Project Charter AIT Waste Water Treatment System


AIT Waste Water Treatment Facility: Project Charter

Document History Version

Description

Date

Author

Checked

Number

1

Original

27/01/13

i

TS

NMcH


AIT Waste Water Treatment Facility: Project Charter

Table of Contents Document History............................................................................................................................... i 1.0

General Information.............................................................................................................. 1

2.0

Project Approval.................................................................................................................... 1

3.0

Project Deliverables .............................................................................................................. 1

4.0

Project manager .................................................................................................................... 2

5.0

Project plan ........................................................................................................................... 2

6.0

Project timeline ..................................................................................................................... 3

7.0

Budget Estimate .................................................................................................................... 3

7.1 Funding Source ...................................................................................................................... 3 7.2 Estimate ................................................................................................................................ 3 Sponsor Acceptance ........................................................................................................................... 4

i


AIT Waste Water Treatment Facility: Project Charter

List of Figures Figure 1 – Project timeline ................................................................................................................................. 3

ii


AIT Waste Water Treatment Facility: Project Charter

List of Tables Table 1 – Project deliverables ............................................................................................................................ 2 Table 2 – Estimated project cost ....................................................................................................................... 3

iii


AIT Waste Water Treatment Facility: Project Charter

1.0

General Information

Project Title:

Brief

Project

Description:

AIT Waste Water Treatment System The project involves the construction of an onsite waste water treatment facility at Athlone Institute of Technology to treat waste from the campuses engineering building.

Prepared By:

Trevor Smullen

Date:

27/01/13

2.0

Version:

001

Project Approval

This Charter approves the commencement of the construction of a sequence batch reactor treatment system for waste water produced by the engineering building at Athlone Institute of Technology, to cater for a maximum loading of 500 persons (250 p.e.). A project plan will be developed and submitted to the Project Sponsor for approval.

Commencement of project

activities will begin upon approval of the project plan and the resources to execute it by the Project Sponsor. Included in the project plan are to be a scope statement; schedule; cost estimate; budget; and provisions for scope, resource, schedule, communications, quality, risk, procurement, and stakeholder management as well as project control.

3.0

Project Deliverables

The purpose of the AIT waste water treatment system project is to treat waste from the campuses engineering building, which represents approximately 400 persons currently and with an expected increase to 500 persons in three to five years. This will act to significantly reduce the annual discharge to the municipal sewer. The project deliverables are outlined in table 1 below.

1


AIT Waste Water Treatment Facility: Project Charter

Table 1 – Project deliverables

Deliverable

Description

Discharge reduction

Significant reduction in discharge flows from the institute to the municipal sewer system

Monetary savings

As a result of discharge reduction there will be a reduction in the annual cost incurred for the discharge of waste water

Environmental sustainability

Increase the environmental sustainability of the institute by onsite treatment of waste water

High grade effluent

Production of high grade effluent from the proposed treatment system

4.0

Project manager

The Project Manager, Trevor Smullen, is hereby authorised to interface with management as required, negotiate for resources, delegate responsibilities within the framework of the project, and to communicate with all contractors and management, as required, to ensure successful and timely completion of the project. The Project Manager is responsible for developing the project plan, monitoring the schedule, cost, and scope of the project during implementation, and maintaining control over the project by measuring performance and taking corrective action.

5.0

Project plan

A completed project plan will be developed and submitted to the Project Sponsor for approval by Monday 11th February 2013. Once the project commences, work on the project will be performed according to the schedule provided in the approved project plan. The Project Manager will obtain approval from the Project Sponsor for any schedule changes which impact the project completion milestone.

2


AIT Waste Water Treatment Facility: Project Charter

6.0

Project timeline

Figure 1 below depicts an estimated timeline of the project

Figure 1 – Project timeline

7.0

Budget Estimate

7.1 Funding Source Funding of the AIT Waste Water Treatment System project will be sought by AIT from the department of education or similar funding streams.

7.2 Estimate This section provides a summary of estimated spending to meet the objectives of the AIT Waste Water Treatment System project as described in this project charter. This summary of spending is preliminary and subject to adjustment. Preliminary costing for the project is provided in table 2. Table 2 – Estimated project cost

Overall cost

Consultancy

50,000

Contractor

100,000

Treatment System

60000

Contingency

100000

Total

310,000

3


AIT Waste Water Treatment Facility: Project Charter

Sponsor Acceptance

Approved by the Project Sponsor:

____________________________________________

Project Sponsor: AIT

4

Date: _____________________