Construction Milestone List AIT Waste Water Treatment System
AIT Waste Water Treatment Facility: Construction Milestone List
Document History Version
Description
Date
Author
Checked
Number
1
Original
21/03/13
i
LM
NMcH
AIT Waste Water Treatment Facility: Construction Milestone List
Table of Contents Document History .................................................................................................................. i 1.0
Milestone List ............................................................................................................ 1
Sponsor Acceptance ............................................................................................................. 2
ii
AIT Waste Water Treatment Facility: Construction Milestone List
1.0
Milestone List Milestone List
Project: Wastewater Treatment Plant Athlone IT Milestone No. Milestone C1000 C1012 C1024 C1102
C1063
C1067 C1080
C1153 C1158 C1022 C1166 C1167
Construction Start Tender Stage Complete Construction Starts On Site Pumping Chamber Complete Treatment Plant Complete (SBR Tank) Reinstatement Complete (Phase 2) Sewer Network Complete Reinstatement Complete (Phase 3) Tank & Pipe Testing Complete Procurement Complete Finishing Works Complete Construction Complete
Date: 09/03/2014
Mandatory/Optional Completion Date Mandatory Mandatory Mandatory Mandatory
10/03/2014 23/04/2014 19/05/2014 17/07/2014
Verification Sponsor Approval Sponsor Approval Sponsor Approval Sponsor Approval
23/07/2014 Mandatory
Sponsor Approval 28/07/2014
Mandatory Mandatory
Sponsor Approval 31/07/2014
Sponsor Approval
05/08/2014 Mandatory Mandatory Mandatory Mandatory Mandatory
1
Sponsor Approval 07/08/2014 28/08/2014 28/08/2014 28/08/2014
Sponsor Approval Sponsor Approval Sponsor Approval Sponsor Approval
AIT Waste Water Treatment Facility: Construction Milestone List
Sponsor Acceptance
Approved by the Project Sponsor:
____________________________________________
Project Sponsor: AIT
2
Date: _____________________