Public-Private Partnerships in Urban Bus Systems

Page 64

46 | Public-Private Partnerships in Urban Bus Systems

TABLE 5.2  Definition

of direct project risks

CATEGORY

RISK

Land availability and acquisition

Land is not available at the time of commercial closure (APMG International 2018g) or delays the delivery of publicly provided infrastructure.

Permits and licensing

The public authority has difficulty obtaining permits and licenses for the project.

Stakeholder management

Incumbent service providers undermine, disrupt, or challenge the project during implementation, or delays in implementing the structure of their participation delay their start of operations.

Change in scope of work

An unforeseen change in project design or service requirements delays implementation (APMG International 2018c).

Environmental and social

Any unforeseen change in the project scope may exacerbate a negative environmental (APMG International 2018e) or social outcome. The design or intervention needs to be modified (or stopped) because the design does not include appropriate consideration of stakeholders’ social or environmental concerns.

Financing

Project costs and risks are miscalculated, the private party assumes an unintended risk, or the government assumes a risk it is not well suited to assume absent a guarantee, which increases financing costs.

Financial closure

A failure to raise the finance required, to satisfy conditions precedent, or to complete negotiations with lenders delays or prevents financial closure.

Collection, fraud

Users willingly avoid payment, or drivers or other employees divert cash revenues from the project.

Collection, affordability

Payment becomes unaffordable for users (APMG International 2018f).

Financial coordination

Project revenues are not distributed correctly due to errors in the revenue system, a complicated payment mechanism, or fraud.

Changes in ownership

A new controlling shareholder is not as capable as, and does not have the capacity of, the original partner (APMG International 2018l).

Construction delays

Construction does not get completed on time for operations to commence.

Geotechnical

Unexpected geological or geotechnical conditions affect designs (APMG International 2018h).

Completion and commissioning

There is a failure to meet an outcome as prescribed (in relation to infrastructure, rolling stock, systems, technology) or a component as commissioned in order to meet the completion acceptance criteria, thereby causing a delay in earning revenues (APMG International 2018d).

Interface risk

Operations begin without all project components (infrastructure, rolling stock, systems, technology) ready to operate together.

Quality and level of service

Services are not available for use or do not meet the quality or expected performance levels, which includes providing enough buses to satisfy demand and meeting schedules for the private partner (APMG International 2018a).

Demand

Demand forecasts are inaccurate, or the project does not comply with assumptions used to estimate demand.

Congestion

Government fails to secure infrastructure or technology, such as exclusive lanes for bus rapid transit (BRT) systems, or to provide priority signaling for buses in free-flow or BRT systems, which results in congestion.

Transportation fares

The project fails to generate enough revenue to cover the cost of operations and debt service because fares are lower than anticipated or are not being updated.

Technology obsolescence

Certain equipment becomes inadequate for the service, or the service becomes outdated (APMG International 2018k).

Fuel

Fuels (or electricity) required are not consistently available in required quantities at reasonable prices.

Competition from incumbent

There is unplanned competition from informal transportation services or incumbent operators whose services should have been restructured. continued


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

A.16 Lessons learned from the business collaboration agreements in Singapore

10min
pages 179-186

partnership

5min
pages 188-190

A.13 Lessons learned for urban mobility in Port-au-Prince, Haiti A.14 Lessons learned from the TransOeste bus rapid transit project in

2min
page 175

C.4 Essential elements of an operation concession contract

2min
pages 192-195

A.15 Lessons learned from the business collaboration agreements in Medellín, Colombia

2min
page 178

Rio de Janeiro, Brazil

5min
pages 176-177

A.11 Lessons learned from the Metrobús-Q System in Quito, Ecuador A.12 Lessons learned from the Avanza Zaragoza concession in Zaragoza,

2min
page 173

Spain

3min
page 174

A.8 Lessons learned from the SYTRAL integrated public transportation system in Lyon, France

2min
page 170

A.9 Lessons learned from the DART Phase I bus rapid transit project in Dar es Salaam, Tanzania

3min
page 171

Cali, Colombia

2min
page 169

Acapulco, Mexico A.7 Lessons learned from the Metrocali bus rapid transit project in

3min
page 168

Monterrey, Mexico A.6 Lessons learned from the Acabús bus rapid transit project in

5min
pages 166-167

Mexico City, Mexico A.5 Lessons learned from the Ecovía bus rapid transit project in

3min
page 165

Bogotá, Colombia A.4 Lessons learned from the Metrobús bus rapid transit project in

5min
pages 163-164

A.2 Lessons learned from the Transantiago bus rapid transit project in Santiago, Chile A.3 Lessons learned from the TransMilenio bus rapid transit project in

3min
page 162

in Lima, Peru

5min
pages 160-161

11.2 Situations affecting economic equilibrium A.1 Lessons learned from the Metropolitano bus rapid transit project

2min
page 156

Economic and financial elements

2min
page 155

Institutional and regulatory elements

7min
pages 152-154

11.1 Remuneration arrangements and incentives

4min
pages 150-151

Technical elements

1min
page 149

Setting up subsidies

4min
pages 145-146

Funding sources

9min
pages 141-144

Private financing instruments

12min
pages 135-139

10.1 Summary of the World Bank Group’s instruments

2min
page 140

Structuring a project’s capital

4min
pages 131-132

Model 4: Private finance and operation of electric buses

2min
page 125

Model 1: Bundled private finance and operation of buses

1min
page 115

bundled or unbundled

2min
page 122

Topical bibliography

5min
pages 108-114

Macroeconomic risks

1min
page 101

Topical bibliography

4min
pages 96-100

7.13 International lessons for achieving quality and level of service

2min
page 89

7.8 International lessons for managing fare evasion and cash risk

2min
page 85

7.7 International lesson for managing affordability risk

2min
page 84

7.1 International lessons for acquiring land

2min
page 80

Planning

1min
page 79

6.5 International lessons for defining technology components

2min
page 77

6.2 International lesson for dealing with incumbent operators

2min
page 71

5.1 Categories and types of direct risk, organized by project stage

2min
page 63

5.2 Definition of direct project risks

2min
page 64

Dealing with incumbent operators

1min
page 69

Identifying project risks

2min
page 62

Overview and guiding principles

1min
page 61

Institutional and regulatory elements

2min
page 56

Fiscal capacity

2min
page 55

Implement punctual infrastructure-related interventions

2min
page 47

Technical elements

2min
page 54

Support private sector initiatives to promote user-friendly technologies

2min
page 46

References

4min
pages 50-53

References

3min
pages 43-45

and Tendering

2min
page 41

2.2 Examples of the objectives and restrictions of key stakeholders

2min
page 42

References

2min
pages 39-40

public or private

2min
page 31

1.2 A public-private partnership: Three reasons why

2min
page 36

Notes

2min
page 38

What is a public-private partnership in urban bus systems?

4min
pages 29-30

Notes

2min
page 24

References

0
pages 25-26

Further discussion

2min
page 37

Key Messages

5min
pages 22-23
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.