations.

 Identify the tasks which can be eliminated.

 Convert maximum internal operations to external Operations.

 Streamline the remaining Internal activities.

 Streamline External activities.

 Document the new procedure and the actions that are yet to be completed.

 Do it all again.

15-01-2023 OM

1. Observe the current methodology

 Watch a full changeover at least once – more is better.

 Do documentation of all the activities happening during the changeover.

OM
15-01-2023

Data recording Format

Company Name

Process : Roll Change Area : Machine No : Start Time : Name : S.N o. ACTIVITYTIME(min) INTERNAL EXTERNAL NEEDED WORKS MOTION TRANSPORT ATION WAITING SEARCHING ELIMINATE COMBINE REDUCE SIMPLIFY REMARK 15-012023 OM

Look for

 Shortages, mistakes, inadequate placement of needed equipment.

 Equipment with slow adjustments for the large coarse part of adjustment.

 Proper placing of all required equipment which are used.

 Lack of functional standardization, that is standardization of only the parts necessary for setup, e.g. all bolts use same size spanner, Same type of bolts used, die grip points are in the same place on all dies.

15-01-2023 OM

Look for

 Much operator movement around the equipment during setup.

 More attachment / bolting points than actually required.

 Attachment points that take more than one turn to fasten.

 Any adjustments after initial setup.

 Any use of experts during setup.

 If there is waiting for anything.

15-01-2023 OM

Separate the INTERNAL and EXTERNAL activities.

 External Operation : One that may be completed while machine is in operation.

 Internal Operation : One that requires the shut down of the machine for completion.

2. Separate internal and external Operations.
15-01-2023 OM

3. Identify the tasks which can be eliminated.

Look for operation / tasks which can be eliminated like, waiting for tools, waiting for crane, etc..

15-01-2023

OM
4 internal operations to external Convert maximum Internal Operations Convert (where possible) Internal activities into External ones. 15-01-2023 OM

5. Streamline the remaining Internal activities

 Simplify the remaining internal activities

 For e.g. It's the last turn of a bolt that tightens it; the rest is just movement.

 And also adopt parallel operations.

15-01-2023 OM

The interrupted screw (or interrupted thread) provides one means of clamping and unclamping something quickly. 15-01-2023

OM
Complete all the external Activities before the change
OM
6. Streamline External activities.
over happens. 15-01-2023

7. Document the new procedure and the actions that are yet to be completed.

 Document all the activities which occurred.

 Note all the activity which are not completed and make action plan.

15-01-2023 OM

8. Do it all again

 Repeat all the steps for the next change over. 15-01-2023

OM

Example Tools

Split thread bolts

15-01-2023

OM

Example Tools

15-01-2023 OM

Example Tools

Reduce the amount of turns required in order to activate the screw.

15-01-2023

OM

Shadow Board

15-01-2023 OM

Benefits of SMED

• Increases throughput by reducing setup times

• Eliminates setup errors

• Increases safety

• Reduces the cost of setups

• Reduces waiting times and inventory buildups

• Reduced setup time

15-01-2023 OM

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.