2024 Kaufman County Transportation Report

Page 1

Kaufman County Transportation Report January 2024

PROJECT STATUS UPDATES • • • • • • • • • • • • • • • • • • • • • •

Project Funding Summary ........................................................................... 2 FM 548 (IH 20 to US 80) ................................................................................ 3 FM 548 North: Phase I................................................................................. 4 FM 548 North: Phase II................................................................................ 5 US 80/SH 205/FM 148 ................................................................................. 6 FM 148 Bypass ............................................................................................ 8 FM 1641 .................................................................................................... 10 FM 741 ...................................................................................................... 12 Helms Trail................................................................................................. 13 SH 205 South ............................................................................................. 14 I-20 Frontage Roads Terrell ....................................................................... 15 I-20 Frontage Roads Kaufman .................................................................. 16 US 80 Widening ......................................................................................... 17 US 80 (FM 460 to Spur 557) ......................................................................... 19 Outer Loop ............................................................................................... 20 FM 740 ...................................................................................................... 21 US 175 Grade Separations Kemp .............................................................. 22 US 175 Safety Improvements Kaufman .................................................... 23 SH 34-US 175 Connector Road .................................................................. 24 US 175 Feasibility Study ............................................................................ 25 Glossary of Acronyms ............................................................................... 26 TxDOT Funding Categories ........................................................................ 27

Kaufman County Transportation Report January 2024

Prepared by:

1


| PROJECT FUNDING SUMMARY | PROJECT

COUNTY

OTHER

TOTAL COST

FM 548 (IH 20 to US 80)

$2,880,808

TBD

$78,259,337

FM 548 North: Phase I

$5,985,718

$97,857,169

$103,842,887

FM 548 North: Phase II

$1,542,811

$23,702,962

$90,851,936

US 80/SH 205/FM 548

$931,624

$16,313,170

$17,244,793

FM 148 Bypass

$7,175,278

$41,274,874

$64,722,157

FM 1641

$5,559,918

$6,668,519

$77,844,134

FM 741

$552,693

$4,974,241

$132,975,923

Helms Trail

$1,680,492

$0

$39,930,492

SH 205 South

$934,255

$255,924,112

$256,858,367

I-20 Frontage Roads Terrell

$0

$8,500,000

$202,041,250

I-20 Frontage Roads Kaufman

$0

$8,500,000

$221,825,281

US 80 Widening

$567,169

$151,379,089

$151,946,258

US 80 (FM 460 to Spur 557)

$0

TBD

$726,000,000

Outer Loop

$7,779,903

TBD

$974,304,199

FM 740

$3,447,966

TBD

$76,044,787

US 175 Grade Separations Kemp

$1,552,105

TBD

$91,038,308

US 175 Safety Improvements Kaufman

$639,500

TBD

$8,639,500

SH 34-US 175 Connector Road

$3,920,943

$0

$3,920,943

US 175 Feasibility Study

TBD

TBD

TBD

TOTAL

$45,171,183

$616,094,135

$3,318,290,552

Kaufman County Transportation Report January 2024

Prepared by:

2


FM 548

2019 CSJ:

2588-01-025; 1091-02-025

Schematic Approval:

June 2024

Limits:

from IH 20 to US 80

Environmental Approval:

January 2025

Project Description:

reconstruct FM 740 and FM 548 to 4lane divided urban roadways and possible grade separation at UPRR crossing near Broad Street

ROW Acquisition Complete:

*

Estimated Construction Cost:

$75,378,529

Utility Relocations Complete:

*

Funding:

*

100% Plans:

*

Commissioner:

Skeet Phillips, Precinct 2

Ready to Let Date:

*

Engineer & Key Contact:

Jacobs, Abe Bekele

Let Date:

*

TxDOT Project Manager:

Jordan Mrayyan

Start Date:

*

Current Activity: • • • • •

Design: Jacobs submitted revised 90% schematic on December 4, 2023, with updated proposed ROW and reduced sound walls. TxDOT recommended further design refinements and to reduce proposed ROW at certain locations along FM 548. Jacobs is refining design and developing pre-final schematic. Jacobs continued finalizing noise analysis and technical reports with requested updates from TxDOT. Jacobs held a coordination meeting with TxDOT PM on December 19, 2023. Coordination meeting with TxDOT held on January 8, 2024, to discuss recommendations from TxDOT’s internal ROW footprint meeting. Environmental: Jacobs continued effort toward preparation of environmental reports.

Kaufman County Transportation Report January 2024

Prepared by:

3


FM 548 North: Phase I

2013 CSJ:

2588-01-022

Schematic Re-Approval:

December 28, 2018

Limits:

From north of US Highway 80 to Windmill Farms Blvd.

Environmental Clearance:

July 3, 2019

Estimated Construction Cost:

$93,294,641

ROW Acquisition Completed:

January 2023

Funding:

$93,294,641: CAT 2

Utility Relocations Complete:

October 2024

Project Description:

Widen existing 2-lane, undivided facility to a 4- to 6-lane, divided facility

100% Plans:

December 2023

Commissioner:

Skeet Phillips, Precinct 2

Ready to Let Date:

October 2024

Engineer & Key Contact:

Westwood, Mark Zoellner, Mark Schluter

Let Date:

*

TxDOT Project Manager:

Gutema Gebrial

Construction Start:

*

Current Activity: •

PS&E: The final plans have been shelved until project letting. Utilities: o AT&T: Anticipate start of relocations in February 2024. o Atmos: Relocation plans approved. Anticipate start of relocations in February 2024. o Farmers Electric Co-Op: Relocated poles to new ROW on two parcels. Additional pole plans with relocations under TxDOT review. o City of Forney: Revised relocation plans have been approved by TxDOT. Anticipate putting out for bids after approval by city council. o High Point WSC: Addressing TxDOT comments to relocation plans. o NTMWD: Anticipate submittal of preliminary relocation plans in February 2024. Anticipate start of relocations in May 2024 and completion in August 2024. o Oncor: Anticipate start of relocations in February 2024. o Suddenlink: Relocation plans approved. Anticipate start of relocations after Oncor and FEC completion. o Peoples Telephone Co-Op: Relocation plans under review by TxDOT.

Kaufman County Transportation Report January 2024

Prepared by:

4


FM 548 North: Phase II

2013 CSJ:

2588-01-017 (Kaufman County) 2588-02-008 (Rockwall County)

Schematic Re-Approval:

December 28, 2018

Limits:

From Windmill Farms Blvd. to SH 205

Environmental Clearance:

July 3, 2019

ROW Acquisition Completed:

August 2022

Utility Relocations Complete:

February 2025

100% Plans:

March 2024

Estimated Construction Cost: Funding: Project Description:

$85,525,922

$69,958,514: Kaufman County segment $15,567,408: Rockwall County segment

$19,919,759: CAT 2 $8,448,796: Kaufman County segment $11,470,963: Rockwall County segment Widen existing 2-lane, undivided facility to a 4 to 6-lane, divided facility

Commissioner:

Skeet Phillips, Precinct 2

Ready to Let Date:

February 2025

Engineer & Key Contact:

Burns & McDonnell, Tony Schmitt

Let Date:

*

TxDOT Project Manager:

Gutema Gebrial

Construction Start:

*

Current Activity: • •

PS&E: The 95% plan review was completed on November 6, 2023, and comments were returned to consultant. The comment resolution meeting was held on December 18, 2023. Burns & McDonnell is currently addressing review comments. Utilities: Anticipate distribution of NORA letters. Plans adequate and SUE provided to utilities.

Kaufman County Transportation Report January 2024

Prepared by:

5


US 80/SH 205/FM 148

2013 CSJ:

0095-04-069

Schematic Approval:

January 26, 2018

Limits:

US 80 and SH 205/FM 148 intersection

Environmental Clearance:

August 23, 2018

Construction Cost:

$15,839,362

ROW Acquisition Complete:

October 2019

Funding:

$9,349,949: CAT 6

Utility Relocations Complete:

October 2022

Project Description:

Intersection improvements to increase the capacity and improve safety at the intersection and the adjacent railroad crossing on FM 148 south of US 80, including full traffic signalization

100% Plans:

December 10, 2021

Commissioner:

Terry Barber, Precinct 3

Let Date:

March 4, 2022

Engineer & Key Contact:

Othon, Jeff Love

Construction Start:

October 3, 2022

TxDOT Project Manager:

Lane Selman

Construction Completion:

August 2024

Current Activity: •

Construction: The project was awarded to Sterling Delaware Holding Company, Inc. with a low bid of $15,839,362.17, at 23.12% over engineer’s estimate. There are 504 working days and 24 months of barricades. See attached TxDOT construction report.

Kaufman County Transportation Report January 2024

Prepared by:

6


TxDOT Monthly Project Report for Kaufman County Date of report: January 15, 2024 Report prepared by: Cody Jolley, P.E. Control: 0095-04-069, ETC. Limits: Intersection SH205/FM148/US80 Project: CM2022(384) Highway: US 80 Contractor: Sterling Delaware Holding Company, Inc. TxDOT Area Engineer: Lane Selman, P.E. TxDOT Assist. Area Engineer: Nic Wadlington, P.E. TxDOT Project Manager: Chris Bruner Contractor’s Superintendent: Kent Bergthold

Phone: (972) 962-3617 Phone: (972) 962-3617 Phone: (972) 962-3617 Phone: (972) 963-0262

Date Work Began: October 3, 2022 Anticipated Completion Date: August 30, 2024

Current activities: Asphalt pavement. Concrete pavement. Work zone striping. Narrative description of last month’s activities: Asphalt pavement. Placing embankment. Placing flexbase. Installing drainage. Narrative description of activities planned for next month: Asphalt pavement. Concrete pavement. Excavation/Removals. Placing embankment. Placing flexbase. Installing drainage. Traffic issues: None Plans for changes in traffic patterns: None Item(s) of work currently controlling project completion: None Other items of significance: None

Kaufman County Transportation Report January 2024

Prepared by:

7


FM 148 Bypass

2013 CSJ:

0751-05-001; 0197-03-078

Schematic Approval:

June 30, 2017

Limits:

From US 175 to south of FM 3039

Environmental Clearance:

April 26, 2019

Construction Cost:

$60,049,999

ROW Acquisition Completed:

November 2020

Utility Relocations Completed:

February 2023

Project Description:

Construct new 2-lane undivided facility; add connection to proposed US 175 frontage road project

100% Plans:

April 28, 2023

Commissioner:

Tommy Moore, Precinct 4

Ready to Let Date:

March 2023

Engineer & Key Contact:

Halff Associates, David Burkett

Let Date:

June 27, 2023

TxDOT Project Manager:

Lane Selman

Construction Completion:

November 2025

Funding:

$38,777,994

CAT 2: $33,777,994 CAT 3: $5,000,000

Current Activity: •

Utilities: With the exception of utilities that will complete relocations at the FM 148 Bypass/US 175 intersection, if necessary, during the US 175 South Frontage Road construction, utilities are clear of construction. Construction: The project was awarded to Granite Construction Company with a low bid of $60,049,998.99 at 3.74% above the engineer’s estimate. There are 35 months of barricades and 735 working days. See attached TxDOT construction report.

Kaufman County Transportation Report January 2024

Prepared by:

8


TxDOT Monthly Project Report for Kaufman County Date of report: January 15, 2024 Report prepared by: Cody Jolley, P.E. Control: 0197-03-078 Limits: 2.3 miles west of FM 148 Bypass to East of FM 148 Bypass Project: F 2023(704) Highway: FM 148 Contractor: Granite Construction Company TxDOT Area Engineer: Lane Selman, P.E. TxDOT Assist. Area Engineer: Nic Wadlington, P.E. TxDOT Project Manager: Jacob Self Contractor’s Superintendent: Brad Tyrer

Phone: (972) 962-3617 Phone: (972) 962-3617 Phone: (972) 962-3617 Phone: (972) 358-3712

Date Work Began: October 2, 2023 Anticipated Completion Date: November 6, 2025

Current activities: Removing existing pavement. Remove existing concrete rip rap. Bridge substructure construction. Narrative description of last month’s activities: Install temporary drainage. Construct temporary pavement. Shift traffic to Phase 1A configuration. Narrative description of activities planned for next month: Remove existing pavement. Install permanent drainage. Bridge substructure construction. Traffic issues: None Plans for changes in traffic patterns: None Item(s) of work currently controlling project completion: None Other items of significance: None

Kaufman County Transportation Report January 2024

Prepared by:

9


FM 1641

2013 CSJ:

1217-01-019; 2588-01-020

Schematic Re-Approval:

April 26, 2021

Limits:

From FM 548 to FM 148

Environmental Clearance:

August 31, 2021

-019: $64,458,505 -020: $2,157,192

ROW Acquisition Completed:

September 2023

-019: $500,000: CAT 7 -020: $500,000: CAT 7

Utility Relocations Complete:

March 2025

Estimated Const. Cost:

$66,615,697 $1,000,000

Funding: Project Description:

Widen to a 4-lane divided (6-lane ultimate) urban facility

100% Plans:

June 2024

Commissioner:

Skeet Phillips, Precinct 2

Ready to Let Date:

March 2025

Engineer & Key Contact:

LTRA, Massoud Manesh

Let Date:

*

TxDOT Project Manager:

Ron Wang

Construction Start:

*

Current Activity: • •

PS&E: LTRA continues working toward the 90% plan submittal. LTRA continues work on roadway plans, drainage/culvert plans, retaining wall layouts, TCP layouts, and signal design. Utilities: Status of utilities in conflict is below. o AT&T: Consultant is working to prepare relocation plans. o Atmos: Consultant is working to prepare relocation plans. o Forney: Reviewing conflict matrix. o o o

Gulf South Pipeline: Reviewing conflict matrix. Oncor: Reviewing plans. NTMWD: Reviewing conflict matrix.

Kaufman County Transportation Report January 2024

Prepared by:

10


Peoples Telephone: Reviewing plans. Suddenlink: Reviewing plans. Talty SUD: Consultant is working to prepare relocation plans. o TVEC: Consultant is working to prepare relocation plans.

o o o

Kaufman County Transportation Report January 2024

Prepared by:

11


FM 741

TxDOT CSJ:

1092-01-021

Schematic Approval:

July 20, 2022

Limits:

From US 175 to FM 548

Environmental Clearance:

March 28, 2023

Project Description:

Widen and reconstruct from a 2-lane urban divided to a 4/6-lane urban divided

ROW Acquisition Complete:

September 2024

Estimated Constr. Cost:

$127,448,989

Utility Relocations Complete:

March 2026

Funding:

*

100% Plans:

November 2025

Commissioner:

Skeet Phillips, Precinct 2 and Tommy Moore, Precinct 4

Ready to Let Date:

March 2026

Engineer & Key Contact:

HNTB, Kyle Riley

Let Date:

*

TxDOT Project Manager:

Solomon Robelie

Construction Completion:

*

Current Activity: • PS&E: The PBLR was approved by Bridge Division on November 8, 2023. • The 30% plan set review has been complete, and comments returned to HNTB. Comment resolution meeting held on December 15, 2023. • HNTB submitted plans adequate for utility coordination on December 22, 2023. • ROW: There are 125 parcels to acquire. There are 4 parcels in appraisal, 19 parcels in negotiations, 82 parcels in ED, and 20 parcels in possession.

Kaufman County Transportation Report January 2024

Prepared by:

12


Helms Trail

2019 CSJ:

*

Schematic Approval:

August 2024

Limits:

from IH 20 to US 80

Environmental Clearance:

November 2024

Project Description:

widen from 2-lane rural to 4-lane divided urban

ROW Acquisition Complete:

*

Estimated Construction Cost:

$38,250,000

Utility Relocations Complete:

*

Funding:

*

100% Plans:

*

Commissioner:

Skeet Phillips, Precinct 2

Let Date:

*

Engineer & Key Contact:

Dannenbaum, William Gladbach

Construction Start:

*

Current Activity: • • • • • • •

Design: Dannenbaum continued Design Summary Report. Dannenbaum continued Route Evaluation Technical Report. Dannenbaum continued Hydrology and Hydraulics efforts. Dannenbaum continued development of the 60% schematic. ROW: Dannenbaum continued creating proposed ROW requirements and mapping. SUE: Preliminary SUE efforts are complete. Environmental: Environmental field work is being scheduled. Culture resources is being conducted.

Kaufman County Transportation Report January 2024

Prepared by:

13


SH 205 South

TxDOT CSJ:

0451-02-028 (Kaufman County) 0451-01-053 (Rockwall County)

Limits:

From US 80 to north of FM 549

Project Description:

Widen from 2-lane rural to 4-lane urban divided with allowance for ultimate 6 lanes

Estimated construction cost: Funding:

$229,132,567

-028: $122,573,837 -053: $106,558,730

$247,515,813

$44,046,699: CAT 2 $203,469,114: CAT 4

Environmental Approval: Environmental Re-eval:

July 3, 2018 (-028) May 1, 2019 (-053) April 12, 2019 December 22, 2021

ROW Acquisition Completed:

July 2023

Utility Relocations Complete:

-028: June 2025 -053: December 2024

100% Plans:

March 2024

Schematic Approval:

Engineer:

TxDOT

Ready to Let Date:

-028: June 2025 -053: December 2024

TxDOT Contact:

Suja Mathew

Let Date:

*

Current Activity: PS&E: TxDOT is working to address 95% plan review comments for the CSJ -028 (Kaufman County) segment. Comment resolution meeting held on December 19, 2023. • TxDOT is working to address 95% plan review comments for the CSJ -053 (Rockwall County) segment. Comment resolution meeting held on December 19, 2023. • Utilities: For CSJ -028: AT&T, Atmos, Dallas Water Utilities, Enterprise, FEC, High Point WSC, NTMWD, Oncor, Oncor Transmission, Oneok, Sprint, and City of Terrell are in conflict. • For CSJ: -053, utility relocations are being coordinated. • Status of -028 utilities in conflict: o AT&T: Relocation plans approved. Anticipate start of relocations in February 2024. o Atmos: Relocation plans approved. Working on utility agreement. o Dallas Water Utilities: Working with TxDOT on utility agreement. TxDOT approved relocation plans. o FEC: Anticipate submittal of relocation plans in March 2024. o High Point WSC: Addressing TxDOT comments to relocation plans. o NTMWD: Addressing TxDOT comments to relocation plans. o Oncor: Relocation plans approved. o Oneok: Working with TxDOT to execute utility agreement. Permit approved. o Sprint: Relocations underway. Anticipate clearance in March 2024. o Terrell: Revised relocation plans under review at TxDOT. •

Kaufman County Transportation Report January 2024

Prepared by:

14


TxDOT

I-20 Frontage Roads – Terrell

CSJ:

0095-14-035; 0495-01-071

Schematic Approval:

January 31, 2019

Limits:

From CR 305 to SH 34

Environmental Approval:

April 10, 2020

Project Description:

Add continuous frontage roads

ROW Acquisition Completed:

October 2023

Estimated construction cost:

$202,041,250

Utility Relocations Complete:

August 2025

Funding:

$8,500,000: CAT 4

100% Plans:

December 2024

Engineer & Key Contact:

LTRA

Ready to Let Date:

August 2025

TxDOT Project Manager:

Marlena Kelly

Let Date:

*

Current Activity: • • •

PS&E: LTRA submitted plans adequate on November 1, 2023. LTRA submitted 60% PS&E on November 10, 2023. The 60% PS&E plan set was submitted for District review on December 22, 2023. PBLR was approved by Bridge Division. Utilities: Utility coordination kick-off meeting to be held. Status of utilities in conflict below: o AT&T: Reviewing TxDOT plans and conflict matrix. o Atmos: Reviewing TxDOT plans and conflict matrix. o Enterprise: Reviewing TxDOT plans and conflict matrix. o Oncor: Reviewing TxDOT plans and conflict matrix. o Oneok: Reviewing TxDOT plans and conflict matrix. o Optimum: Reviewing TxDOT plans and conflict matrix. o Rose Hill SUD: Consultant reviewing TxDOT plans and conflict matrix. o City of Terrell: Reviewing TxDOT plans and conflict matrix. o TVEC: Consultant reviewing TxDOT plans and conflict matrix. o Zayo: Reviewing TxDOT plans and conflict matrix.

Kaufman County Transportation Report January 2024

Prepared by:

15


TxDOT

I-20 Frontage Roads – Kaufman

CSJ:

0095-14-036

Schematic Approval:

January 31, 2019

Limits:

From west of FM 741 to Big Brushy Creek

Environmental Approval:

April 10, 2020

Project Description:

Add continuous frontage roads

ROW Acquisition Complete:

January 2024

Estimated construction cost:

$221,825,281

Utility Relocations Complete:

August 2025

Funding:

$8,500,000: CAT 4

100% Plans:

December 2024

Engineer & Key Contact:

EST

Ready to Let Date:

August 2025

TxDOT Project Manager:

Ron Wang

Let Date:

*

Current Activity: • • • •

PS&E: District completed review of the 30% plan submittal. Comment resolution meeting scheduled for February 9, 2024. EST resubmitted bridge layout on January 16, 2024. TxDOT District is reviewing. Meeting scheduled for January 25, 2024, to discuss. EST provided revised hydraulic report on November 15, 2023, and TxDOT Dallas District is reviewing. ROW: There are 84 parcels to acquire. There are: 1 parcel in negotiations, 1 parcel in ED, and 82 parcels in possession.

Kaufman County Transportation Report January 2024

Prepared by:

16


US 80 Widening

TxDOT CSJ:

0095-03-080; -085

Schematic Approval:

August 24, 2018

Limits:

From Lawson Road to FM 460

Environmental Approval:

April 13, 2020

Project Description:

Reconstruct and widen from 4 to 6 main lanes and reconstruct 2/4-lane discontinuous to 4/6-lane continuous frontage roads

ROW Acquisition Completed:

February 2022

Estimated Construction Cost:

$128,902,801

Utility Relocations Complete:

June 2023

100% Plans:

March 2022

$146,274,571

Funding:

$139,443,588: CAT 4; $1,882,263: CAT 6 $3,944,904: CAT 10; $1,003,816: CAT 11

Engineer & Key Contact:

Halff Associates, Jeremy McGahan

Let Date:

June 29, 2022

TxDOT Project Manager:

Lane Selman

Construction Completion:

September 2026

Current Activity: •

Construction: The project let on June 29, 2022. The project was awarded to Webber, LLC, with a low bid of $128,902,801.08, at 7.40% above engineer’s estimate. There are 42 months of barricades and 1,086 working days. See attached TxDOT construction report.

Kaufman County Transportation Report January 2024

Prepared by:

17


TxDOT Monthly Project Report for Kaufman County Date of report: January 15, 2024 Report prepared by: Cody Jolley

Control: 0095-03-080 Limits Lawson Road to FM 460 Project: F 2022(793) Highway: US 80 Contractor: Webber, LLC TxDOT Project Manager: Chris Bruner Contractor’s Superintendent: Robert Cox Contractor’s Superintendent: Javier Zubillaga

Phone: (972) 962-3617 Phone: (214) 406-9600 Phone: (346) 224-6877

Date Work Began: April 4, 2023 Anticipated Completion Date: September 30, 2026

Current activities: Constructing drill shafts/columns. Setting bridge deck panels. Placing bridge beams. Pouring bridge deck westbound. Installing drainage. Embankment. Flexbase. Constructing temporary pavement. Placing asphalt on permanent pavement. Narrative description of last month’s activities: Constructing drill shafts/columns. Setting bridge deck panels. Placing bridge beams. Pouring bridge deck westbound. Installing drainage. Embankment. Flexbase. Constructing temporary pavement. Narrative description of activities planned for next month: Constructing drill shafts/columns. Setting bridge deck panels. Placing bridge beams. Pouring bridge deck westbound. Setting panels/forming bridge deck FM 460. Installing drainage. Embankment. Flexbase. Placing asphalt on temporary pavement. Traffic issues: None Plans for changes in traffic patterns: None Item(s) of work currently controlling project completion: None Other items of significance: None

Kaufman County Transportation Report January 2024

Prepared by:

18


US 80 (FM 460 to Spur 557)

TxDOT CSJ:

0095-03-106; 0095-04-076

Schematic Approval:

January 2024

Limits:

From FM 460 to Spur 557

Environmental Approval:

March 2024

Project Description:

Widen and add lanes

ROW Acquisition Complete:

August 2025

Estimated Construction Cost:

$726,000,000

Utility Relocations Complete:

February 2027

Funding:

*

100% Plans:

*

Engineer & Key Contact:

*

Ready to Let:

February 2027

TxDOT Project Manager:

Nelson Underwood

Let Date:

*

Current Activity: • •

Schematic: The schematic was approved on January 2, 2024. Environmental: A public hearing has been scheduled for Thursday, February 8, 2024, from 5:30 – 7:30 p.m. at the Rhodes Intermediate School Cafeteria (775 Innovation Boulevard, Forney, TX 75126). Public meeting materials will be available online at www.keeptimovingdallas.com/projects/ushighways/us80-spur557 through February 23, 2024.

Kaufman County Transportation Report January 2024

Prepared by:

19


Outer Loop

2019 CSJ:

0918-11-109

Schematic Approval:

January 2025

Limits:

From SH 205 to IH 20

Environmental Approval:

August 2025

Project Description:

6-lane freeway with continuous 2/3-lane frontage roads

ROW Acquisition Complete:

*

Estimated Construction Cost:

$966,504,296

Utility Relocations Complete:

*

Funding:

*

100% Plans:

*

Engineer & Key Contact:

HDR, Brian Swindell

Ready to Let Date:

*

TxDOT Project Manager:

Liang Ding

Let Date:

*

Current Activity: • • • • • •

Design: HDR continues coordination with project stakeholders. HDR also continues coordination with TxDOT, Halff Associates (Rockwall County Outer Loop project), NCTCOG, and ITS. HDR is continuing efforts on the 60% schematic design. Right-of-entry letters for environmental investigations, survey, and SUE are being compiled. HDR is beginning coordination for VE study. Anticipate a VE study to be held the week of March 25, 2024. Environmental: TxDOT has approved this project for an EA in lieu of an EIS. Utilities: Data collection for Level D SUE continues.

Kaufman County Transportation Report January 2024

Prepared by:

20


FM 740

2019 CSJ:

2249-01-009; 1091-01-023

Limits: Project Description:

from Kaufman/Rockwall County Line to Ranch Road reconstruct FM 460 and FM 740 to 4-lane divided urban roadways

Schematic Approval:

August 2025

Environmental Approval:

December 2025

ROW Acquisition Complete:

*

Estimated Construction Cost:

$72,596,821

Utility Relocations Complete:

*

Funding:

*

100% Plans:

*

Commissioner:

Skeet Phillips, Precinct 2

Ready to Let Date:

Engineer & Key Contact:

Atkins, Alex Amponsah

Let Date:

*

TxDOT Project Manager:

Hiruy Berhe

Construction Start:

*

Current Activity: • •

• •

Design: Atkins continued drainage efforts. Atkins continued preparation of 30% schematic and submitted for review on December 15, 2023. Atkins to hold coordination meeting with City of Forney. Atkins continued efforts to refine traffic analysis of various intersections along FM 740 corridor. Bi-weekly coordination meetings with Atkins, TxDOT, and ITS are ongoing.

Kaufman County Transportation Report January 2024

Prepared by:

21


2019

US 175 Grade Separations – Kemp

CSJ:

0197-05-063

Schematic Approval:

November 2023

Limits:

from Business US 175 to FM 1895

Environmental Approval:

November 2024

Project Description:

construct interchange at BUS 175 and FM 1895

ROW Acquisition Complete:

*

Estimated Construction Cost:

$89,486,203

Utility Relocations Complete:

*

Funding:

*

100% Plans:

*

Commissioner:

Tommy Moore, Precinct 4

Ready to Let Date:

*

Engineer & Key Contact:

Halff, Melanie Cleavelin

Let Date:

*

TxDOT Project Manager:

Liang Ding

Construction Start:

*

Current Activity: • •

Schematic: TxDOT approved the schematic on November 13, 2023. Environmental: Efforts on environmental documentation and technical reports continue. Awaiting TxDOT approval on two environmental reports. Coordinating with TxDOT regarding May 2024 STIP revision to include project.

Kaufman County Transportation Report January 2024

Prepared by:

22


2019

US 175 Safety Improvements – Kaufman

CSJ:

0197-04-086

Schematic Approval:

NA

Limits:

from 0.5 miles south of SH 34 to Fair Road

Environmental Approval:

December 2023

Project Description:

relocate existing crossovers, construct U-turns and deceleration lanes

ROW Acquisition Complete:

NA

Estimated Construction Cost:

$8,000,000

Utility Relocations Complete:

NA

Funding:

*

100% Plans:

March 2024

Commissioner:

Mike Hunt, Precinct 1

Ready to Let Date:

August 2024

Engineer & Key Contact:

Quiddity, David Unger

Let Date:

August 2024

TxDOT Project Manager:

Hiruy Berhe

Construction Start:

*

Current Activity:

Design: Quiddity completed the 95% PS&E plan set and submitted to TxDOT for review on December 8, 2023. Anticipate receipt of TxDOT comments on the 95% plans in January 2024. Environmental: Project received environmental clearance on December 13, 2023.

Kaufman County Transportation Report January 2024

Prepared by:

23


SH 34-US 175 Connector Road CSJ:

Schematic Approval:

NA

Environmental Approval:

NA

Project Description:

Construction of new 4-lane divided (Roadway No. 1) and new 4-lane undivided (Roadway No. 2) connection roads for new Kaufman County justice center

ROW Acquisition Complete:

*

Construction Cost:

$3,450,478

Utility Relocations Complete:

*

Funding:

2019 County Bond Funds

100% Plans:

November 2023

Engineer & Key Contact:

TNP, Matt Atkins

Let Date:

November 2023

TxDOT Project Manager:

NA

Construction Start:

*

NA Roadway No. 1: south of US 34 to new

Limits:

Roadway No. 2

Roadway No. 2: southwest of US 175 to new Roadway No. 1

Current Activity: • •

Construction: Kaufman County advertised bids for the construction of the project, with bids due on November 30, 2023. Pre-bid meeting was held on November 20, 2023. Pavecon Public Works, LP was the lowest bidder, with a bid of $3,450,477.70. The county awarded the project to Pavecon on December 19, 2023. Anticipate a pre-construction meeting to be scheduled.

Kaufman County Transportation Report January 2024

Prepared by:

24


US 175 Feasibility Study CSJ/Project ID:

A00190822

Schematic Approval:

*

Limits:

From west of FM 1389 (Kaufman County line) to east of SH 198 (Henderson County line)

Environmental Approval:

*

Project Description:

Feasibility study to investigate capacity improvements including main lanes expansion and addition of continuous frontage roads and new interchanges

ROW Acquisition Complete:

*

Estimated Construction Cost:

*

Utility Relocations Complete:

*

Funding:

*

100% Plans:

*

Engineer & Key Contact:

BGE, Hossein Hosseiny

Ready to Let Date:

*

TxDOT Project Manager:

Stephen Endres

Let Date:

*

Current Activity: • • • • •

Design: Traffic projections are under District/TTI review. BGE is continuing to develop alternatives, including evaluating design options for all grade separations and interchanges, to include interchange options for US 175 in City of Kaufman. TxDOT Dallas District directed BGE to further develop design with an urban typical section throughout the county to minimize ROW impacts. Public Involvement: BGE has met with Kemp, Mabank, Crandall, City of Kaufman, and NCTCOG. BGE to meet with Tarrant Regional Water District (Cedar Creek Lake owner). Previously scheduled public meetings on January 25, January 30, and February 1 have been canceled pending District review of and county input regarding proposed design.

Kaufman County Transportation Report January 2024

Prepared by:

25


Glossary of Acronyms • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • •

AADT – Annual Average Daily Traffic AFA – Advanced Funding Agreement ARPA – Archeological Resources Protection Act ASED – Annual Scope & Estimate Documentation CE – Categorical Exclusion (environmental clearance process for projects that do not involve significant environmental impacts) CLOMR – (FEMA’s) Conditional Letter of Map Revision Conformity – Federal requirement in nonattainment areas to conduct air quality analysis on projects, programs, and policies identified in transportation plans, transportation improvement programs, federally funded projects, or projects requiring federal approval CSJ – (TxDOT’s) Control Section Job Number EA – Environmental Assessment ED – Eminent Domain EIS – Environmental Impact Statement EPIC – Environmental Permits, Issues, and Commitments FONSI – Finding of No Significant Impact IAJR – Interstate Access Justification Request ICA – Interlocal Cooperative Agreement IFP – Initial Financial Plan MAPO – Meeting with Affected Property Owners MPO – Metropolitan Planning Organization MTP – Metropolitan Transportation Plan NCTCOG – North Central Texas Council of Governments NEPA – National Environmental Policy Act NOPC – Notice of Proposed Construction NORA – Notice of Required Accommodation NTTA – North Texas Toll Authority PBLR – Preliminary Bridge Layout Review PS&E – Plans Specifications and Estimate PUA – Possession and Use Agreement ROW – Right-of-Way RTC – Regional Transportation Council RTL – Read to Let (date project is clear for construction but lacks funding for actual let) RTR – Regional Toll Revenue (funds resulting from certain toll/managed lane projects in DFW region) RULIS – Right-of-Way, Utilities, Leasing, and Information System STBG – Surface Transportation Block Grant STIP – Statewide Transportation Improvement Program SUE – Subsurface Utility Engineering SW3P – Storm Water Pollution Prevention Plan TIA – Time Impact Analysis TPP – Transportation Planning and Programming TPWD – Texas Parks & Wildlife Department TTC – Texas Transportation Commission TxDOT – Texas Department of Transportation UTP – Unified Transportation Program VE – Value Engineering

Kaufman County Transportation Report January 2024

Prepared by:

26


TxDOT Funding Categories • • • • • • • • • • • •

CAT 1: Preventive Maintenance and Rehabilitation CAT 2: Metropolitan and Urban Area Corridor Projects CAT 3: Non-Traditionally Funded Transportation Projects CAT 4: Statewide Connectivity Corridor Projects CAT 5: Congestion Mitigation and Air Quality Improvement CAT 6: Structures Replacement and Rehabilitation (Bridge) CAT 7: Metropolitan Mobility and Rehabilitation CAT 8: Safety Projects CAT 9: Transportation Alternatives CAT 10: Supplemental Transportation Projects CAT 11: District Discretionary CAT 12: Strategic Priority

Kaufman County Transportation Report January 2024

Prepared by:

27


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.