2020 Eugene Parks and Recreation Bond and Levy Report

Page 17

Bond Project Expenditures The following table shows all bond project related expenditures.

Bond Project Expenditures Project

Total Project Budget

Bond Project Budget

FY19 Total Project Expenses

FY20 Bond Fund Expenses

FY20 Other Fund Expenses

FY20 Total Project Expenses

Total Project Expenses to Date

Park Renovation Projects Tugman Park

$1,000,000

$750,000

$269,543

$232,020

$19,206

$251,226

$520,769

Berkeley Park

$1,000,000

$1,000,000

$50,653

$54,638

$16,796

$71,434

$122,087

Trails and Habitat Projects Amazon Park Running Trail renovation

$1,535,000

$750,000

$72,393

$300,284

$127,528

$427,812

$500,205

Delta Ponds Loop Trail completion

$1,350,000

$480,000

$117,407

$175,767

$79,582

$255,349

$372,756

Ridgeline Habitat restoration

$150,000

$150,000

$4,079

$16,775

$

$16,775

$20,854

Amazon Creek Habitat restoration

$2,850,000

$400,000

$9,111

$

$36,978

$36,978

$46,089

Safety/Lighting Improvements West Bank Path lighting

$1,000,000

$1,000,000

$30,700

$83,843

$

$83,843

$114,543

Alton Baker Park (Pre’s Trail) Lighting

$750,000

$750,000

$

$29,056

$13,195

$42,251

$42,251

$1,200,000

$

$19,037

$825

$19,862

$19,862

$1,500,000

$

$2,968

$

$2,968

$2,968

School District Partnerships Churchill/YSP Community Center Planning

$1,200,000

Repairing and Improving Infrastructure Restroom Improvements

$1,500,000

Community Centers, Pools & Fields Echo Hollow Pool renovation

$12,248,667

$7,963,667

$499,805

$3,763,423

$52,195

$3,815,618

$4,315,423

Campbell Community Center renovation

$5,700,000

$3,850,000

$562,770

$2,084,245

$67,387

$2,151,632

$2,714,402

Sheldon Pool renovation

$10,145,000

$7,445,000

$42,330

$179,345

$8,337

$187,682

$230,012

Sports Complex Phase 1

$4,000,000

$775,000

$

$19,579

$1,448

$21,027

$21,027

Striker Field

$3,500,000

$267,000

$87,227

$740

$108,904

$109,644

$196,871

Riverfront Park

$14,000,000

$500,000

$1,848,855

$

$3,966,213

$3,966,213

$5,815,068

$933,500

$933,500

$255,779

$51,360

$

$51,360

$307,139

$3,850,651

$7,013,079

$4,498,593

$11,511,672

$15,362,323

New Park Development

Bond Issuance Costs Total Spending

17