Iv-Consult
PETROGAS HALFWEG-PLATFORM NORTH SEA
THE PLAN OF APPROACH (Part 1 by Jeroen Kwakernaak (Petrogas E&P Rijswijk), Niels van Berlaer (DEME Offshore) and Ad van den Dool (Iv-Consult Papendrecht)
A collision with a tankship caused considerable damage to a platform that was being prepared for decommissioning. This navigational error sounded alarm bells: was the platform still safe, and how could it be removed? Introduction The Halfweg gas field is a natural gas field in the North Sea on the Dutch continental shelf 20 km west of Den Helder. It was discovered in 1968. The total gas yield of the field was estimated to be 2.53 BCM (Billion Cubic Metre). The exploitation of the Halfweg field began in May 1991 with test drilling Q1/23. After a successful test, the well was temporarily abandoned due to a planned tie-back (connection to an existing production facility). This tie-back was realised with the installation of the Halfweg platform in May 1995 (fig. 1); well Q1/123 became production well A1. In addition to well A1, two new wells were drilled: Halfweg A2 and A3, completed in September 1995. Gas could now be pumped via the Halfweg platform to the so-called Photo: DEME Offshore
WGT (West Gas Trunkline) and then to the gas treatment installation in Den Helder. On the 1st of January 2006, gas production from the Halfweg platform to the WGT was terminated. The Halfweg platform now only produced gas Photo: Petrogas
to supply power onboard two existing platforms
Fig. 1
and functioned as a so-called gas compression platform.
Installation of the Halfweg platform in 1995
English translation of 3 articles in Dutch magazine 'Bouwen met Staal' nr. 271 – 273 (2019/2020)
1
Platform removal preparation It was formally decided to end production on the 6th of June 2016, after which the drilled wells had to be closed under the 'P&A campaign' (Plug and Abandonment). This operation was completed in November 2017. At the same time, preliminary preparations for the platform removal, such as cleaning the pipelines, were implemented. Furthermore, in preparation for the platform removal, Iv-Consult was commissioned to perform a FEED study (referred to later in this article). Based on this study, the request for the actual removal of the platform was issued in November 2017 to several offshore contractors.
Fig. 2 Proposed lifting configuration (Iv-Consult)
FEED study The study aimed to investigate the structural
The removal of the gravity base was also examined.
integrity of the platform during removal and sea
However, during the engineering process, it was
transport. Originally, the platform was designed
decided to cut the piles just above the gravity
as a self-installing and de-installing platform. De-
base, remove them and leave the gravity base
installing would have to be done through a reverse
behind on the seabed.
installation procedure, whereby the gravity base (concrete caisson at the base of the platform)
Tankship collision
would be de-ballasted to create buoyancy and the
Towards the end of the tender process, a collision
platform lowered with strand jacks. Unfortunately,
with a chemical tanker (Elsa Essberger) occurred
it appeared this method could no longer be
on New Year's Eve 2017, causing significant
used, and an alternative had to be devised, for
damage to the platform. As a result, all plans were
which various options were reviewed. Ultimately,
frozen, and immediate action was taken to assess
removing the platform with a Heavy Lift Vessel was
and determine the damage. To facilitate this, a
chosen. After determining the correct weight and
campaign was organised from a Survey Support
location of the centre of gravity, the most suitable
Vessel, involving the following:
lifting configuration could be determined based
►► Visual underwater inspection with an ROV
on the as-built data. The structural integrity of the
(Remotely Operated Vehicle) to determine
platform could then be demonstrated with lifting
damage to the platform leg connections at the
simulations (the platform legs would be cut loose
gravity base and damage to the gravity base
prior to the lifting operation and lifted separately).
itself. ►► Visual inspection of the platform with a UAV
A hoisting configuration with three spreader bars was chosen to prevent the platform from being
(Unmanned Aerial Vehicle) taking detailed
'crushed' by the internal horizontal forces that
images of the platform and legs. ►► 3D scanning of the platform and legs to
occur with a four-point single hook lift (fig. 2). The
determine deformations.
legs could easily be lifted by using an ILT (Internal Lifting Tool) or, for example, with welded-on lifting points. The contractor could determine this at a later stage.
2
The tender was postponed due to the collision, and an investigation was initiated to determine the structural integrity of the damaged platform (Fig. 3).
Fig. 3
Damaged Halfweg platform during inspection
Structural Integrity Fig. 4
Two important questions raised after the collision: ►► Is the structure of the platform still safe?
SACS-model (Iv-Consult)
predicted corresponded with the observed plastic
►► How can we safely remove the damaged
deformations onboard the platform. A validated
platform?
calculation model formed the basis for the followup research: the design of efficient reinforcements
Two critical questions were raised following the
to safely remove the platform.
collision:
►► Is the platform structure still safe?
Decommissioning study
►► How can we safely remove the damaged
With all defects now identified, the design for the
platform?
reinforcements of the platform necessary for safe lifting and transport could be created. A plan also
To answer these questions, it was essential to obtain
had to be developed for the method and sequence
the best possible and detailed insight into the
of cutting the platform legs.
extent of the damage - which required access to
The tankship initially collided with the legs at the
the platform. Based on the inspections conducted,
front of the platform, then passed and hit the
preliminary calculations were performed on the
underside of the platform and finally halted after
residual strength and stability of the platform,
colliding with the rear legs. As a result, the legs
revealing no immediate danger of collapse; the
suffered plastic deformation, which necessitated
platform was safe to visit. However, the helideck
extra care when cutting the legs to prevent
was damaged to an extent that made it unsafe
the sudden release of internally stored energy,
to land a helicopter on the platform. Instead, a
potentially leading to an unsafe situation.
vessel with a motion-compensated walkway was
To prevent the legs from 'shocking' during the
used to conduct detailed on-site examinations
cutting operation, shear keys were used to prevent
(visual inspection and NDE (Non-Destructive
the leg parts from moving apart. Cutting the legs
Examination)). All collected data could now be
altered the static system of the structure (the one-
combined with the point cloud from the 3D scan,
piece legs were now interrupted), and the order
thus providing an overall impression of the damage.
of cutting appeared to have a major influence on
A comparison was subsequently formed with the
the release of the stored energy. Of course, the aim
results of the preliminary calculation model (fig. 4a
was to release this energy as gradually as possible.
and 4b). In particular, it was examined whether the locations where (local) damage of the structure was
3
The lower deck of the topside required special
Offshore operations (such as cutting the legs)
attention as it was a requirement not to work
were simulated and practised on land to avoid
below the topside: this would prove very expensive
surprises offshore. DEME Offshore selected
since scaffolding and rope access technicians were
the Heavy Lift Jack-Up Vessel Apollo with an
needed. As a result, the structural parts of the lower
800-tonne crane for the lifting operation. This
deck, damaged by the collision (deformation of
crane vessel formed a stable working platform and
several beams and torn-off connections), had to be
was crucial for an efficient operation during the
reinforced from above (fig. 5).
winter period (two winter storms occurred during the operation). Once the welding work for the reinforcements and the installation of all lifting aids was complete, the legs were cut just below the platform using abrasive water jet cutting. In Photo: DEME Offshore
one lift, the platform was removed and placed on
Temporary reinforcements of the top deck
Photo: DEME Offshore
Fig. 5
the deck aboard the Apollo (Fig. 6).
Fig. 6
Platform ready for hoisting with Apollo
Removal of platform legs Photo: DEME Offshore
The four legs were cut using diamond wire
Fig. 7
cutting, the preferred method as the legs still contained secondary steel and risers that needed cutting simultaneously. Following arrival in
Removal of the legs
Vlissingen, the platform and piles could be transferred to the quay of the company Hoondert,
Preparation and removal platform
and the dismantling could commence. In April
In August, DEME Offshore was contracted as an EPRD
2019, the entire platform, including the piles,
contractor by Petrogas E&P Netherlands. However,
was dismantled, and contaminated parts were
even before the contract was signed, all parties
disposed of via regular waste flows.
closely collaborated in the engineering and offshore visits to determine the best strategy for removing the platform. Due to the tight schedule, it was decided to involve the MWS (Marine Warranty Surveyor) in the process as soon as possible so that any questions/ queries could be discussed as early as possible. Because all parties had agreed the platform would be removed at the end of 2018, all disciplines worked concurrently.
4
IMPACT COLLISION (text part 2 by Edwin Belder and Ad van den Dool (Iv-Consult Papendrecht)
At the moment of collision, the Elsa Essberger, with a full weight of about 5,000 tons, had a speed of about 6 m/s and successively hit three columns (legs), the foundation of the crane and the lower deck of the platform (fig. 8). Fortunately, the platform was unmanned and the vessel crew was not injured. The ship suffered significant damage to the bow, port, and starboard sides (fig. 8a). This incident sounded a major alarm with the Coast Guard, who immediately inspected the situation. Following the release, the Elsa Essberger sailed to the port of Rotterdam for further questioning by judicial authorities. The co-owner (and operator) of the platform, Petrogas E&P Netherlands, was informed and took immediate action to have the structural safety of the platform examined. Iv-Consult was familiar with the platform and was, therefore, requested to assess the structural safety, including an
Fig. 8a Elsa Essberger, after collision
investigation to identify possible hidden damage via Finite Element Method (FEM) analyses. In addition, the platform would be photographed with a drone (Bluestream [3]), and an ROV inspection of the Gravity Base Structure (GBS) and the legs would also be conducted.
Fig. 8b Locations of the main impacts
5
Pd
denting force (kN);
Fy
yield stress of the tube (N/mm2);
T
wall thickness of the tube (mm);
X
depth of the dent (mm);
D
diameter of the tube (mm);
Edent absorbed energy in the dent (Joule). Fig. 9
Dent measurements in the point cloud
Structural safety Due to reasonable doubts about the structural
Three main impact loads were defined for the
safety in combination with the upcoming spring
calculation model, each in a slightly different
storms, simplified analyses in SACS (Offshore
direction. The ship changed direction after the first
Structural Analysis and Design Software) were
impact and thus moved towards the second leg
initially performed, adding hinges in the legs at the
and hit crane pedestal. It was decided to perform
points where major dents were visually identified.
a 1st-order and a 2nd-order geometric non-linear
This schematisation was combined with wind load
(GNL) analysis for each step, impact 1 to 3. A push-
and wave action from a 1-year storm. The coarse
over analysis was performed, simulating impact
analyses showed that the platform was safe in
1 to 3. Initial impact forces were put on an intact
these given conditions. However, the preliminary
model, the overloaded members were identified
calculation results were insufficient to place an
and subsequently deactivated. This resulted in
inspection team onboard the platform.
the deformed position of the platform simulating
The regular procedure for such calamities is to
the permanent deformation after the first impact.
withdraw the offshore certificate, excluding access
This deformed model was then used as the base
to the platform. Therefore, the structural safety had
model for the next impact. This was repeated for
to be proved with more detailed calculations.
all impact stages. The final deformations (Figures
Bluestream had processed the drone images into
10 and 11) could be validated with the point cloud.
a 3D point cloud that provided more detailed
The final resulting geometry was then combined
information about the damage and permanent
with maximum wave, wind and sea current loads
deformations (Fig. 9). The point cloud helped
for a return period of 1 year. It was concluded
assess the size of the dents in the platform legs as a
that, although the collision had caused significant
basis for determining the impact loads.
permanent deformation, this would not lead to a global nor local collapse of the structure.
6
Fig. 10 SACS FEM-model
Fig. 11 Stress plots FEM-model
Gravity Base Structure
Onboard inspection
A separate analysis was performed for the Gravity
The onboard inspections were conducted in May
Base Structure (GBS) based on the maximum
and June 2018 by a team from Petrogas, Iv-Consult
impact load. The legs, fixed with dowels and a
and Bluestream. All damage was documented
base plate in the GBS, were substantially damaged
based on an inspection protocol, and large-scale
just above the 6-metre-high GBS. During the ROV
Non-Destructive Testing (NDT) research was
inspection, it was confirmed that the structure
conducted (Eddy currents and ultrasonic research).
had failed locally at the GBS-leg transition: the
During the inspection, it became clear that several
legs were buckled locally. However, no cracks in
secondary beams of the lower deck and helideck
the steel or the concrete were observed. For more
were partly torn from the web of main girders. An
insight into the structural capacity of the GBS, it
undesirable situation because these secondary
was also decided to analyse the GBS with FEM
girders should guarantee the lateral stability of the
software. This revealed the structural capacity of
main girders. Furthermore, two bottom flanges
the GBS was sufficient. The offshore certificate was
of the lower deck main girders were plastically
re-issued based on these analyses, thus allowing
deformed in a sideways direction over several
inspection onboard the platform.
metres (Figs. 12 and 13). The pedestal of the crane had collapsed entirely, and the crane itself was several degrees out of alignment. Despite everything, the condition of the platform was encouraging but not safe enough to be removed. Therefore, it was decided to reinforce the platform locally to enable a safe removal.
Fig. 12 Deformed main girder
Fig. 13 Location of deformed main girder
7
Strengthening the platform The primary purpose of the reinforcements was to make the platform suitable for lifting and sea transport to a decommissioning yard in the Netherlands. However, reinforcing offshore has
z = 0,145
0,264
its limitations. Locations above the water and below the lower deck are challenging to reach and
x=1
can be dangerous. This resulted in a secondary objective: designing all reinforcements above deck
y = 0,221
measurements in mm
to facilitate safe offshore work. Furthermore, it was
Fig. 15 Rotation of the main girder
also decided to design the reinforcements where possible with fillet welds to ensure the time for –2,70454
performing NDT was kept to a minimum. Where possible, S355N was chosen because of its better weldability; this was the best choice given the
5,43155
offshore conditions. 13,5676
The crane pedestal had a dent halfway between 18,9917
the decks (fig. 13, top, right). Therefore, to prevent
21,7037
any further deformation, it was decided to support 1 gedeukte kraanfundering
the foundation at that spot with a brace to the
2 HEB 200
deck (fig. 14). 3main buis 168,3x8
Fig. 16 Analysis of the main girder
4 plaat S235
At the lower deck and helideck, the secondary
1
beams, damaged at the welded connection to
2
the main beams, were reinforced with welded
22
5 33
54
T-stubs (fig. 17). Since the secondary beams were
100
originally designed as torsional buckling restraints for the main girders, the main girders were 392
additionally examined with restraints at different
3
positions.
50
700
200 16 200
300
4
12
50
3000
A
Fig. 14 Reinforcement of crane foundation: 1. Dented crane foundation, 2. HEB 200, 3. Tube 168,3x8, 4. Existing deck plate S235
1
3 724
A 2
The lower deck's deformed main beam (Fig. 12,
1 2 3 4
13, 15 and 16) was analysed in Ansys according to DNV-GL-RP-C208 and C204 to exclude the
130
possibility of lateral-torsional buckling of this UB
UB 838x292x176 UB 356x171x45 1/2IPE 500 R = 25 (typ.)
95
3
184
838x292x176, from which the web and flanges were plastically deformed. Any buckling instability
12 4
50
of the structure during lifting and transport should be excluded.
Fig. 17 Reinforcements of secondary girders
8
DECOMMISSIONING (Part 3 by Fabio Amico and Ad van den Dool (Iv-Consult Papendrecht)
The Halfweg platform was removed in several steps. First, the top side was removed. For this purpose, the legs were cut 1.5 m below the lower deck of the platform and lifted one by one onto the crane vessel. The analysis for cutting the columns is highlighted in this final section. legs and fully cut legs. The calculations were performed using FEM, first to examine the overall behaviour of the platform and then focus on the locally damaged areas where high-stress spots were present. A FEM beam model was used to analyse the general behaviour, while non-linear plate models were used for the local checks. The analyses were conducted in accordance with DNV GL and the Eurocodes for members, plates, and shells. Order of cutting The order of cutting has a major influence on the platform's internal stress/load distribution. When a leg is partially cut, it can still transfer the internal axial shear forces and bending moments, depending on the seize of the cut. However, when the cut is almost complete, the internal forces generated by deformation migrate to the other
Cutting the legs
legs due to the change of the static scheme. The
The legs were first partially cut, just below deck:
increase in bending moment of the uncut legs
the initial cut. Shear keys were then placed on the
was significant (magnification factor of about 1.5).
inside of the legs and welded to the lower leg part.
A sensitivity analysis, in which various cutting
The legs were then cut through, and the platform
sequences were evaluated, was performed to
lifted. The cutting operation was done with
choose the most favourable cutting sequence.
waterjet cutting in combination with an abrasive.
When partially or entirely cut, the residual strength ultimately determined in which weather
Analysis method
conditions (wind, current and waves) the operation
The analysis to safely cut the legs included
could be performed safely (within the reference
detailed calculations that considered the material,
period of one year).
geometric nonlinearity, imperfections, residual stresses, deformations, and stored energy from the collision. Additionally, the effects of (reduced) loads from wind, waves and currents had to be analysed in two different scenarios: partially cut
9
From beam model to plate model A selection of load combinations was analysed to identify worst-case scenarios. Leg B3 was identified as having the highest stress concentrations; in addition, leg A3 was to be analysed, having the most critical global deformation just above the intended cut (Fig. 18). The leg was yielded locally (observed from the damaged paint layer). The internal and external loads from the global SACS FEM model (Fig. 19) were applied to the ANSYS plate model for those two critical legs (A3 and B3). Besides the loads, the associated boundary conditions (displacements and rotations) were modelled (Fig. 20). To cover uncertainties
B
around the cut location, three orientations of the initial cut were considered (skipped by 40°).
A
3 1
Fig. 18 Bulge on column A3 (source: Deme)
Fig. 19 Global FEM model
F,M
Cutting orientation A
1
Interface loads
1
2
2
Cut location
2
3
3
Displacements
Interface loads
1 Topside
F,M
3 ,
Cutting orientation B 40˚
Environmental loads 4
Reaction forces at GBS interface
SACS Global Beam Model
Cutting orientation C 80˚ 80°
4
ANSYS Beam Model of leg A3 and B3
ANSYS Plate Model of leg A3 and B3
Fig. 20 Load transfer (from SACS-beam model tot local ANSYS plate model)
10
Fig. 21 Zoom-in of FEM model at the cut location
Fig. 22 Determination of plastic design reference ratio rRpl (incremental analysis for ULS)
stress (N/mm2)
400 350
353 max.
300 250 200
112
150
0,0943 min.
100 50 0
0
0,01
0,02 0,03 strain (-)
0,04
0,05
Fig. 23 Material stress and strain relationship Fig. 24 Stress concentration of lifting eye
Fig. 25 Stress at shear key
FEM plate model
Nonlinear Analysis
In addition, the geometry of the FEM plate model
The purpose of the analysis was to investigate
also contained the measured deformations/
the strength of the legs at the weakest location
imperfections, such that the structure's response
during cutting. However, this location could not
could be predicted as accurately as possible. The
easily be predetermined and was based on the
legs were modelled with shell elements. The leg
condition with the greatest internal loads. After
axis followed the deformed shape of the SACS
all, the imperfection (dent) and the plastically
beam model (Fig. 19). The local dent was modelled
deformed areas had a considerably reduced
with the actual geometric deviations. The shear
residual capacity, although they did not belong to
keys and stiffeners were modelled with plate
the most heavily loaded leg part. Therefore, the leg
elements. The holes (lifting eyes), necessary for
as a whole had to be considered. The analysis was
removing the columns after removal from the
performed as MNIA (material nonlinear analysis
topside, were also modelled. The presence of the
with imperfections). The dent was modelled in the
holes delivered a significant impact and caused
FEM model using shell elements. The stress-strain
peak stress concentrations (Fig. 24). The mesh size
relationship of the material (Fig. 23) was elastic-
at the cut location was between 2 and 10 mm.
plastic. The checks were performed according to
An average mesh size of 50 mm was applied for
EN 1993-1-6 and DNVGL-RP-C208. According to the
the rest of the leg (Fig. 21). Various mesh sizes
theory for large deformations, second-order effects
were evaluated to obtain reliable results and a
were also taken into account with the geometrical
reasonable calculation time. The three cuts were
nonlinearity. An incremental analysis (Fig. 22) was
modelled in a way that would allow the edges
performed to determine the plastic resistance
to separate from each other. The three cutting
reference ratio rRpl, which, together with the elastic
orientations A, B and C (Fig. 20) were investigated
critical buckling reference ratio, resulted in the
with three different submodels.
overall slenderness λov and the reduction factor Χov.
11
ʎov = √(rRp/rRa) χov = f(ʎov, ʎov,o,βov,ŋov) ʎov
overall slenderness
ɑov
overall elastic imperfection reduction-factor
βov plastic range-factor ŋov
interaction exponent Fig. 26 Shear key after installation (source Deme Offshore)
The design buckling resistance ratio was determined and compared with the limit
250 200
with LBA (Linear Buckling Analysis) was included at
150
each load level, resulting in the most minor critical
100
stress on welds (Mpa)
according to EN 1993-1-6. A specific value check
buckling factor (Euler multiplier). The maximum allowable strain was considered to be 2%. Material properties and load factors were in accordance with DNVGL-RP-C208 and DNVGL-OS-C101.
50 0 –50 –100 –150 –200 0
Shear keys In each leg, three shear keys, each at an angle of
100 200 300 400 500 600 700 800 900 1000 weld lenght (mm)
comb
120 degrees, were mounted prior to the cutting
VM,all
operation. The primary purpose of shear keys is
all
the transfer of horizontal loads, however due to
combined stress acting on the weld throat normal stress acting on the weld throat allowable combined stress allowable normal stress allowable shear stress
friction, the shear keys were loaded vertically as
Fig. 27 Normal, shear and combined stress in the shear key weld
well. Because various load directions could occur
The methodology and cutting procedure were
during the lifting process, the application of box-
determined in close collaboration with the MWS
shaped cross-sections suitable for transferring
and Deme Offshore: the offshore execution and
torsion was chosen. The maximum horizontal load
the analyses should match and thus ensure the
between the cut parts of the legs in combination
release of potential energy on-site in the legs
with the maximum expected vertical pull-out
occurs gradually and not abruptly.
load (caused by steel-to-steel friction) was taken into account. Stiffeners along the leg wall were
The legs were cut in a predetermined order,
added to compensate for deformations in the wall
following the most efficient transition of the
and reduce the welds' stress level (fig. 25-26). The
static system. The cutting execution (Fig. 28) was
weld checks were performed by extrapolating the
performed with continuous monitoring of critical
normal and shear stresses along the weld (fig. 27)
zones whereby local and plastic deformations or
and were tested against the maximum permissible
settlements were predicted with the FEM models.
value according to the standard.
In this way, the risk of uncontrolled or undesired structure behaviour was minimised, and the operation was performed safely. References
12
Fig. 28 Cutting of the legs (source: Deme Offshore)
1. Petrogas E&P Netherlands (Rijswijk). Oil and gas operator, with shares in several platforms in the North Sea. 2. Iv-Consult (Papendrecht). An international engineering company, part of Iv-Groep, active in structural and mechanical engineering with a broad portfolio in offshore decommissioning and transport and installation. 3. Deme Offshore (Zwijndrecht, Belgium). Offshore and dredging contractor. 4. SACS. Offshore structural analysis and design software. 5. ANSYS. Engineering simulation and 3D design software.
13
Photo: DEME Offshore
About Iv-Consult Iv-Consult is specialized in the design of challenging steel and mechanical structures and has a long track record regarding offshore removal and transportation projects. Offshore inspections and 3D-scanning are part of our expertise.
About the authors Jeroen Kwakernaak (Petrogas E&P Rijswijk), Niels van Berlaer (DEME Offshore), Edwin Belder, Fabio Amico and Ad van den Dool (Iv-Consult Papendrecht)
Would you like to know more about the possibilities for your project? At Iv-Consult, we would be happy to share our ideas and knowledge and provide a quotation. Email Ad: a.d.vandenDool@Iv-Consult.nl or call: +31 88 943 2501
14
15
www.iv-consult.nl
16