Construction Analysis Assignment 3

Page 1

ABPL20033 - Construction Analysis, Semester 2 - 2018 Dr Alberto Pugnale – Subject coordinator Dr Sofia Colabella – Senior Tutor Dion Keech – Tutor Emma Kelly, 950391, 17.10.2018 Queenscliff House, T15 ASSIGNMENT 3

FLIPBOOK SECTION 3D: Layers of information


1. Structural Systems, below ground The proximity to the beach and the views available at the site influenced the design of the house significantly. The layout of the rooms, the large glazing throughout the house and the open plan living areas capture the exteriour and enhance the feeling of it being a beach house, which was requested by the clients. The harsh environmental conditions and the large spans required for large glazing dictated the use of material, eg. galvanised steel.

Vertical Structural systems, below ground Horizontal

Pad Footing 300 diameter, 150 mm deep poured concrete

Stumps reinforced 100 x 100mm prefabricated concrete

Mass Concrete Pad 600 x 600 x 400mm poured concrete

Columns square hollow sections galvanised steel to be later installed

Stripfooting reinforced 450 x400m poured concrete 4 wire mesh, starter bars

Stumps 100 x 100 prefabricated concrete

Mass concrete pad

Pad footing

ABPL20033 - 2018, Emma Kelly | 950391 |T 15, Dion Keech

Strip footing reinforced concrete


2. Structural Systems, above ground

Primary Structure

Steel frame - Universal Beam, Parallel Flange Channel, Eaqual Angle Concrete - insitu wall Timber - brearers, joists (groundfloor)

Secondary Structure

Timber - stud walls, rafters, soldiers, battens, I- joists

Bracing

Strap bracing - 30 x 0.8 galv. steel Ply bracing - 6mm F11 plywood

Ground Floor Horizontal Structural Systems, above ground

First Floor Vertical Roof

The steel framing was designed by the engineers in order to achieve large spans and allow for large glazed areas. This is to capture the view and visually connect the building parts. A timber floor was later introduced in order to achieve the necessary green star rating, as the new planning scheme allowed for a loophole.

Rafters 2/240 x 45 Hyspan Laminated Veneer Lumber at 1200 centres

Square Hollow Section 89 x 89 x 4 Parallel Flange Universal Beam Channel 125 x 65 250 37

Stud wall 90 x 45 studs at 600 centres

Soldiers

Battens 90 x 35 MGP 10 at 900 centres

I-joists 360x 90 at 450 centres

Strap bracing 30 x 0.8 galv steel

Square Hollow Section 150 x 150 x 6 galvanised steel

Insitu concrete wall Floor joist 45 x 90 MGP10 Bearers 2/45x90 MGP

Ply bracing 6 mm ply

ABPL20033 - 2018, Emma Kelly | 950391 |T 15, Dion Keech


3. Internal (non-load bearing) partitions Fixed Internal Partitions

Movable

Internal non load bearing studwalls Plasterboard lining Frosted glazing - “Matelux� Toughened grade A safety glass pivot doors

Plasterboard ceiling

Non-loadbearing stud walls

The internal partitions separate different areas according to their program. They mediate the privacy of the occupants and organise every day life. The frosted glazing separating the en-suite shower and the corridor is an interesting way to separate a very private from a very public area. It blurres the lines of what is intimite and a thouroughfare. The plasterboard lining allows for even paint finishes that can be changed over the years, the pivot doors allow for a smooth opening in the walls without a bulky frame. All these methods make for a smooth and simple finish thorughout the house.

Frosted glazing

Pivot door

Frosted glazing Pivot door

Plasterboard walls

ABPL20033 - 2018, Emma Kelly | 950391 |T 15, Dion Keech


4. Environmental Protections

galvanised steel to prevent corrosion due to moisture Horizontal

Waterproofing

Environmental Protections

paint - Tasman Terrasand clear hydrophobic sealer for concrete walls sarking - 55mm Bradford foil

Vertical Insulation

plasterboard - waterproof in wet areas roof - R4.0 gold batts between rafters, 55 mm Bradford foil walls- R3.2 Bradford Soundscreen batts, 2 x R1.6 batts floor - 2.5 Bradford Soundscrren batts

The largest part of the environmental protections throughout the house are being kept invisible from the outside. The insulation and sarking is within the building envelope. The sealing paint finish on the concrete wall is translucent and doesn’t interfere with the concretes appearance.

55 mm Bradford non-combustable blanket insulation

R 4.0 Bradford gold batts between rafters R 2.5 Bradford Soundscreen batts Hydrophobic sealer on concrete

R 3.2 Bradford Soundscreen batts

R 2.5 Bradford Soundscreen batts

ABPL20033 - 2018, Emma Kelly | 950391 |T 15, Dion Keech


5. Mechanical and electrical systems

hot water - shower, sinks

The electrical layout is made to meet the occupants needs, e.g.. power-plugs or lightswitches next to the bed, plugs in the kitchen and bathroom for appliances etc. The hydronic heating system is chosen to have the least influence on every day life as it is non intrusicive. Also, it is laid out to allow for an optimal use of energy when heating the rooms. Positioning the trenches under the windows allows for a thorough heat transfer throughout the rooms. As both systems are hidden within the building fabric, the spaces didn’t need to be organised in accordance to the mechanical and electrical systyems. The trenches also allow for the large glazing areas, as they don’t need walls to be mounted on.

Water Supply

Essential services

cold water - shower, sinks, toilet sewage - from sinks, toilet,shower, etc. to sewer line

Elecricity

Electrical layout throughout roof structure for eventual downlights or pendant lights

hydronic heating - closed loop system hot water supply, heat emitted through radiator, cold water return connection from grid to property, to switch board, supply throughout house on seperate circuits controlledand manageable by fuses

Boiler or other hot water system

Hydronic heating trench and connections

Trench

Trench

boiler and trench connection Electrical layout to powerplugs in bedroom

Cold and hot water connection tosho

Cold and hot water connection to kitchen

hydronic trench and distribution (retrieved from: www.purmo.com)

SWITCHBOARD HW HOT WATERSYSTEM

HH HYDRONIC HEATING CLOSED LOOP

hydronic trench running along window front

HW HH

ABPL20033 - 2018, Emma Kelly | 950391 |T 15, Dion Keech


6. Physical Enclosures systems

Boxgutter

Metal roofsheet

138mm x 19mm dressed, ship lapped, Spotted Gum cladding

Horizontal

External cladding

cement

“Matrix” Façade Panels, 8mm thick, 2390x590 panels

Vertical

Roof

roof sheets

Metal roof “Trimdeck Hi Ten” sheets

Windows

gutter

150 x 300 boxgutter

parapet capping

galvanised steel capping finished with dulux paint

frame, sill, glazing, flashing

tassie oak frame

Enclosure Systems Wooden cladding to enclose and seal building

wood

blackbutt sill Window and Sliding doors

toughened glass Kitchen bench

The physical enclosure system consists of different components. The timber cladding greys over time and reflects the intention of the architects to create a building that blends in with the sanddunes and create a true beach house. The cement cladding on the kitchen indicates a change of program in the inside. The gutter is hidden within the roof structure and maintains a thin roof profile, also enabling the building to sit within the landscape almost naturally. Roof sheet Windows and Sliding door

Parapet capping

Boxgutter

Cement cladding

Spotted gum cladding

ABPL20033 - 2018, Emma Kelly | 950391 |T 15, Dion Keech


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.