Group 5_Kaira Looro Women's House Project

Page 79

4.1.4

Cistern Construction

By: Yuzki Wang

Courtyard cistern construction consists of 8 steps: 1. Excavation Excavate a pit in dimension of 2.7m in height, 5.5m in length and 5.5m in width 2. Floor construction Base construction with plain concrete and a layer of coarse gravel underneath for a firm bottom. Concrete reinforced with mesh reinforcement. Leave concrete 8-12 hours to cure 3. Brick laying Lay bricks on four sides to make solid walls. Leave 100-200mm space between brick walls and the pit for later side reinforcement. Mortar brick in ratio of 1:4 (1 cement : 4 sand) 4. Concrete render Water brick walls before starting concrete rendering to encourage better bind between cement and bricks. Render bricks with concrete mixture in ratio of 1:3 (1 cement : 3 sand) along with 400-500 ml of waterproofing. Double coat brick walls to achieve better durability. Each coat is let to cure for 8-12 hours. 5. Beam construction Set up temporary popping and formwork for beam construction. Pour concrete into formwork and let it cure for 12-16 hours. 6. Top construction Apply recycled timber shuttering on top of beams along with recycled cardboards and mesh reinforcement. Set up formwork for top construction and allow for access points. Bind and tie the shuttering with metal wire. Pour concrete in ratio of 1:2:4 (1 cement: 2 sand :4 coarse gravel). Let concrete set for 10-12 hours then apply pond curing. Remove formwork after a minimum of 10-12 days 7. Side reinforcement Place reinforcement bars in the gap between the pit and brick walls, pour concrete in a ratio of 1:2:4 and let it sit for 8-12 days. 8. Opening construction Lay bricks around the cistern access opening. Use mortar in ratio of 1:4

ABPL2077 Humanitarian Construction 2021

79


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

5.4 Waste Treatment

2min
pages 92-93

5.2 Vegetation

4min
pages 86-90

7.0 References

9min
pages 95-101

5.1 Food Security

4min
pages 84-85

5.0 Landscape Design Considerations

2min
page 83

4.2 Programme

2min
page 81

4.3 Cost Proposal

2min
page 82

4.1.5 Cistern Construction

1min
pages 79-80

3.4 Consequence of Design

0
page 64

3.1 Building Form and Function

0
pages 58-59

2.4 Conflict in Use

1min
page 51

2.5 Land Tenure, Women and Future Suggestions

5min
pages 52-54

2.2 Land Tenure Context and Arrangements

4min
pages 47-48

2.1 Site Location

0
page 46

2.3 Land Tenure Risks

4min
pages 49-50

2.0 Land Tenure Considerations

3min
page 45

1.4.6 Women’s Health Considerations

5min
pages 34-37

1.4.4 Wastewater Treatment

2min
pages 27-28

1.4.2 Water Treatment

4min
pages 22-24

1.3 Stakeholder Involvement

10min
pages 8-15

1.4 WASH

2min
pages 16-17

1.6 Gender Equality Priorities and Actions

8min
pages 41-44

1.4.1 Water Access

5min
pages 18-21

1.2 Community Engagement Plan

7min
pages 4-7
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.