REQUEST FOR QUOTATION (RFQ)
FOR
SUPPLY AND INSTALLATION OF 2 TPD ROTARY KILN GASIFICATION PILOT PLANT 2TPD 190821
FROM
Purchase Department, Karunya Institute of Technology and Sciences Karunya Nagar, Coimbatore Tamil Nadu 641114 Ph: 9487846521, 9442291395
REQUEST FOR QUOTATION (RFQ) FOR SUPPLY AND INSTALLATION OF 2 TPD ROTARY KILN GASIFICATION PILOT PLANT TABLE OF CONTENTS
1. OBJECTIVES OF THE RFQ ................................................................................................. 3 2. PROJECT OVERVIEW ......................................................................................................... 3 3. ABOUT KITS ........................................................................................................................ 3 4. TECHNICAL DETAILS ......................................................................................................... 4 4.1.
Technical Details.......................................................................................................... 4
5. SCHEDULE OF BIDDING PROCESS .................................................................................. 6 6. GENERAL TERMS OF BIDDING ......................................................................................... 7 7. CHANGE IN OWNERSHIP ................................................................................................... 8 8. COST OF BIDDING .............................................................................................................. 8 9. VERIFICATION OF INFORMATION ..................................................................................... 8 10. VERIFICATION AND DISQUALIFICATION .......................................................................... 8 11. CONTENT OF THE BIDS ..................................................................................................... 9 11.1. Part A - Technical Bid .................................................................................................. 9 11.2. Part B – Cost Bid ....................................................................................................... 10 12. BID SUBMISSION PROCESS ............................................................................................ 10 13. BIDDER EVALUATION CRITERION .................................................................................. 11 13.1. Technical Bid ............................................................................................................. 11 13.2. Cost Bid ..................................................................................................................... 11
LIST OF APPENDICES
Appendix 1
2TPD 190821
Scope of Supply
Page 2 of 11
REQUEST FOR QUOTATION (RFQ) FOR SUPPLY AND INSTALLATION OF 2 TPD ROTARY KILN GASIFICATION PILOT PLANT 1. OBJECTIVES OF THE RFQ Supply and installation of 2 TPD Rotary Kiln Gasification Pilot Plant The objective for the RFQ is to invite bids for supply of a 2 Tons Per Day (TPD) Rotary Kiln Gasification pilot plant at a designated site by Karunya Institute of Technology and Sciences (KITS) in Coimbatore and install it at site to make it fully operational. 2. PROJECT OVERVIEW Karunya Institute of Technology and Sciences (KITS) is setting up an R&D prototype of 2 TPD Rotary Kiln Gasification pilot plantfor converting non-recyclable plastic waste into high quality syngas. This system is designed and developed together with KITS’ Technology Partner, especially for KITS, Coimbatore to accomplish the project objectives outlined in its proposal submitted to the Department of Science and Technology, India under the program for waste management technologies. The primary goal of the proposed project is to improve the quality of syngas during the gasification of waste. Gasification is known to be the cleanest mode of energy recovery from plastic wastes with no negative impact on the environment. Rotary Kiln gasification system provides the most reliable, cost effective, and environmentally sound solution for converting nonrecyclable plastic waste into high calorific syngas. The flexibility of the system with respect to its ability to operate with varied source of waste with vastly different physical and chemical properties makes this system unique and versatile for broader application. Environmentally, the system is prevented from generating carcinogens, it is associated with producing least amounts of NOx, and the emission of sulfur, carbon monoxide, and particulates are maintained below the regulatory limits. 3. ABOUT KITS Karunya Institute of Technology and Sciences, was founded with the noble vision to raise professionals and leaders of high academic calibre and unblemished character, nurtured with a strong motivation and commitment to serve humanity. The institution is the fulfillment of the vision of its founders Late Dr. D. G. S. Dhinakaran and the present Chancellor Dr. Paul Dhinakaran. Established in 1986 as an Engineering College, it was granted an autonomous status in 1999 and declared Deemed-to-be University by the University Grants Commission (UGC) in recognition of its academic excellence by the Ministry of Human Resources Development under section 3 of the UGC Act, 1956 vide 2TPD 190821
Page 3 of 11
notification no 9-3-2000-U3 dated 23.6.2004 of the Government of India. Accredited by NAAC, the institution offers a wide array of Bachelors, Masters and Doctoral Degree programs in various branches of Engineering, Biotechnology, Food processing and Agricultural Sciences. From a humble beginning of 180 students, the institution has rapidly grown to 8491 students and 452 faculty representing 18 academic departments. In the three decades of service to higher education, Karunya Institute of Technology and Sciences has made significant progression in teaching learning, research and consultancy, innovation and transfer of technology, community service and value education. Translating the vision of the Founders into action, the institution is currently engaged in finding solutions to human problems in the four major areas such as Water, Food, Healthcare, and Energy through scientific and technological interventions. 4. TECHNICAL DETAILS 4.1. Technical Details The waste is thermally treated to convert the solid hydrocarbons into syngas. Syngas is composed primarily of carbon monoxide (CO) and hydrogen (H2) and smaller quantities of carbon dioxide, water, and methane, based on the input feedstock. The heat for this thermal treatment is generated by partial combustion of solid hydrocarbon with substoichiometric amount of air. By introducing only, a small amount of air amounting to far less than that would be required for complete combustion; the presence of free oxygen is eliminated in the gasifier. The syngas produced by this gasification process is a clean fuel that is combustible and can be used to generate electricity, steam or even hot air, or as a basic building block for chemical manufacturing. With appropriate approvals even hazardous waste processing will be possible. Syngas can then easily replace the conventional fuels to produce energy in the form of steam, which can used to produce electricity or air-conditioning or for effluent treatment. Alternatively syngas can be cleaned and then used to produce electric power or further chemical process to produce other chemicals. A schematic of the gasification system is shown in Figure 1. The gasifier or the first stage operated at 9800C and operates in the reducing regime unlike an incinerator where the mode is oxidation. The evolution of free chlorine radicals is arrested keeping the environment devoid of the primary contributors to the formation of carcinogens and the absence of free oxygen that prevents the waste bound nitrogen from being converted to NOX. The sulfur if any, present in the waste is converted to H2S. In the reducing regime, the chlorine present in the solid waste is converted into Hydrogen Chloride, which is easily removed during fuel gas cleanup before it is used as fuel. In contrast, the incinerator converts all the chlorines into carcinogens (Dioxins). Also, because of the reducing regime, all the nitrogen bound into the waste is converted to molecular nitrogen (N2). This improved system thus 2TPD 190821
Page 4 of 11
eliminates a profound source of NOX. In contrast, all the N2 bound in the solid wastes is converted into the oxides of nitrogen (NOx), which is a major link in the greenhouse gas production. The syngas produced from the solid waste has a calorific value of 850 to 1100 KCal/Nm3 compared to 8000 KCal/Nm3 for natural gas. When natural gas is utilized as fuel, the flame temperature is approximately 2200 oC. In contrast when fuel gas from Rotary Kiln Gasification is utilized as fuel; the flame temperature is less than 1500oC. Hence, the thermal NOx produced by syngas is an order of magnitude less than that from natural gas, because of the lower flame temperature. This is also an important environmental consideration in country’s continuous quest to reduce the emission of greenhouse gases from all sources. The sulfur likewise is removed from the fuel gas in the form of solid sulfides prior to its use, thereby further adding to the cleaner environment mandate.
SCIENTIFIC
GASIFICATION SYNGAS
Agriculture
BOILER
STEAM
Petroleum
GASIFICATION
Figure 1: Schematic of the Rotary Kiln Gasification System Figure 1. Schematic of the Rotary Kiln Gasification System
There will like like ash, ash, which which will be will initially planned into a scientific and There will be beother otheroutputs outputs be initially planned into landfill a scientific subsequently after analyzing the ash for its worthiness; it could be sold to cement factory; generating landfill and subsequently ashincludes for its the worthiness; could be sold additional revenue. The designafter of theanalyzing gasificationthe system preliminary itplant design for converting 2 TPD of non-hazardous wastes into clean fuel gas and the subsequent utilization of the syngas to cement factory for making fly ash bricks; generating additional revenue. The as mentioned above.
design of the gasification system includes the preliminary plant design for converting The design is carried out in sufficient details to enable accurate determination of the cost for the plant 2components TPD of non-hazardous wastes into clean fuel gas and the subsequent utilization of and comprises of: the syngas as mentioned above. • Process Flow Diagram • Process Description for the plant 2TPD 190821 Page 5 of 11 • Heat and Mass Balances and Potential Energy Output • Utility Requirements • Equipment list and specifications The overall material balance at the various components is shown in Figure 2. The 2 TPD Waste to energy system consists of 5 subsystems. These subsystems are 1) Feed Subsystem; 2) Gasifier Subsystem; 3) Gas
The 2 TPD Waste to Energy system consists of 5 subsystems. These subsystems are 1) Feed Subsystem; 2) Gasifier Subsystem; 3) Gas Cleanup Subsystem; 4) Steam Generation Subsystem and 5) Auxiliary Subsystem. The feed preparation and delivery equipment will be supplied by others. Further technical details including – 1) Process Flow Diagram 2) Process Description for the plant 3) Heat and Mass Balances and Potential Energy Output 4) Utility Requirements 5) Equipment list and specifications areprovided in the Appendix 1 of Scope of Supply. The appendix also includes the necessary design drawings of the pilot plant. It is the responsibility of the bidder to review, understand the technical requirements of the bid. Any deviation from the technical details may result in the bid being disqualified.Hence the bidder is advised to review the detailed scope of supply provided in the Appendix 1thoroughly. 5. SCHEDULE OF BIDDING PROCESS Date of RFQ Last date for receiving queries Reponses to the queries by KITS
23.08.2021 31.08.2021
Bid Due Date
15.09.2021
Opening of Bids
17.09.2021
Letter of Award(LOA)
05.10.2021
Validity of Bids
60 Days of Bid Due Date
Signing of Acceptance letter
Within 7 days of award of LOA
2TPD 190821
Page 6 of 11
6. GENERAL TERMS OF BIDDING 6.1. No Bidder shall submit more than one Bid for the Project. 6.2. For all technical details refer Scope of Supply in Appendix 1. Any deviation from the technical details may result in the bid being disqualified. Hence the bidder is advised to review the technical details provided in the appendix thoroughly. 6.3. The Bid should be furnished in the format described in section11 of this document, clearly indicating the bid amount in both figures and words, in Indian Rupees, and signed by the Bidder’s authorised signatory. In the event of any difference between figures and words, the amount indicated in words shall be taken into account. 6.4. Any condition or qualification or any other stipulation contained in the Bid that is not in the RFQ or contravenes any condition or qualification mentioned in the RFQ, shall render the Bid liable to rejection as a non-responsive Bid. 6.5. The Bid and all communications in relation to or concerning the Bidding Documents and the Bid shall be in English language. 6.6. The documents including this RFQ and all attached documents, provided by KITS are and shall remain or become the property of the KITS and are transmitted to the Bidders solely for the purpose of preparation and the submission of a Bid in accordance herewith. Bidders are to treat all information as strictly confidential and shall not use it for any purpose other than for preparation and submission of their Bid. 6.7. This RFQ is not transferable. 6.8. Any award of Contract pursuant to this RFQ shall be subject to the terms of Bidding Documents. 6.9. The bidder will be expected to coordinate and work closely with KITS’ technology partner (together called the consortium) for engineering design and technical aspects and will have to comply to the technical requirements of the consortium.
2TPD 190821
Page 7 of 11
7. CHANGE IN OWNERSHIP By submitting the Bid, the Bidder shall be deemed to have acknowledged and agreed that in the event of a change in control of an Associate whose Technical Capacity and/ or Financial Capacity was taken into consideration for the purposes of pre-qualification under and in accordance with the RFQ, the Bidder shall be deemed to have knowledge of the same and shall be required to inform KITS forthwith along with all relevant particulars about the same and KITS may, in its sole discretion, disqualify the Bidder or withdraw the LOA from the Selected Bidder. 8. COST OF BIDDING The Bidders shall be responsible for all of the costs associated with the preparation of their Bids and their participation in the Bidding Process. KITS will not beresponsible or in any way liable for such costs, regardless of the conduct or outcome of the Bidding Process. 9. VERIFICATION OF INFORMATION It shall be deemed that by submitting a Bid, the Bidder has: 1. made a complete and careful examination of the Bidding Documents; 2. received all relevant information requested from KITS. All queries should be sent by email only to ps@karunya.edu with a copy to madhuganesh@karunya.edu No phone or postal mail enquires will be accepted. 10. VERIFICATION AND DISQUALIFICATION KITSreserves the right to verify all statements, information and documents submitted by the Bidder in response to the RFQ. The bidder has to make available all such information, evidence and documents as may be necessary for such verification. Any such verification or lack of such verification, by KITS shall not relieve the Bidder of its obligations or liabilities. KITS reserves the right to reject any Bid and appropriate the Bid Security if: (a) at any time, a material misrepresentation is made or uncovered, or (b) the Bidder does not provide, within the time specified by KITS, the supplemental information sought by KITS for evaluation of the Bid.
2TPD 190821
Page 8 of 11
Such misrepresentation/ improper response shall lead to the disqualification of the Bidder. If such disqualification / rejection occurs after the Bids have been opened and the Lowest Bidder gets disqualified / rejected, then KITS reserves the right to: 1. considerthe remaining bids for evaluation 2. take any such measure as may be deemed fit in the sole discretion KITS, including annulment of the Bidding Process. 11. CONTENT OF THE BIDS 11.1.Part A - Technical Bid Item
Description
1
Detailed technical proposal including specifications and overall GA drawings, if applicable.
2
List all items from technical evaluation criterionlisted in Section 13.1
3
Corporate Profile
4
Engineering personnel and support staff details. These details must indicate the capability for mechanical and process design and production of manufacturing quality drawings
5
Fabrication and assembly facility details
6
Provide details for the experience of assembling, installing, integrating and commissioning at least one waste to energy plant, of similar or higher capacity preferably based on rotary kiln gasification technology
7
Reference letters for supply of waste to energy projects preferably of rotary kiln gasification technology of equal or higher of the requested capacity in the bid
8
Delivery Schedule The equipment should be delivered within 9 months from award of contract and installed within 12 months from award of contract. All equipment must be available for periodic inspections by a team designated by KITS and any rectification necessary shall be implemented at vendor’s cost. These rectifications should not affect the delivery schedule.
2TPD 190821
Page 9 of 11
11.2.Part B – Cost Bid Item 1
Description Total bid cost in numbers and in words to meet the requirements listed under Appendix 1 of scope of supply Justification of bid cost with price breakup 1) Equipment supply cost including installation at designated project site by KITS (In categories as listed in Table 4 of Scope of Supply in Appendix 1 2) The cost must include all applicable taxes, loading, transportation, Insurance, handling, off-loading and manpower 3) Basis for any central, state or local taxes included in the bid cost must be stated clearly and separately 4) Payment Terms including schedule of payments Permanent Account Number (PAN) of the Bidder Goods and Services Tax registration number (GST) Bidder’s bank account details duly signed and sealed by their bank
2
3 4 5
12. BID SUBMISSION PROCESS The bids must be submitted by email in two PDF documents 1) Technical Bid 2) Cost Bid Each PDF document must have
Project title RFQ number Bidder’s company name, address Bidder’s technical contact information Bidder’s commercial contact information
All pages shall be marked confidential. If a password is used for securing a PDF document, the password shall be sent in a separate email. Proposals should be sent on or before 15th September 2021 to the following Email ID ONLY :dsttdtwm201909g@karunya.edu The subject of the email shall be 2TPD 190821; Company Name” Any revisions to the submission prior to the bid acceptance date shall be indicated by revision numbers and all documents must be resubmitted. 2TPD 190821
Page 10 of 11
13. BIDDER EVALUATION CRITERION 13.1.Technical Bid 1) Bidder should have 5 years experience in manufacturing and supply of power and/or process plants. 2) Should have the experience of assembling, installing, integrating and commissioning at least one waste to energy plant of similar capacity or higher capacity, preferably with Rotary Kiln Gasification Technology. 3) TheBidder should have capability to design and produce manufacturing quality drawings on their own or through their consultants. If an external agency is used, it should be explicitly mentioned in the quote with experience details, resume and other credentials. 4) The Bidder should follow applicable Indian standards for manufacturing 5) The Bidder must have manufacturing facilities in India and must be able to support the project for 2 years from the date of installation 13.2.Cost Bid 1) The cost bid must be inclusive of – a. Equipment cost b. Freight, P&F and Insurance c. All applicable center and state taxes d. Installation cost that is inclusive for hiring equipment, manpower, travel to the site, lodging and boarding e. All Overheads 2) The total cost of the bid for the entire system including equipment supply to the site and installation to make the system operational shall be a criteriafor selection of the vendor. 3) The bidder requested payment terms shall be discussed with Purchase Committee of KITS and a mutually acceptable payment terms. 4) The equipment supplied shall be onsite warrantied for 1 year from the date of completion of installation. 5) The Bidder shall support the project for maintenance and repair of the equipment supplied for 2 TPD Rotary Kiln Gasification pilot plant for 2 years from the date of completion of installation. 6) A sum of Rs. 35 lacs shall be withheld from the total order value and reimbursed to the bidder subject to the following conditions a. Rs. 20 Lacs shall be reimbursed to the bidder after completing installation of the pilot plant b. Rs. 15 Lacs shall be reimbursed after 2 years of completing installation of the pilot plant 2TPD 190821
Page 11 of 11
SUPPLY AND INSTALLATION OF 2 TPD ROTARY KILN GASIFICATION PILOT PLANT 2TPD 190821
APPENDIX 1 SCOPE OF SUPPLY
FROM
Karunya Institute of Technology and Sciences Karunya Nagar, Coimbatore Tamil Nadu 641114
August 2021
APPENDIX 1 SCOPE OF SUPPLY SUPPLY AND INSTALLATION OF 2 TPD ROTARY KILN GASIFICATION PILOT PLANT TABLE OF CONTENTS 1. INTRODUCTION ................................................................................................................................... 3 2. PROCESS DESCRIPTION OF 2 TPD ROTARY KILN GASIFICATION PILOT PLANT ....................... 4 3. HEAT AND MASS BALANCE AND STREAM FLOW DIAGRAM .......................................................... 8 4. UTILITY REQUIREMENTS.................................................................................................................. 11 5. EQUIPMENT GROUPS ....................................................................................................................... 11 6. EQUIPMENT SPECIFICATIONS......................................................................................................... 13 7. INSTALLATION ................................................................................................................................... 21 8. DRAWINGS ......................................................................................................................................... 23 9. REFERENCES .................................................................................................................................... 24
LIST OF TABLES Table 1: Heat and Mass Balance for 2 TPD Rotary Kiln Gasification Pilot Plant ......................................... 8 Table 2: Utility Requirements for 2 TPD Rotary Kiln Gasification Pilot Plant ............................................. 11 Table 3: List of Equipment Groups and their Descriptions ......................................................................... 11 Table 4: Equipment Specifications for the 2 TPD Rotary Kiln Gasification Pilot Plant ............................... 13 Table 5: Specifications for Syngas Analyzer – (AI-680) ............................................................................. 24 Table 6: Specifications Flue Gas Analyzer (AI-710)................................................................................... 25 Table 7: List of Instruments ........................................................................................................................ 25 Table 8: List of Control Valves ................................................................................................................... 25 Table 9: List of Manual Valves ................................................................................................................... 25 Table 10: Electrical Cable Requirement and Specifications....................................................................... 26 Table 11: Motor Control Center (MCC) Specification ................................................................................. 26 Table 12: List of Motors .............................................................................................................................. 29 Table 13: Control System Specifications .................................................................................................... 30 Table 14: Specifications of Pipes and Fittings............................................................................................ 31
Page 2 of 32 Appendix 1 - 2TPD 190821
APPENDIX 1 SCOPE OF SUPPLY SUPPLY AND INSTALLATION OF 2 TPD ROTARY KILN GASIFICATION PILOT PLANT 1. INTRODUCTION Karunya Institute of Technology and Sciences (KITS) is setting up an R&D prototype of 2 Tons Per Day (TPD) Rotary Kiln Gasification pilot plant for converting non-recyclable plastic waste into high quality syngas. This system is designed and developed by KITS’ Technology Partner, especially for KITS, Coimbatore to accomplish the project objectives outlined in its proposal submitted to the Department of Science and Technology, India under the program for waste management technologies. The primary goal of the proposed project is to improve the quality of syngas during the gasification of waste. This document includes all the necessary technical information related to the design of the 2 TPD Rotary Kiln Gasification pilot plant to meet the following project objectives • • • •
Process non-recyclable plastic waste from Municipal Solid Waste (MSW) Use of enriched air for improving the calorific value of Syngas Integrate the gasifier system with steam or power generator Demonstrate sustainable waste to syngas production using rotary kiln gasification
The upcoming sections contain system configuration, system description, heat and mass balances, stream data, utility requirements, equipment list and general specifications and mechanical design drawings. The drawings provided in this document are design drawings and are not to be used for fabrication. The bidder is responsible for preparing manufacturing drawings necessary for executing the contract. Any deviation from the design objectives should be informed to the technical team at KITS prior to implementation. It is the responsibility of the bidder to review, understand the technical requirements of the bid. Any deviation from the scope of supply may result in the bid being disqualified. Hence the bidder is advised to review the detailed scope of supply provided here thoroughly.
Page 3 of 32 Appendix 1 - 2TPD 190821
2. PROCESS DESCRIPTION OF 2 TPD ROTARY KILN GASIFICATION PILOT PLANT The 2 TPD Rotary Kiln Gasification pilot plant achieves thermochemical conversion of non-recyclable plastics into high quality syngas (heating value of 1,200 kCal/Nm3 to 2300 kCal/Nm3) using enriched air (40% to 95% O2) gasification and then utilizing the high calorific syngas for producing steam for on-Campus consumption. The flue gas from the system is cleaned for the removal of sulfur and chlorine compounds as well as for the removal of the particulates before it is discharged to the atmosphere in order to comply with the local emission standards. The 2 TPD Rotary Kiln Gasification pilot plant consists of 5 subsystems. These subsystems are Feed Subsystem, Gasifier Subsystem, Gas Cleanup Subsystem, Steam Generation Subsystem and Auxiliary Subsystem. Each of these subsystems has unique process function. All of these operate in sync in order to achieve the objective of generating high calorific value syngas from non-recyclable plastic attendant with system’s additional objectives of operating in environmentally clean manner and delivering saturated steam as energy product for consumption on KITS campus. The system will also be able to generate hot water by providing additional equipment. All these subsystems are described in detail in the following section referring to the process flow diagram (PFD) for the system provided as Figure 1 below. • Feed Subsystem - Feed Subsystem will be provided by CMERI and is not part of Scope of Supply The feed subsystem will process 2 TPD of material, whose average composition is described in the heat and mass balance section below. The material will be processed by this feed system to a size not exceeding 50mm. and delivered to the gasifier for use in the pilot plant. Details of this feed system will be provided after the contract has been awarded. • Gasifier Subsystem The components of gasification subsystem include a Plastic Chopper (SH-010) to chop the size of the plastic waste into less than 15 mm size, a Transfer Conveyor (BC-020) to transfer chopped plastic into the gasification reactor, a Screw Feeder (SC-070) to introduce waste feed into the reactor, a Rotary Kiln Gasifier (RX-300) for gasification, a Start-up Burner (BRN-310) and associated Blower (BL-320) for preheating the gasifier, a Process Air Blower (BL-330) for air supply for waste gasification, oxygen supply components for supply of oxygen to enrich air to 40 to 95 % and an Air Distributor (AD340) to distribute air inside of the gasifier. Page 4 of 32 Appendix 1 - 2TPD 190821
The Rotary Kiln gasifier is a horizontal, refractory-lined kiln designed for high process temperatures. The start-up burner is located at the feed inlet side of the kiln to raise the gasifier temperature. The burner is equipped with its own air and fuel supply. LPG is used as the fuel for burner. Rented LPG cylinders supplies LPG for the burner operation. The burner is fired initially during start-up to raise the temperature inside the gasifier to near ignition temperature of the waste and also to preheat the refractory and the downstream equipment. Initial heating of the system is necessary to initiate partial combustion of the waste as well as to prevent condensation in the downstream equipment. After the desired temperature is attained with the start-up burner, waste is gradually introduced into the gasifier using Gasifier Screw Feeder (SC-070) while allowing the temperature to rise. Process water and enriched air (40 to 95 % O2) are used as gasification media and is introduced gradually along with the feed. The primary source of process air is the Process Air Blower (BL-330). Pure oxygen in rented cylinder gangs is added to the process air stream to enrich the air and bring the oxygen level to 40 to 95%. As the waste feed is increased, the LPG in the start-up burner is reduced. The feed nozzle is kept clear off the direct impingement from the burner flame. Gasification is a thermochemical process that uses heat and steam to convert wastes directly into syngas comprising primarily of carbon monoxide, methane, hydrogen, water vapor, carbon dioxide, and nitrogen. Heat necessary for gasification process is derived from partial combustion of waste with controlled amount of air and oxygen introduced along the length of the gasifier using the Gas Distributor (AD-340). The syngas has combustion characteristics similar to that of the natural gas; however, its calorific content for this project will vary from 1,500 – 2,300 kCal/Nm3. In order to accomplish the objective of producing high quality syngas, gasification medium is enriched with oxygen. This enriched gasification medium has an oxygen concentration of 40%. Metered quantity of pure oxygen from rented cylinders is mixed with air (21% O2) and is supplied to the gasifier. The system has all necessary instrumentation to achieve automatic mixing of oxygen with air. • Gas Cleanup Subsystem Gas clean-up Subsystem also knows as Flue gas Cleanup comprises of components for cleaning the syngas/flue gas produced by syngas combustion. The gas is cleaned to remove sulphur and chloride impurities before it is discharged to the atmosphere. These gaseous impurities are scrubbed off by reacting them with lime in the reaction chamber, Flue Gas Desulfurizer (FGD-675). A sorbent injection system (Sorbent Hopper (H-540), Sorbent Feeder (SC-550) and Rotary Valve (RV-560)) is included for storing and supplying sorbent to FGD. The particulates in the flue gas are removed using the Bag Filter (BF-600). The bag filter is capable of removing 99% of solids in the size range of 2 microns and larger. In the current design, the Flue Gas Desulphurizer (FGD-675) is Page 5 of 32 Appendix 1 - 2TPD 190821
integrated with the Bag Filter (BF-600) to make the system compact. Air required for the bag filter cleaning is provided by Air Compressor Package (C-900) included in Auxiliary group. An Induced Draft Blower (BL-660) assists the flow of gas from the gasifier through the gas utilization and clean-up system. The cleaned flue gas is released to the atmosphere. The solids collected in the FGD and bag filter are discharged and collected in separate residue bins. • Steam Generation Subsystem The syngas generated in the gasifier is directly combusted in a Combustion Chamber (CC-570), which is integrated to gasifier. Combustion Chamber is associated with a Burner (BRN-580) and an associated Blower (BL-585), Combustion Chamber Blower (BL-590) for supplying combustion air for syngas combustion, Moving Grate (FV-350) at the discharge side to ensure sealed discharge of solid residue from combustion chamber. The Heat Recovery Steam Generator (B-500) utilizes the energy in syngas to generate saturated steam at the header for further use in the campus. Supply of feed water from Fee Water Tank (TK-510) is also included. • Auxiliary Subsystem The major components in this group are Stack (ST-670) to release the clean flue gas from the gas cleanup components into the atmosphere, Air Compressor (C-900) for compressed air supply for the bag filter as well as instrument air supply for the control valves, Process Water Tank (TK-700) and Process Water Pumps (P-705A/B).
Page 6 of 32 Appendix 1 - 2TPD 190821
Figure 1: Process Flow Diagram of 2 TPD Rotary Kiln Gasification Pilot Plant
Page 7 of 32 Appendix 1 - 2TPD 190821
3. HEAT AND MASS BALANCE AND STREAM FLOW DIAGRAM Design of the 2 TPD Rotary Kiln Gasification Pilot Plant is based on material and energy balance presented in Table 1. The stream flow diagram is also presented in Figure 2 below. Table 1: Heat and Mass Balance for 2 TPD Rotary Kiln Gasification Pilot Plant Parameter Capacity
Value
Unit 2.00
Waste Name
TPD
Mixed Waste
Gasification Mode
Enriched Air (40% O2)
Waste Composition (Dry Weight Basis) C
60.00
%
H
7.20
%
O
20.60
%
N
0.00
%
S
1.00
%
Cl
1.00
%
10.20
%
5.00
%
20.00
%
Ash Moisture in Feed Moisture for Gasification Additional Water Required
16
kg/h
HHV, (Dry) (Dulong)
6398
kCal/kg
HHV, (Wet) (Dulong)
6078
kCal/kg
Total Feed Rate
83
kg/h
Dry Feed Rate
79
kg/h
Moisture Feed Rate (Moisture in feed + water added)
20
Gasification Temperature
kg/h
900
C
O2
40
%
N2
60
%
Oxidant Feed Rate
4.2
mol/h
Oxidant Feed Rate
123
kg/h
Oxidant Flow Rate
98
Nm3/h
Oxidant Composition (Mole Basis)
Page 8 of 32 Appendix 1 - 2TPD 190821
Parameter
Value
Unit
Syngas Produced
9.7
mol/h
Syngas Produced
214
kg/h
Syngas Mol Wt
22.1
kg/kgmol
Syngas Produced
227
Nm3/h
Syngas Produced
923
Am3/h
Syngas Composition (Mol Basis) CO
22.50
%
H2
23.20
%
CH4
2.05
%
CO2
12.80
%
H2O
17.50
%
H2S
0.22
%
N2
21.35
%
HCl
0.20
%
C2
0.18
%
Ash Produced HHV of Syngas (wet)
8 1529
kg/h kCal/Nm3
Total Heat Input
506,490
kCal/h
Heat in Syngas
347,842
kCal/h
Sensible Heat in Syngas
61,827
kCal/h
Latent Heat in Syngas
16,369
kCal/h
409,668
kCal/h
Steam Pressure
4.5
Bar A
Steam Temperature
144
C
Enthalpy of Steam
655
kCal/kg
27
C
496
kg/h
Total Heat Available for Recovery
Feed Water Temperature Steam Generation Potential
The stream balance block diagram for 2 TPD Rotary Kiln Gasification Pilot Plant is shown as Figure 2.
Page 9 of 32 Appendix 1 - 2TPD 190821
Figure 2: Stream Balance Block Diagram for 2 TPD Rotary Kiln Gasification Pilot Plant
NON-RECYCLABLE PLASTIC WASTE 2 mTPD 5 % Moisture
FEED SYSTEM
NON-RECYCLABLE PLASTIC WASTE 83 kg/h 6,078 kCal/kg
AIR 73 Nm3/h 89 kg/h
OXYGEN (95%) 25 Nm3/h 34 kg/h
SYNGAS 227 Nm3/h 214 kg/h 900 °C CH – 347,840 kCal/h SH – 61,820 kCal/h LH – 16,370 kCal/h SOLIDS 2 kg/h SH – 1,100 kCal/h
WATER 16 kg/h
GASIFIER
SOLID RESIDUE 6 kg/h SH- 3,163 kCal/h
AIR 658 Nm3/h 803 kg/h
COMBUSTION CHAMBER
FLUEGAS 834 Nm3/h 1,017 kg/h 1,200 °C SH – 380,060 kCal/h LH – 45,970 kCal/h SOLIDS 2 kg/h SH – 1,424 kCal/h
FLUEGAS 834 Nm3/h 1,017 kg/h 150 °C SH – 39,440 kCal/h LH – 45,970 kCal/h SOLIDS 1 kg/h SH – 381 kCal/h
WATER 510 kg/h
BOILER
BLOW DOWN 16 kg/h
COMPRESSED AIR 34 Nm3/h 41 kg/h
LIME 3 kg/h
ACTIVATED CARBON 1 kg/h
FLUEGAS 867 Nm3/h 1,057 kg/h 110 °C SOLIDS 0.0004 kg/h
FLUEGAS CLEANUP SOLID RESIDUE 7 kg/h
SOLID RESIDUE 1 kg/h
STEAM 494 kg/h 4.5 barA 144 °C
Legend CH – Chemical Heat SH – Sensible Heat LH – Latent Heat
PROJECT NAME
2 TPD ROTARY KILN GASIFICATION SYSTEM
STREAM FLOW DIAGRAM -40% ENRICHED AIR USED AS OXIDANT RVS 25-JUN-2021
Prepared By:
Checked By:
Approved By
Date :
Date :
Date :
SM 30-JUN-2021
GK 02-JUL-2021 20-DEC-2018
Project No.
169
Document No.
169-100-002B
REV No.
0
C
DESCRIPTION
SCALE : SCALE
ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE SPECIFIED DO NOT SCALE DRAWING
DATE
SHEET:1 OF 1
DOCUMENT TITLE
REVISIONS REV
VER No.
0
Page 10 of 32 Appendix 1 - 2TPD 190821
4. UTILITY REQUIREMENTS The design utility requirements for 2 TPD Rotary Kiln Gasification Pilot Plant are listed in Table 2. Table 2: Utility Requirements for 2 TPD Rotary Kiln Gasification Pilot Plant Item
Utility Name
User
Quantity 16 10 512
Unit lph lph lph
1
Process Water
2
Boiler Feed Water
Gasifier Ash Quenching Boiler
3
Lime Powder
Dry Scrubber
3
kg/h
4
LPG
5
Oxygen
Start-Up Burner-Gasifier Start-Up Burner-Boiler Gasifier
12 12 25
kg/h kg/h Nm3/h
6
Compressed Air
Plant Operation
40
Nm3/h
7
Electricity
Plant Operation
30
kW
5. EQUIPMENT GROUPS All the equipment in 2 TPD Rotary Kiln Gasification Pilot Plant except those for the feed system are grouped under 7 categories as shown in table 3. Feed System Components will be provided by others and is not part of this RFQ. The following list of components will form the basis of the bid package to be submitted by the bidder. It is expected that the bidder will provide the bid costing for supply and installation of components with a breakup according to the groups listed below, in addition to freight, taxes and other costs that form the total cost of the bid package. Do not include any cost information in technical part of the bid package. Table 3: List of Equipment Groups and their Descriptions Item 1
Group Name Gasifier Components
Group Descriptions This includes all the components required for the gasification of prepared feed material and converts it into Syngas for further energy recovery. This is an integral part of the gasification system. These specially designed components ensure maximum conversion of the waste into syngas. These components are to be installed and integrated into the other components in the gasification system at the KITS project site. The key components are Plastic Chopper (SH010), Waste Transfer Conveyor (SC-055), Gasifier Screw Feeder (SC-070), Gasifier (RX-300), Process Air Blower (BL-330), Air Distributor (AD-340), Startup Burner (BRN-310) and Shredder (SH-010). This also include Page 11 of 32
Appendix 1 - 2TPD 190821
Item
Group Name
2
Steam Generation Components
3
Flue Gas Cleanup Components
4
Electrical & Instrumentation Components
5
Auxiliary Components
6
Ducting and Piping
7
Refractory
Group Descriptions associated accessories like Startup Burner Blower (BL-320). The Steam generation components utilizes the chemical energy in syngas produced in the gasifier and converts it to thermal energy to produce steam using a heat recovery exchanger. The design of each component in the group is unique and should work concurrently with the upstream and downstream components. These components are to be installed and integrated with the Kiln and Gas Cleanup components. This includes key equipment like Combustion Chamber (CC-570), Heat Recovery Steam Generator (B-500) and Combustion Blower for CC-570 (BL-590). The subsystem also includes Burner for CC-570 (BRN-580), Blower for BRN-580 (BL-585), Moving Grate (FV-350), Ash Bin (BN-360) and Feed Water Tank (TK-510) as accessories. This consists of components for removing acid gas pollutants as well as particulates in the combustion products after heat recovery from the steam generation components. This group includes a specially designed bag filter with an integrated reaction chamber for acid gas removal along with other components. These components are to be assembled and installed at the site along with the other components in the gasification system. The key equipment in this group are Sorbent Injection System (H-630), Flue Gas Desulphurizer (FGD-675) integrated with Bag Filter (BF-600), Carbon Bed Filter (CF-620), ID Fan (F-660) and Ash Bin (BN-677). This is also an integral part of the gasification system that is exclusively chosen for the specially designed components in various component groups. This group enables the proprietary control system to work efficiently. All the components in this group are to be installed and integrated into the gasification system at the KITS project site. This group includes the key components like the Motor Control Center (MCC) and the Cabinet for accommodating the PLC and its accessories. This also includes all the instrumentation specifically required for the operation and monitoring of the gasification system. Most of the instruments are specially designed to work in concurrence with the gasification equipment and are to be integrated into each group during the manufacturing stage. All these components are to be installed at the KITS project site. The key components are the Field Instruments, Control Valves, Shut off Valves, Manual Valves and Control System including Programmable Logic Control (PLC) and Human Machine Interface (HMI) for plant operation. The Auxiliary Component group includes the auxiliary equipment required for the gasification system. These components are to be installed and integrated into other components in the gasification system at the KITS project site. The major components in the subsystem are the Process Water Tank (TK-700), Process Water Pumps (P-705 A/B), Air Compressor (C-900) and Stack (ST670). The Piping and Ducting Component group includes all the piping and ducting for the integration of each component group. These ducts and pipes must align with the components in each component group and has to be included along with each component group for integration at the KITS project site. Some of the Gasification and the Steam generation components operate at high temperatures and hence high temperature insulation is required to protect Page 12 of 32
Appendix 1 - 2TPD 190821
Item
Group Name
Group Descriptions the equipment. The Gasifier (RX-300), Combustion Chamber (CC-570) and Heat Recovery Steam Generator (B-500) are provided with high temperature castable refractory coating to protect the metal components directly coming in contact with hot and corrosive gases from the process.
6. EQUIPMENT SPECIFICATIONS The 2 TPD Rotary Kiln Gasification Pilot Plant is designed to generate high CV syngas from enriched air gasification of non-recyclable plastic waste in municipal solid waste (MSW), primarily focusing on the utilization of syngas from gasifier to produce steam. The list of components for the system along with their specifications are shown in the below table. The component sizes are selected for processing 2 ton per day (TPD) nonrecyclable plastic waste as feed. The capacity numbers for each equipment are derived from a theoretical Heat & Mass balance. All the equipment are designed with sufficient margin and turn down to process 2 TPD capacity. Though the system is intended for demonstration purpose with intermittent operation, the design supports continuous operation. The equipment specifications are detailed out in Table 4 below. Table 4: Equipment Specifications for the 2 TPD Rotary Kiln Gasification Pilot Plant Item
Tag No.
Tag Name
Specification
1. GASIFIER COMPONENTS 1
SH-010
Feed Chopper
Application – To reduce the pre-processed waste feed size to less than 15 mm size Type – Single Shaft Chopper Capacity – 100 kg/h Incoming Feed Size- 150 mm (maximum) Feed Bulk Density – 100-200 kg/m3 Size Reduction – Less than 15 mm Operation –Designed for 24x7 operation Power Supply – 415V/50Hz/3Ph
Page 13 of 32 Appendix 1 - 2TPD 190821
Item 2
Tag No. BC-020
Tag Name Transfer Conveyor
Specification Application – Transfer chopped feed to gasifier screw feeder Type – Z Type Belt Conveyor Capacity – 100 kg/h Belt – Nylon/ Rubber Other Components – Carbon Steel Belt Width – 500 mm Operation – Designed for 24x7 operation Power Supply – 415V/50Hz/3Ph Reference Drawing – 169-D-GG-020-1000
3
SC-070
Gasifier Screw Feeder
Application – To feed the waste material into the gasifier Type – Screw Conveyor with external Jacketed chute Capacity – 100 kg/h MOC: • •
Screw – Wear Resistant Steel Other components – Carbon Steel
Operation – Continuous Power Supply – 415V/50Hz/3Ph Reference Drawing – 169-D-GG-070-1000 4
RX-300
Gasifier
Type – Rotary Kiln Capacity – 100 kg/h Max Operating Temperature – 900 0C MOC – Carbon Steel Insulation – Castable Refractory. 230 mm refractory lined on the inside which consists of 100 mm dense phase & 130 mm insulation phase Kiln Inside Diameter with Refractory Lining – 600 mm Kiln Length – 1200 mm Drive – Induction motor controlled by a variable frequency drive Turndown Ratio – 4:1 Operation – Continuous Power Supply – 415V/50Hz/3Ph Reference Drawing – 169-D-GG-300-1000 Page 14 of 32
Appendix 1 - 2TPD 190821
Item
Tag No.
Tag Name
5
BRN-310
Startup Burner
Application – To heat up the gasifier Capacity – 125,000 kCal/h Fuel – LPG Provisions Included: • Safety systems • Fuel train components • Controls and safety interlocks. Operation – Equipment designed for 24x7 operation but will be operated for 10 to12 hrs. during start-up process.
6
BL-320
Startup Burner Blower
Type – Centrifugal Blower Application – To supply fuel required for start-up burner (BRN-310) Capacity – 240 Nm3/h MOC – Carbon Steel Operation – Equipment designed for 24x7 operation, but will be operated in conjunction with BRN-310 Power Supply – 415V/50Hz/3Ph
7
BL-330
Process Air Blower
Type – Centrifugal Blower Application – To supply process air for gasifier Capacity – 240 Nm3/h MOC – Carbon Steel Operation – Continuous Power Supply – 415V/50Hz/3Ph
8
AD-340
Air Distributor
Type – Concentric Tube Size – As per Drawing Capacity- 240 Nm3/h MOC- Stainless Steel Operation – Continuous Reference Drawing – 169-D-GG-070-1000
Oxygen Cylinders
Application – To supply oxygen for enriched air gasification Type – Rented oxygen cylinders sourced locally
Syngas Analyzer
Application – To measure syngas composition Type – Syngas Analyzer Reference – Table 5
9
10
AI-680
Specification
Page 15 of 32 Appendix 1 - 2TPD 190821
Item
Tag No.
Tag Name
Specification
2. STEAM GENERATION COMPONENTS 11
CC-570
Combustion Chamber for Boiler-500
Application – For complete combustion of Syngas Design Temperature – 1,200 0C Design Syngas Flow Rate – 380 Nm3/h Syngas Temperature – 900 0C Syngas Inlet Pressure – (-)5 to 0 mmWC Combustion Efficiency – 99.99% Gas Retention Time – 2 seconds Gas Heating Value Range – 1,000 to 2,000 kCal/Nm3 MOC - Carbon Steel Insulation – Membrane Water Wall. Refractory if needed, as recommended by bidder Approximate Inside Dimensions (LxWxH) – 3000 mm x 1800 mm x 1300 Maximum Particulate in Syngas – 50 kg/h Initial Heat up – Using a pilot burner Operation – Continuous Reference Drawing – 169-D-GG-570-1000
12
BRN-580
Burner for CC-570
Application – To preheat the Combustion chamber to required temperature Capacity – 125,000 kCal/h Fuel – LPG Provisions Included: Safety systems Fuel train components Controls and safety interlocks Installation Location – On the combustion chamber Operation – Equipment designed for 24x7 operation, but will be operated initially during system dry out and for 3 to 4 hrs during start-up process
13
BL-585
Blower for BRN580
Application – To supply air for burner Capacity – 240 Nm3/h Static Pressure – 500 mmWC MOC – Carbon Steel Power Supply – 415V/50Hz/3Ph Operation – Continuous
Page 16 of 32 Appendix 1 - 2TPD 190821
Item
Tag No.
Tag Name
Specification
14
BL-590
Combustion Application – Combustion Air Supply to CC-570 Blower for CC-570 Type – Centrifugal Capacity – 900 Nm3/h Discharge Pressure – 200 mmWC MOC – Carbon Steel Power Supply – 415V/50Hz/3Ph Operation – Continuous
15
FV-350
Mini Travelling Grate
Application –To Combust the solids coming out of the gasifier Type – Travelling Grate Solid Burning Capacity – 100 kg/h Power Supply – 415V/50Hz/3Ph Operation – Continuous
16
B-500
Heat Recovery Steam Generator
Application –To recover heat in the flue gas produced by the combustion chamber and produce steam Type – Water Tube Boiler Flue Gas Flowrate – 1,200 Nm3/h Design temperature – 1,200 0C MOC • Body – Carbon Steel • Tubes – Boiler Grade Steel Steam Pressure – 4.5 barA Steam Pressure – 144 0C Max Steam production capacity – 600 kg/h Maximum Allowable Pressure drop – 100 mmWC Inside insulation – 100 mm thick refractory on the inlet nozzle or as recommended by bidder Outside Insulation – 50 mm Mineral wool with GI cladding Operation – Continuous Reference Drawing – 169-D-GG-500-1000
17
TK-510
Feed Water Tank
Application –To store feed water for boiler Type – Storage Tank Capacity – To match with boiler requirement MOC – As recommended by bidder
Page 17 of 32 Appendix 1 - 2TPD 190821
Item 18
Tag No. P-520 A/B
Tag Name Feed Water Pumps
Specification Application –To supply feed water to the boiler Type – Centrifugal or as recommended by bidder Capacity – To match with boiler requirement Head - To match with boiler requirement MOC – As recommended by bidder
3. FLUE GAS CLEANUP COMPONENTS 19
H-540/ SC-550/ RV-560
Sorbent Injection System (Sorbent Hopper/Sorbent Feeder/Rotary Airlock for SC550)
20
BF-600 & Bag Filter & FGD-675 Flue Gas De-sulphurizer
Application – To store and supply sorbent for acid neutralization Type – Storage Hopper with bottom conical discharge Capacity – 25 kg Normal Discharge rate – 4 kg/hr Maximum Discharge rate – 8 kg/hr Turn Down Ratio – 5:1 Bulk density of Sorbent - 600-700 kg/m3 Accessories: • Sorbent Feeder (SC-550) – To ensure uniform discharge • Rotary Valve (RV-560) – To prevent false air entry MOC: • Hopper – Carbon Steel • Sorbent Feeder – Wear Resistant Steel • Other components – Carbon Steel Operation – Equipment designed for continuous operation, but will only be operated according to requirement Application – To separate particulates as well as acid gases from flue gas Type – Reverse Pulse Jet Bag Filter with integrated reaction chamber Gas Flowrate – 1,400 Nm3/h (2,000 Am3/h) Gas Temperature – 150 0C Design Temperature – 220 0C MOC – Carbon Steel Filtration Efficiency – 99.99 % for 2 microns and larger Maximum Allowable Pressure drop – 150 mmWC Outside Insulation – 50mm Mineral wool with GI cladding Page 18 of 32
Appendix 1 - 2TPD 190821
Item
Tag No.
Tag Name
Specification Operation – Continuous Special Provision – Additional volume at the inlet for maintaining sorbent reaction time. Residue Discharge Provision – Leak proof arrangement Power Supply – 415V/50Hz/3Ph Ref Drawing – 169-D-GG-675-1000
21
CF-620
Carbon Bed Filter
Application – To separate particulates from flue gas Adsorbent Material - Activated carbon Maximum Temperature – 120 0C Tray Thickness - 50mm Filter Size - 300mm X 600 mm Filter Efficiency – 90% to 99% Particle removal size – Up to 3 microns Filter Efficiency Rating - MERV 7 Carbon Concentration – 0.33 g/cm2 Ref Drawing – 169-D-GG-620-1000
22
F-660
ID Fan
Application – To generate draft to carry the gases all the way from gasifier to the exhaust Type – Induced Draft Centrifugal Fan Capacity – 1,400 Nm3/h (2,000 Am3/h) Suction Pressure – 900 mmWC Discharge Pressure – 100 mmWC Inlet Gas Temperature – 150 0C Design Temperature – 175 0C Drive Arrangement – VFD controlled direct drive through coupling. MOC • Impeller – Carbon Steel • Casing – Carbon Steel Additional Provision: • Online Impeller cleaning • Anti-vibration mounts • Impellor designed for medium dust loading Operation – Continuous Power Supply – 415V/50Hz/3Ph
Page 19 of 32 Appendix 1 - 2TPD 190821
Item 23
Tag No. AI-710
Tag Name
Specification
Flue Gas Analyzer Application – To measure flue gas composition Type – Flue Gas Analyzer Reference – Table 6
4. AUXILIARY COMPONENTS 24
ST-670
Stack
Application - To exhaust the flue gas from syngas combustion Type - Self supported Gas Flowrate – 1, 400 Nm3/h (2,000 Am3/h) Gas Temperature – 150 0C MOC - Carbon Steel with 45 % alumina refractory lining at the bottom Height – To meet local codes Diameter – To match with the flow rate and height
25
TK-700
Process Water Tank
Application – To store process water Type – Storage Tank Capacity – 2 m3 MOC – HDPE
26
P-705 A/B
Process Water Pump A/B
Application – To supply process water for gasifier Type – Centrifugal Capacity – 0.5 m3/h Head – 100 m MOC – Carbon Steel Power Supply – 415V/50Hz/3Ph
27
C-900
Air Compressor Application – To supply compressed air for Package instruments Type – Rotary Screw Capacity - 50 m3/h (30 CFM) Discharge pressure - 7 barg Accessories: • Air Dryer – 50 m3/h (30 CFM) • Air receiver tank - 200 litres Operation - Continuous
5. ELECTRICAL AND INSTRUMENTATION COMPONENTS 28
Inst-01
Field Instruments
Reference - Table 7
29
Valve-01
Control Valves
Reference - Table 8
30
Valve-01
Manual Valves
Reference - Table 9 Page 20 of 32
Appendix 1 - 2TPD 190821
Item
Tag No.
Tag Name
Specification
31
MCC-01
Motor Control Centre
Reference – Table 10 Table 11 Table 12
32
CS-01
Control System
Reference - Table 13
6. DUCTING AND PIPING COMPONENTS 33
PI-01
Piping and Ducting
Reference - Table 14
7. REFRACTORY COMPONENTS 34
Ref-01
Refractory
Dense Refractory Service Temperature – 1450 0C Bulk Density – 2.45 g/cc Permanent Linear Change @ 1100 0C – (0.18) % Cold Crushing Strength @ 1100 0C – 300 kgf/cm2 Alumina - >60% Iron - <1.0% Thermal Conductivity @ 450 0C– 0.95 kCal/h.m.0C Insulation Refractory Service Temperature – 1350 0C Bulk Density – 1.45 g/cc Permanent Linear Change @ 1100 0C – 30 % Cold Crushing Strength @ 1100 0C – 30 kgf/cm2 Iron – 3.5% Thermal Conductivity @ 450 0C– 0.32 kCal/h.m.0C
7. INSTALLATION The 2 TPD Rotary Kiln Gasification pilot plant will be installed at the project site in KITS campus near Coimbatore, India. All components in the bid package must be supplied to the project site and installed. Detailed information on the project site will be provided after the contract is awarded. The 2 TPD Rotary Kiln Gasification pilot plant must be installed such that it is ready to be operational. All labour, equipment, consumables, utilities and any other associated cost must be borne by the bidder. Do not include any cost information in the technical bid package. Page 21 of 32 Appendix 1 - 2TPD 190821
The following points may be noted for installation. i.
The bidder is responsible for installation of all the equipment as per the engineering drawings provided and make the system operational.
ii.
The bidder should prepare necessary installation drawings and send for approval for KITS project in-charge, prior to starting the installation activities.
iii.
Necessary drawings for the civil foundations and structures should be provided to KITS well in advance, by the bidder, if any.
iv.
The bidder is responsible for arranging all installation items such as fasteners, foundation bolts, safety equipment, other necessary tools, consumables, spares and other accessories.
v.
Arrangement of necessary heavy equipment (Cranes, Forklift, etc.)needed for installation are within the bidder’s scope of supply.
vi.
The bidder shall arrange necessary local manpower required for installation. Any insurance requirements for installation is bidder’s responsibility.
vii.
A site in-charge should be appointed by the bidder, who will be responsible for communicating with KITS’ technical team.
viii.
Installation must be completed within the schedule approved during finalization of the contract.
ix.
The bidder shall setup all the necessary arrangements required for installation of the components including scaffolding and other structures.
x.
Utilities such as compressed air, diesel, auxiliary power etc. as required for the installation shall be arranged by the bidder.
xi.
Installation manuals of all items should be supplied along with the installation documents.
Page 22 of 32 Appendix 1 - 2TPD 190821
8. DRAWINGS Item
Drawing Number
Drawing Title
Layout Drawings 1
169-D-GG-000-1001
Layout
2
169-D-GG-000-1002
Front Elevation
3
169-D-GG-000-1003
Left Side Elevation
4
169-D-GG-000-1004
Right Side Elevation
Equipment Group Drawings 5
169-D-GG-300-2000
Gasifier Components
6
169-D-GG-500-2000
Steam Generation Components
7
169-D-GG-600-2000
Flue Gas Cleanup Components
8
169-D-GG-900-2000
Auxiliary Components
Equipment Drawings 9
169-D-GG-020-1000
Transfer Conveyor
10
169-D-GG-070-1000
Gasifier Feed Screw
11
169-D-GG-300-1000
Gasifier
12
169-D-GG-570-1000
Combustion Chamber for Boiler-500
13
169-D-GG-500-1000
Heat Recovery Steam Generator
14
169-D-GG-675-1000
Flue Gas De-sulphurizer
15
169-D-GG-620-1000
Carbon Bed Filter
Page 23 of 32 Appendix 1 - 2TPD 190821
2.4m
2.9m PLANT CAPACITY & PROCESS FEED
STACK HEIGHT MUST BE AS PER LOCAL CODES AND REGULATIONS, STACK LOCATION IS SUBJECT TO CHANGE AS PER SITE CONDITION
19
COMPONENT NO.
TAG NO.
EQUIPMENT
01
SH-010
PLASTIC CHOPPER
2TPD GASIFICATION SYSTEM
02
BC-020
TRANSFER CONVEYOR
MIXED PLASTIC
03
SC-070
GASIFIER SCREW FEEDER
04
RX-300
GASIFIER
05
BRN-310
STARTUP BURNER
06
BL-320
STARTUP BURNER BLOWER
07
BL-330
PROCESS AIR BLOWER
08
AD-340
AIR DISTRIBUTOR
PROJECT OVER VIEW
18
ASH DISCHARGE
09
29
27
STEAM OUTLET
30
TROLLEY FOR ASH BIN MOVEMENT
17
23
2.8m
1.4m
28
21
16 ASH DISCHARGE
13.2m
15
CONTROL ROOM & OFFICE SPACE 14
3.6m
15m 3m
20
11
5.0
12 13
04
ACCESS PLATFORM FOR FEEDING
09
1.8m
5.8m
07
08
02
01
2.2m
03
FEED INLET
AI-680
SYNGAS ANALYZER
11
CC-570
COMBUSTION CHAMBER
12
BRN-580
BURNER FOR CC-570
13
BL-585
BLOWER FOR COMBUSTION CHAMBER BURNER
14
BL-590
BLOWER FOR COMBUSTION CHAMBER
15
FV-350
MINI TRAVELLING GRATE
16
BN-360
ASH BIN
17
B-500
HEAT RECOVERY SYSTEM
18
TK-510
FEED WATER TANK
19
P-520 A/B
FEED WATER PUMPS
20
SORBENT INJECTION SYSTEM
21
H-540/SC550/RV-560 BF-600 & FGD-675
BAG FILTER & FLUEGAS DESULPHURIZER
22
CF-620
CARBON BED FILTER
23
F-660
ID BLOWER
24
BN-610 & BN-675
ASH BIN FOR BF-600 & FGD-675
25
AI-710
FLUEGAS ANALYZER
26
ST-670
STACK
27
TK-700
PROCESS WATER TANK
28
P-705 A/B
PROCESS WATER PUMP A/B
29
C-900
AIR COMPRESSOR PACKAGE
30
MCC-01
MOTOR CONTROL CENTRE
- ALL STAIRCASE AND PLATFORMS SHOULD HAVE HANDRAILS AS PER INDIAN STANDARD. - SAFETY GUARD SHOULD BE PROVIDED FOR ALL ROTATING EQUIPMENT WHEREVER REQUIRED. - WARNING & SAFETY LABELS , ELECTRICAL AND FLOW INDICATORS MUST BE PROVIDED WHERE EVER APPLICABLE AS PER INDIAN STANDARDS. - PIPE & PIPE RACKS , CABLE & CABLE TRAY PIPE SUPPORTS ARE NOT SHOWN IN THE LAYOUT. - LAYOUT IS SUBJECT TO CHANGE AS PER FINAL DESIGN AND SITE CONDITION.
05
06
10
1.6m 4.5m 11m
2.9m REFERENCE DRAWING LIST
NOTES: - THIS IS A PRELIMINARY DRAWING ISSUED FOR RFQ PURPOSE ONLY, NOT FOR CONSTRUCTION OR INSTALLATION. - THE OVERALL DIMENSIONS AND EQUIPMENT SIZE IS SUBJECT TO CHANGE BASED ON FINAL SITE CONDITION AND DESIGN. - CIVIL STRUCTURES SHOWN IN THIS DRAWING IS ONLY FOR REFERENCE.
REVISIONS REV.
DATE
DRAWING NO.
DRAWING TITLE
169-D-GG-000-1002
FRONT ELEVATION
DRAWING TITLE
PROJECT NAME
DESCRIPTION
ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE SPECIFIED. DO NOT SCALE DRAWING.
2 TPD ROTARY KILN GASIFICATION SYSTEM
LAYOUT CAD By: DATE:
PC
25-JUN-2021
CHD By: DATE:
GK
30-JUN-2021
APPD By: DATE:
AM
02-JUL-2021
PROJECT NO:
169
DRAWING NO:
169-D-GG-000-1001
REV NO:
0
VER NO:
0
SCALE :1:200
22
OXYGEN CYLINDERS
C
26
SHEET:1 OF 1
3m
3m
STACK HEIGHT MUST BE AS PER LOCAL CODES AND REGULATIONS, STACK LOCATION IS SUBJECT TO CHANGE AS PER SITE CONDITION
COMPONENT NO.
TAG NO.
EQUIPMENT
01
SH-010
PLASTIC CHOPPER
2TPD GASIFICATION SYSTEM
02
BC-020
TRANSFER CONVEYOR
MIXED PLASTIC
03
SC-070
GASIFIER SCREW FEEDER
04
RX-300
GASIFIER
05
BRN-310
STARTUP BURNER
06
BL-320
STARTUP BURNER BLOWER
07
BL-330
PROCESS AIR BLOWER
08
AD-340
AIR DISTRIBUTOR
PROJECT OVER VIEW PLANT CAPACITY & PROCESS FEED 26
09
20
21
11
CC-570
COMBUSTION CHAMBER
12
BRN-580
BURNER FOR CC-570
13
BL-585
BLOWER FOR COMBUSTION CHAMBER BURNER
14
BL-590
BLOWER FOR COMBUSTION CHAMBER
15
FV-350
MINI TRAVELLING GRATE
16
BN-360
ASH BIN
17
B-500
HEAT RECOVERY SYSTEM
18
TK-510
FEED WATER TANK
19
P-520 A/B
FEED WATER PUMPS
20
SORBENT INJECTION SYSTEM BAG FILTER & FLUEGAS DESULPHURIZER
04
22
CF-620
CARBON BED FILTER
23
F-660
ID BLOWER
24
BN-610 & BN-675
ASH BIN FOR BF-600 & FGD-675
25
AI-710
FLUEGAS ANALYZER
26
ST-670
STACK
27
TK-700
PROCESS WATER TANK
28
P-705 A/B
PROCESS WATER PUMP A/B
29
C-900
AIR COMPRESSOR PACKAGE
30
MCC-01
MOTOR CONTROL CENTRE
6.9m * 09
- ALL STAIRCASE AND PLATFORMS SHOULD HAVE HANDRAILS AS PER INDIAN STANDARD. - SAFETY GUARD SHOULD BE PROVIDED FOR ALL ROTATING EQUIPMENT WHEREVER REQUIRED. - WARNING & SAFETY LABELS , ELECTRICAL AND FLOW INDICATORS MUST BE PROVIDED WHERE EVER APPLICABLE AS PER INDIAN STANDARDS. - PIPE & PIPE RACKS , CABLE & CABLE TRAY PIPE SUPPORTS ARE NOT SHOWN IN THE LAYOUT. - LAYOUT IS SUBJECT TO CHANGE AS PER FINAL DESIGN AND SITE CONDITION. * SUBJECT TO CHANGE AS PER FINAL DESIGN.
EL 0.0 14
SYNGAS ANALYZER
21
05
02
AI-680
17
03
01
10
H-540/SC550/RV-560 BF-600 & FGD-675
11 CONTROL ROOM & OFFICE SPACE
OXYGEN CYLINDERS
07
06
13
10.9m 11m
REV.
DATE
DRAWING TITLE
169-D-GG-000-1001
LAYOUT
DRAWING TITLE
PROJECT NAME
SHEET:1 OF 1
REVISIONS
DRAWING NO.
DESCRIPTION
ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE SPECIFIED. DO NOT SCALE DRAWING.
2 TPD ROTARY KILN GASIFICATION SYSTEM
FRONT ELEVATION CAD By: DATE:
PC
25-JUN-2021
CHD By: DATE:
GK
30-JUN-2021
APPD By: DATE:
AM
02-JUL-2021
PROJECT NO:
169
DRAWING NO:
169-D-GG-000-1002
REV NO:
0
VER NO:
0
SCALE :1:200
NOTES: - THIS IS A PRELIMINARY DRAWING ISSUED FOR RFQ PURPOSE ONLY, NOT FOR CONSTRUCTION OR INSTALLATION. - THE OVERALL DIMENSIONS AND EQUIPMENT SIZE IS SUBJECT TO CHANGE BASED ON FINAL SITE CONDITION AND DESIGN. - CIVIL STRUCTURES SHOWN IN THIS DRAWING IS ONLY FOR REFERENCE.
C
REFERENCE DRAWING LIST
STACK HEIGHT MUST BE AS PER LOCAL CODES AND REGULATIONS, STACK LOCATION IS SUBJECT TO CHANGE AS PER SITE CONDITION
COMPONENT NO.
TAG NO.
EQUIPMENT
01
SH-010
PLASTIC CHOPPER
2TPD GASIFICATION SYSTEM
02
BC-020
TRANSFER CONVEYOR
MIXED PLASTIC
03
SC-070
GASIFIER SCREW FEEDER
04
RX-300
GASIFIER
05
BRN-310
STARTUP BURNER
06
BL-320
STARTUP BURNER BLOWER
07
BL-330
PROCESS AIR BLOWER
08
AD-340
AIR DISTRIBUTOR
PROJECT OVER VIEW PLANT CAPACITY & PROCESS FEED
26
09
20
21
17
CONTROL ROOM & OFFICE SPACE
6.9m *
11
04
22
03
EL 0.0 27
23
29
14
02
07
10
AI-680
SYNGAS ANALYZER
11
CC-570
COMBUSTION CHAMBER
12
BRN-580
BURNER FOR CC-570
13
BL-585
BLOWER FOR COMBUSTION CHAMBER BURNER
14
BL-590
BLOWER FOR COMBUSTION CHAMBER
15
FV-350
MINI TRAVELLING GRATE
16
BN-360
ASH BIN
17
B-500
HEAT RECOVERY SYSTEM
18
TK-510
FEED WATER TANK
19
P-520 A/B
FEED WATER PUMPS
20
SORBENT INJECTION SYSTEM
21
H-540/SC550/RV-560 BF-600 & FGD-675
BAG FILTER & FLUEGAS DESULPHURIZER
22
CF-620
CARBON BED FILTER
23
F-660
ID BLOWER
24
BN-610 & BN-675
ASH BIN FOR BF-600 & FGD-675
25
AI-710
FLUEGAS ANALYZER
26
ST-670
STACK
27
TK-700
PROCESS WATER TANK
28
P-705 A/B
PROCESS WATER PUMP A/B
29
C-900
AIR COMPRESSOR PACKAGE
30
MCC-01
MOTOR CONTROL CENTRE
- ALL STAIRCASE AND PLATFORMS SHOULD HAVE HANDRAILS AS PER INDIAN STANDARD. - SAFETY GUARD SHOULD BE PROVIDED FOR ALL ROTATING EQUIPMENT WHEREVER REQUIRED. - WARNING & SAFETY LABELS , ELECTRICAL AND FLOW INDICATORS MUST BE PROVIDED WHERE EVER APPLICABLE AS PER INDIAN STANDARDS. - PIPE & PIPE RACKS , CABLE & CABLE TRAY PIPE SUPPORTS ARE NOT SHOWN IN THE LAYOUT. - LAYOUT IS SUBJECT TO CHANGE AS PER FINAL DESIGN AND SITE CONDITION. * SUBJECT TO CHANGE AS PER FINAL DESIGN.
18
28
OXYGEN CYLINDERS
01
13.2m 15m
REV.
DATE
DRAWING TITLE
169-D-GG-000-1001
LAYOUT
DRAWING TITLE
PROJECT NAME
SHEET:1 OF 1
REVISIONS
DRAWING NO.
DESCRIPTION
ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE SPECIFIED. DO NOT SCALE DRAWING.
2 TPD ROTARY KILN GASIFICATION SYSTEM
LEFT SIDE ELEVATION CAD By: DATE:
PC
25-JUN-2021
CHD By: DATE:
GK
30-JUN-2021
APPD By: DATE:
AM
02-JUL-2021
PROJECT NO:
169
DRAWING NO:
169-D-GG-000-1003
REV NO:
0
C
NOTES: - THIS IS A PRELIMINARY DRAWING ISSUED FOR RFQ PURPOSE ONLY, NOT FOR CONSTRUCTION OR INSTALLATION. - THE OVERALL DIMENSIONS AND EQUIPMENT SIZE IS SUBJECT TO CHANGE BASED ON FINAL SITE CONDITION AND DESIGN. - CIVIL STRUCTURES SHOWN IN THIS DRAWING IS ONLY FOR REFERENCE.
VER NO:
0
SCALE :1:40
REFERENCE DRAWING LIST
PROJECT OVER VIEW 2TPD GASIFICATION SYSTEM
TAG NO.
EQUIPMENT
01
SH-010
PLASTIC CHOPPER
02
BC-020
TRANSFER CONVEYOR
03
SC-070
GASIFIER SCREW FEEDER
04
RX-300
GASIFIER
05
BRN-310
STARTUP BURNER
06
BL-320
STARTUP BURNER BLOWER
07
BL-330
PROCESS AIR BLOWER
08
AD-340
AIR DISTRIBUTOR
STACK HEIGHT MUST BE AS PER LOCAL CODES AND REGULATIONS, STACK LOCATION IS SUBJECT TO CHANGE AS PER SITE CONDITION
MIXED PLASTIC
09
26 20
21 17 02
11
12
06
09
13
15
TROLLEY FOR ASH BIN MOVEMENT
16
27
SYNGAS ANALYZER
11
CC-570
COMBUSTION CHAMBER
12
BRN-580
BURNER FOR CC-570
13
BL-585
BLOWER FOR COMBUSTION CHAMBER BURNER
14
BL-590
BLOWER FOR COMBUSTION CHAMBER
15
FV-350
MINI TRAVELLING GRATE
16
BN-360
ASH BIN
17
B-500
HEAT RECOVERY SYSTEM
18
TK-510
FEED WATER TANK
19
P-520 A/B
FEED WATER PUMPS
20
SORBENT INJECTION SYSTEM
21
H-540/SC550/RV-560 BF-600 & FGD-675
BAG FILTER & FLUEGAS DESULPHURIZER
22
CF-620
CARBON BED FILTER
23
F-660
ID BLOWER
24
BN-610 & BN-675
ASH BIN FOR BF-600 & FGD-675
25
AI-710
FLUEGAS ANALYZER
26
ST-670
STACK
27
TK-700
PROCESS WATER TANK
28
P-705 A/B
PROCESS WATER PUMP A/B
29
C-900
AIR COMPRESSOR PACKAGE
30
MCC-01
MOTOR CONTROL CENTRE
- ALL STAIRCASE AND PLATFORMS SHOULD HAVE HANDRAILS AS PER INDIAN STANDARD. - SAFETY GUARD SHOULD BE PROVIDED FOR ALL ROTATING EQUIPMENT WHEREVER REQUIRED. - WARNING & SAFETY LABELS , ELECTRICAL AND FLOW INDICATORS MUST BE PROVIDED WHERE EVER APPLICABLE AS PER INDIAN STANDARDS. - PIPE & PIPE RACKS , CABLE & CABLE TRAY PIPE SUPPORTS ARE NOT SHOWN IN THE LAYOUT. - LAYOUT IS SUBJECT TO CHANGE AS PER FINAL DESIGN AND SITE CONDITION. * SUBJECT TO CHANGE AS PER FINAL DESIGN.
EL 0.0 01
AI-680
18
13.2 m
15m
REFERENCE DRAWING LIST
NOTES: - THIS IS A PRELIMINARY DRAWING ISSUED FOR RFQ PURPOSE ONLY, NOT FOR CONSTRUCTION OR INSTALLATION. - THE OVERALL DIMENSIONS AND EQUIPMENT SIZE IS SUBJECT TO CHANGE BASED ON FINAL SITE CONDITION AND DESIGN. - CIVIL STRUCTURES SHOWN IN THIS DRAWING IS ONLY FOR REFERENCE.
REVISIONS REV.
DATE
DRAWING NO.
DRAWING TITLE
169-D-GG-000-1001
LAYOUT
DRAWING TITLE
PROJECT NAME
DESCRIPTION
2 TPD ROTARY KILN GASIFICATION SYSTEM
RIGHT SIDE ELEVATION
ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE SPECIFIED. DO NOT SCALE DRAWING. CAD By: DATE:
PC
25-JUN-2021
CHD By: DATE:
GK
30-JUN-2021
APPD By: DATE:
AM
02-JUL-2021
PROJECT NO:
169
DRAWING NO:
169-D-GG-000-1004
REV NO:
0
VER NO:
0
SCALE :1:200
04
10
C
08
6.9 m *
03
OXYGEN CYLINDERS
SHEET:1 OF 1
PLANT CAPACITY & PROCESS FEED
COMPONENT NO.
COMPONENT TAG NO. NO
11m
10.9m
1.9m
1.8m
08
15m
07
01
SH-010
PLASTIC CHOPPER
02
BC-020
TRANSFER CONVEYOR
03
SC-070
GASIFIER SCREW FEEDER
04
RX-300
GASIFIER
05
BRN-310
STARTUP BURNER
06
BL-320
STARTUP BURNER BLOWER
07
BL-330
PROCESS AIR BLOWER
08
AD-340
AIR DISTRIBUTOR
09
OXYGEN CYLINDERS
2.8m
10
1.0m
2.2m
1.2m
1.0m
0.6m 2.6m
AI-680
SYNGAS ANALYZER
NOTES: - THIS IS A PRELIMINARY DRAWING ISSUED FOR RFQ PURPOSE ONLY, NOT FOR CONSTRUCTION OR INSTALLATION - THE OVERALL DIMENSIONS AND FINAL SIZE IS SUBJECT TO CHANGE BASED ON FINAL SITE CONDITION AND DESIGN. -CIVIL STRUCTURE SHOWN IN THIS DRAWING IS ONLY FOR REFERENCE
06
0.3m
EQUIPMENT
0.4m 2.2m
1.7m
0.8m
0.6m
1.6m
TOP VIEW
02
03
04
05
09
3.8m
01
ISOMETRIC VIEW SCALE 1 : 100
EL 0.0
DRAWING TITLE
169-D-GG-000-1001
LAYOUT
REV.
DATE
DRAWING TITLE
PROJECT NAME
SHEET:1 OF 1
REVISIONS DESCRIPTION
ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE SPECIFIED. DO NOT SCALE DRAWING.
2 TPD ROTARY KILN GASIFICATION SYSTEM
GASIFIER COMPONENTS CAD By: DATE:
PC
25-JUN-2021
CHD By: DATE:
GK
30-JUN-2021
APPD By: DATE:
AM
02-JUL-2021
PROJECT NO:
169
DRAWING NO:
169-D-GG-300-2000
REV NO:
0
C
DRAWING NO.
FRONT VIEW
VER NO:
0
SCALE :1:40
REFERENCE DRAWING LIST
COMPONENT TAG NO. NO
11m
19
19
18
17
11
CC-570
COMBUSTION CHAMBER
12
BRN-580
BURNER FOR CC-570
13
BL-585
BLOWER FOR COMBUSTION CHAMBER BURNER
14
BL-590
BLOWER FOR COMBUSTION CHAMBER
15
FV-350
MINI TRAVELLING GRATE
16
BN-360
ASH BIN
17
B-500
HEAT RECOVERY SYSTEM
18
TK-510
FEED WATER TANK
19
P-520 A/B
FEED WATER PUMPS
NOTES: - THIS IS A PRELIMINARY DRAWING ISSUED FOR RFQ PURPOSE ONLY, NOT FOR CONSTRUCTION OR INSTALLATION - THE OVERALL DIMENSIONS AND FINAL SIZE IS SUBJECT TO CHANGE BASED ON FINAL SITE CONDITION AND DESIGN. -CIVIL STRUCTURE SHOWN IN THIS DRAWING IS ONLY FOR REFERENCE.
9.5m
15m
** TROLLEY
EQUIPMENT
16
15
3.7m
11
4.7m
0.3m
TOP VIEW
12
REFERENCE DRAWING LIST
EL 0.0
FRONT VIEW REVISIONS REV.
DATE
DRAWING NO.
DRAWING TITLE
169-D-GG-000-1001
LAYOUT
DRAWING TITLE
PROJECT NAME
DESCRIPTION
2 TPD ROTARY KILN GASIFICATION SYSTEM
STEAM GENERATION COMPONENTS
ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE SPECIFIED. DO NOT SCALE DRAWING. CAD By: DATE:
PC
25-JUN-2021
CHD By: DATE:
GK
30-JUN-2021
APPD By: DATE:
AM
02-JUL-2021
PROJECT NO:
169
DRAWING NO:
169-D-GG-500-2000
REV NO:
0
VER NO:
0
SCALE :1:50
13
C
14
ISOMETRIC VIEW SCALE 1 : 100
SHEET:1 OF 1
4.3m
** The Ash bin is Placed on a movable trolley which will move the Ash bin in and out from its location for ash removal.Trolly will be pulled out and then the Ash bin will be moved out by using a forklift or similar arrangement.The ash can be emptied as per site facility available. In its place an empty Ash bin can be placed and the trolly can be pushed back to its original location. A flexible joint made up of high temp , non breathable ceramic fibre cloth or similar is being used between Mini travelling grate and Ash bin. This Flexible joint must be leak proof and quick releasable type.
1.4m
COMPONENT TAG NO. NO
7m
SORBENT INJECTION SYSTEM
21
H-540/SC550/RV-560 BF-600 & FGD-675
22
CF-620
CARBON BED FILTER
23
F-660
ID BLOWER
24
BN-610 & BN-675
ASH BIN FOR BF-600 & FGD-675
25
AI-710
FLUEGAS ANALYZER
15m
3.5m
20
3.2m
EQUIPMENT
BAG FILTER & FLUEGAS DESULPHURIZER
NOTES: - THIS IS A PRELIMINARY DRAWING ISSUED FOR RFQ PURPOSE ONLY, NOT FOR CONSTRUCTION OR INSTALLATION - THE OVERALL DIMENSIONS AND FINAL SIZE IS SUBJECT TO CHANGE BASED ON FINAL SITE CONDITION AND DESIGN. - CIVIL STRCTURE SHOWN IN THIS DRAWING IS ONLY FOR REFERENCE
11m
TOP VIEW
20
6.9m
21 22
ISOMETRIC VIEW SCALE 1 : 100 23 24
REV.
DATE
169-D-GG-000-1001
LAYOUT
DRAWING TITLE
PROJECT NAME
SHEET:1 OF 1
REVISIONS
DRAWING TITLE
DESCRIPTION
ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE SPECIFIED. DO NOT SCALE DRAWING.
2 TPD ROTARY KILN GASIFICATION SYSTEM
FLUEGAS CLEANUP COMPONENTS CAD By: DATE:
PC
25-JUN-2021
CHD By: DATE:
GK
30-JUN-2021
APPD By: DATE:
AM
02-JUL-2021
PROJECT NO:
169
DRAWING NO:
169-D-GG-600-2000
REV NO:
0
C
FRONT VIEW
DRAWING NO.
VER NO:
0
SCALE :1:40
REFERENCE DRAWING LIST
EL 0.0
1.1m
1m
COMPONENT TAG NO. NO
1.3m 0.03m 1m
26
ST-670
STACK
27
TK-700
PROCESS WATER TANK
28
P-705 A/B
PROCESS WATER PUMP A/B
29
C-900
AIR COMPRESSOR PACKAGE
9m
1.8m
2.8m
EQUIPMENT
NOTES: - THIS IS A PRELIMINARY DRAWING ISSUED FOR RFQ PURPOSE ONLY, NOT FOR CONSTRUCTION OR INSTALLATION - THE OVERALL DIMENSIONS AND FINAL SIZE IS SUBJECT TO CHANGE BASED ON FINAL SITE CONDITION AND DESIGN. -CIVIL STRUCTURE SHOWN IN THIS DRAWING IS ONLY FOR REFERENCE
15m
1.2m 1m
3m
2.7m 2.8m
0.7m
0.6m
3.7m
11m
TOP VIEW
STACK HEIGHT AS PER LOCAL CODES & REGULATIONS 26
29
1.5m
ISOMETRIC VIEW SCALE 1 : 100
EL 0.0
DRAWING TITLE
169-D-GG-000-1001
LAYOUT
REVISIONS REV.
DATE
DRAWING TITLE
PROJECT NAME
DESCRIPTION
ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE SPECIFIED. DO NOT SCALE DRAWING.
2 TPD ROTARY KILN GASIFICATION SYSTEM
AUXILIARY COMPONENTS CAD By: DATE:
PC
25-JUN-2021
CHD By: DATE:
GK
30-JUN-2021
APPD By: DATE:
AM
02-JUL-2021
PROJECT NO:
169
DRAWING NO:
169-D-GG-900-2000
REV NO:
0
C
DRAWING NO.
FRONT VIEW
VER NO:
0
SCALE :1:40
REFERENCE DRAWING LIST
SHEET:1 OF 1
27
0.4m
1.2m
28
TAG NUMBER
DESCRIPTION
02
BC-020
TRANSFER CONVEYOR
DESIGN SPECIFICATION
788
701
1254 580
TOP VIEW
831
ISOMETRIC VIEW
3497
CAPACITY
100 kg/hr WITH 20% DESIGN MARGIN
MATERIAL
SHREDDED PLASTIC
BULK DENSITY
100-200 kg/m3
MATERIAL SIZE
1/2 - 1 " PRE SHREDDED
MOISTURE
MAX 20%
CONVEYOR TYPE
SIDE WALL CONVEYOR
BELT TYPE
RUBBER CLEATED
BELT MUST BE COVERED TO PREVENT SPILLAGE AND DUST
3380
* GEARED MOTOR IS NOT SHOWN IN THE DRAWING, REFER EQUIPMENT SPECIFICATION SHEET FOR MORE DETAILS
** THIS ANGLE CAN BE INCREASED TO MAXIMUM POSSIBLE TO REDUCE THE FOOT PRINT
577
1103
°
630
2286
SIDE VIEW
REV.
DATE
DRAWING TITLE
PROJECT NAME
DESCRIPTION
ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE SPECIFIED. DO NOT SCALE DRAWING.
2 TPD ROTARY KILN GASIFICATION SYSTEM
TRANSFER CONVEYOR CAD By: DATE:
PC
25-JUN-2021
CHD By: DATE:
GK
30-JUN-2021
APPD By: DATE:
AM
02-JUL-2021
PROJECT NO:
169
DRAWING NO:
169-D-GG-020-1000
REV NO:
0
VER NO:
0
SCALE :1:20
REVISIONS
C
FRONT VIEW NOTES: - THIS IS A PRELIMINARY DRAWING ISSUED FOR RFQ PURPOSE ONLY, NOT FOR CONSTRUCTION OR INSTALLATION. - EQUIPMENT SIZE, DIMENSION AND SHAPE ARE SUBJECT TO CHANGE BASED ON FINAL SITE CONDITIONS AND DESIGN. SHEET:1 OF 1
PROJECTION
COMPONENT NO.
4511
70
MACHINING TOLERANCE FOR LINEAR GENERAL TOLERANCE FOR LINEAR SURFACE FINISH SYMBOLS DIMENSIONS, IS-2102(MEDIUM) DIMENSIONS, IS-2102(COARSE) ⁓ 30 120 400 1000 2000 OVER 0.5 3 30 120 400 1000 2000 ROUGHNESS 6 OVER 0.5 3 6 SYMBOL 30 120 400 1000 2000 4000 UPTO 3 6 30 120 400 1000 2000 4000 UPTO 3 6 N1 N2 N3 N4 N5 N6 N7 N8 N9 3.0 1.2 4.0 2.0 0.2 0.3 0.5 0.8 1.2 2.0 0.1 0.1 0.2 0.3 0.5 0.8 TOL TOL 0.2 0.4 0.8 1.6 3.2 6.3 12.5 25 50 Ra, µm ANGULAR DIMENSIONS: 1 ANGULAR DIMENSIONS: 1
REFERENCE DRAWING LIST DRAWING NO. DRAWING TITLE 169-D-GG-000-1001 LAYOUT 169-D-GG-300-2000 GASIFIER COMPONENTS
THIS IS THE FEED CHUTE MATCHING FLANGE AND HAS TO BE WELDED AT SITE
DRAWING NO.
DRAWING TITLE
169-D-GG-000-1001
LAYOUT
169-D-GG-300-2000
GASIFIER COMPONENTS
COMPONENT NO.
TAG NUMBER
03
SC-070
DESCRIPTION GASIFIER SCREW FEEDER
DESIGN SPECIFICATIONS PRE PROCESSED WASTE FEED 100 kg/hr CAPACITY
SS-304 SCREW DIA 240mm PITCH 1:1
610
370
M10 STUD SHOULD BE WELDED TO THE ACCESS DOOR. SILICON GASKET TO BE CONSIDERED FOR PROPER SEALING
FEED DENSITY
100 TO 200 kg/m3
MAX. LUMP SIZE
25 mm
FEED MOISTURE
20% MAX.
SCREW INSTALLATION
CANTILEVER
MOTOR POWER
3 HP *
695
REFER EQUIPMENT SPECIFICATION SHEET FOR MORE DETAILS * SUBJECTED TO CHANGE AS PER FINAL DESIGN
545 TOP VIEW
FEED INLET 10"CARBON STEEL SCH40 PIPE
212
A
1342 ISOMETRIC VIEW
361 265
SQ.TUBE 70X70X5.0
700
1336
SQ.TUBE 100X100X3.2
1701
2062
FEED DISCHARGE
SECTION A-A 629 916
2044
A SIDE VIEW
FRONT VIEW
REV.
DATE
DRAWING TITLE
PROJECT NAME
DESCRIPTION
ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE SPECIFIED. DO NOT SCALE DRAWING.
2 TPD ROTARY KILN GASIFICATION SYSTEM
GASIFIER SCREW FEEDER CAD By: DATE:
PC
25-JUN-2021
CHD By: DATE:
GK
30-JUN-2021
APPD By: DATE:
AM
02-JUL-2021
PROJECT NO:
169
DRAWING NO:
169-D-GG-070-1000
REV NO:
0
VER NO:
0
SCALE :1:20
REVISIONS
C
NOTES: - THIS IS A PRELIMINARY DRAWING ISSUED FOR RFQ PURPOSE ONLY, NOT FOR CONSTRUCTION OR INSTALLATION. - EQUIPMENT SIZE, DIMENSION AND SHAPE ARE SUBJECT TO CHANGE BASED ON FINAL SITE CONDITIONS AND DESIGN. SHEET:1 OF 1
PROJECTION
MACHINING TOLERANCE FOR LINEAR GENERAL TOLERANCE FOR LINEAR SURFACE FINISH SYMBOLS DIMENSIONS, IS-2102(MEDIUM) DIMENSIONS, IS-2102(COARSE) ⁓ 30 120 400 1000 2000 OVER 0.5 3 30 120 400 1000 2000 ROUGHNESS 6 OVER 0.5 3 6 SYMBOL 30 120 400 1000 2000 4000 UPTO 3 6 30 120 400 1000 2000 4000 UPTO 3 6 N1 N2 N3 N4 N5 N6 N7 N8 N9 3.0 1.2 4.0 2.0 0.2 0.3 0.5 0.8 1.2 2.0 0.1 0.1 0.2 0.3 0.5 0.8 TOL TOL 0.2 0.4 0.8 1.6 3.2 6.3 12.5 25 50 Ra, µm ANGULAR DIMENSIONS: 1 ANGULAR DIMENSIONS: 1
REFERENCE DRAWING LIST
DRAWING TITLE
169-D-GG-000-1001
LAYOUT
169-D-GG-300-2000
GASIFIER COMPONENTS
04.10 04.02
04.17
462
04.11
1
2600*
04.01 KILN
IS 2062 Gr A,1060mm ID x 1080mm OD x 10mm Thk
1
345
04.02 INLET HOOD
INTEGRATED INLET HOOD DESIGN, SS 310, 300mm LG x 10mm THK, WITH 50mm REFRACTORY
1
100
04.03 TYRES
IS 2708, 1120mm ID x 1270mm OD x 75mm W , HARDNES 220-230 BHN
2
125 ea
04.04 MAIN SPROCKET
EN9, BRN 200-230, 104 TEETH, 1.5" PITCH, 1242mm PCD x 23.1mm THK, ANSI CHAIN NO.120 OR EQUIVALENT, 4 PIECE DESIGN
1
40
04.05 PINION SPROCKET
EN9, BRN 200-230, 15 TEETH, 1.5" PITCH, 181mm PCD x 15mm THK, ANSI CHAIN NO.120 OR EQUIVALENT
1
5
04.06 IDLER SPROCKET
EN9, BRN 200-230, 15 TEETH, 1.5" PITCH, 181mm PCD x 15mm THK, ANSI CHAIN NO.120 OR EQUIVALENT
1
5
04.07 PINION SHAFT
EN19, 60mm OD X 450mm LG
1
10
04.08 LOCK RING
4
25 ea
12
1 ea
04.11 INTEGRATED FEED CHUTE
IS 2062, 1120mm ID x 1190mm OD x 20mm THK IS 2062, 50mm W x 38mm H x 12mm THK IS 2062 WITH HIGH TEMP FLEXIBLE NON BREATHABLE SEAL SS 310, 263mm ID x 5mm THK , AIR COOLED AND PROCESS INTEGRATED
04.12 BURNER NOZZLE
04.20
04.12
04.18
04.05 04.13
04.15
23
150
600
04.07
04.14
135
237
04.16
300
04.19
FOR 04.09 SUPPORT MAIN SPROCKET HOOD 04.10 INLET SEAL CHAMBER
1769 08
1
25
1
30
TO SUIT BURNER DIMENSIONS ***
1
8
04.13 ROLLER
IS 2708, 170mm DIA, 210mm COLLAR OD, 125mm WIDTH
4
15 ea
04.14 ROLLER SHAFT
EN19, 60mm OD X 310mm LG
4
6 ea
04.15 PILLOW BLOCK
SKF OR EQUIVALENT, MODEL: SY50TR, BALL BEARING SHAFT DIA 50mm
10
3 ea
04.16 COUPLING
FCL 180
1
12
04.17 CHAIN
ANSI CHAIN NO.120, 4.7m LG **
1
9
04.18 CHAIN COVER
IS 2062
1
40
04.19 GEAR MOTOR
3HP, GEARBOX OUTPUT RPM 32 KILN RPM 0.3 TO 3 VFD CONTROLLED **
1
04.20 CHAIR PLATE
IS 2062, 150mm W x 95mm L x 10mm THK
04.21 DENSE REFRACTORY
80mm THK ACID RESISTANT DENSE REFRACTORY, 60% ALUMINA **
1
570
04.22 INSULATION REFRACTORY
150mm THK CASTABLE INSULATION REFRACTORY ** 3" SCH40 PIPE WITH ANSI 150# FLANGE
1
800
1
10
FEED INLET
ISOMETRIC VIEW
TOP VIEW A
1620 1300, KILN LENGTH
150
04.22
300
800
102
04.21
10
*
350
23°
216
1270 TYRE OD
536
1080
60
1060
AIR INLET
600, KILN ID 760
388 08
TRUE R85 ROLLER RADIUS 30°
300
SECTION A-A
A
967
TYPE OPERATING TEMPERATURE FEED CAPACITY
150
950
NOTES: - THIS IS A PRELIMINARY DRAWING ISSUED FOR RFQ PURPOSE ONLY, NOT FOR CONSTRUCTION OR INSTALLATION. - EQUIPMENT SIZE, DIMENSION AND SHAPE ARE SUBJECT TO CHANGE BASED ON FINAL SITE CONDITIONS AND DESIGN.
SHREDDED PLASTIC 100 TO 200 kg/m3
ROTATION SPEED 0.3 to 3 RPM TURNDOWN RATIO 4:1 REFER EQUIPMENT SPECIFICATION SHEET FOR MORE DETAILS
REVISIONS DATE
75
DESIGN SPECIFICATIONS ROTARY KILN 900 deg C 100 kg/hr
FEED TYPE FEED DENSITY
FRONT VIEW
REV.
AIR DISTRIBUTOR
60
* THE WEIGHT SHOWN IS WITHOUT SUPPORT STRUCTURES. ** SUBJECTED TO CHANGE AS PER FINAL DESIGN *** BURNER CAPACITY 125,000 KCal/h MUST BE USED FOR PRE HEATING PURPOSE (REFER SPECIFICATION SHEET) - 60 DEG V SHAPE 6mm DIA SS310 REFRACTORY ANCHORS PLACED 4" APART TO BE CONSIDERED. - 2 COAT ZINC RICH PRIMER AND 2 COAT ENAMEL PAINT MUST BE APPLIED. - CHAIN AND COUPLING GUARDS MUST BE PROVIDED AS PER OSHA. - HEAT TREATMENT FOR THE COMPONENT MUST BE CONSIDERED AS PER DESIGN REQUIREMENT. - THRUST ROLLER MUST BE CONSIDERED (NOT SHOWN IN THE DRAWING) - AN EXTENDED ASH CHUTE (SS310) AT KILN DISCHARGE SIDE MAY BE REQUIRED AS PER MINI TRAVELLING GRATE FEED INTAKE POSITION (NOT SHOWN IN THE DRAWING)
1701
1264 MAIN SPROCKET OD
ROTARY KILN GASIFIER
DISCHARGE
04.06
150 75
GASIFIER (RX-300)
DRAWING TITLE
PROJECT NAME
DESCRIPTION
ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE SPECIFIED. DO NOT SCALE DRAWING.
2 TPD ROTARY KILN GASIFICATION SYSTEM
GASIFIER CAD By: DATE:
PC
25-JUN-2021
CHD By: DATE:
GK
30-JUN-2021
APPD By: DATE:
AM
02-JUL-2021
PROJECT NO:
169
DRAWING NO:
169-D-GG-300-1000
REV NO:
0
VER NO:
0
SCALE :1:20
04.08
SPECIFICATION
04
QTY
APPROX. WEIGHT (kg)
DESCRIPTION
C
04.01
300 PROJECTION
DRAWING NO.
04.09 04.04
COMPONENT NO.
SHEET:1 OF 1
04.03
2°
MACHINING TOLERANCE FOR LINEAR GENERAL TOLERANCE FOR LINEAR SURFACE FINISH SYMBOLS DIMENSIONS, IS-2102(MEDIUM) DIMENSIONS, IS-2102(COARSE) ⁓ 30 120 400 1000 2000 OVER 0.5 3 30 120 400 1000 2000 ROUGHNESS 6 OVER 0.5 3 6 SYMBOL 30 120 400 1000 2000 4000 UPTO 3 6 30 120 400 1000 2000 4000 UPTO 3 6 N1 N2 N3 N4 N5 N6 N7 N8 N9 3.0 1.2 4.0 2.0 0.2 0.3 0.5 0.8 1.2 2.0 0.1 0.1 0.2 0.3 0.5 0.8 TOL TOL 0.2 0.4 0.8 1.6 3.2 6.3 12.5 25 50 Ra, µm ANGULAR DIMENSIONS: 1 ANGULAR DIMENSIONS: 1
REFERENCE DRAWING LIST
169-D-GG-500-2000
COMPONENT NO.
ITEM
DESCRIPTION
17
B-500
HEAT RECOVERY SYSTEM
STEAM GENERATION COMPONENTS DESIGN SPECIFICATIONS
3161 1000
TYPE
WATER TUBE BOILER
GAS FLOW RATE
1200 Nm3/hr
INLET GAS TEMPERATURE
1200 deg C
OUTLET GAS TEMPERATURE
150 deg C
ASH CARRY OVER IN FLUEGAS 2 kg/hr
484
918
568
350
STEAM PRODUCTION
MAX. 500 kg/hr
STEAM DICHARGE PRESSURE
4.5 barA
REFER EQUIPMENT SPECIFICATION SHEET FOR MORE DETAILS - THE MODEL SHOWN IN THE DRAWING IS ONLY FOR REFERENCE * SUBJECTED TO CHANGE
326
TOP VIEW
8" * FLUE GAS EXIT NOZZLE
2" * STEAM EXIT NOZZLE
1003
INTEGRATED STEAM DRUM
406
ISOMETRIC VIEW
467
1499
2524
8" DENSE PHASE REFRACTORY COATED FLUE GAS INLET DUCT
1835 FRONT VIEW
SIDE VIEW
REV.
DATE
DRAWING TITLE
PROJECT NAME
DESCRIPTION
ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE SPECIFIED. DO NOT SCALE DRAWING.
2 TPD ROTARY KILN GASIFICATION SYSTEM
HEAT RECOVERY SYSTEM CAD By: DATE:
PC
25-JUN-2021
CHD By: DATE:
GK
30-JUN-2021
APPD By: DATE:
AM
02-JUL-2021
PROJECT NO:
169
DRAWING NO:
169-D-GG-500-1000
REV NO:
0
VER NO:
0
SCALE :1:20
REVISIONS
C
NOTES: - THIS IS A PRELIMINARY DRAWING ISSUED FOR RFQ PURPOSE ONLY, NOT FOR CONSTRUCTION OR INSTALLATION. - EQUIPMENT SIZE, DIMENSION AND SHAPE ARE SUBJECT TO CHANGE BASED ON FINAL SITE CONDITIONS AND DESIGN. SHEET:1 OF 1
PROJECTION
MACHINING TOLERANCE FOR LINEAR GENERAL TOLERANCE FOR LINEAR SURFACE FINISH SYMBOLS DIMENSIONS, IS-2102(MEDIUM) DIMENSIONS, IS-2102(COARSE) ⁓ 30 120 400 1000 2000 OVER 0.5 3 30 120 400 1000 2000 ROUGHNESS 6 OVER 0.5 3 6 SYMBOL 30 120 400 1000 2000 4000 UPTO 3 6 30 120 400 1000 2000 4000 UPTO 3 6 N1 N2 N3 N4 N5 N6 N7 N8 N9 3.0 1.2 4.0 2.0 0.2 0.3 0.5 0.8 1.2 2.0 0.1 0.1 0.2 0.3 0.5 0.8 TOL TOL 0.2 0.4 0.8 1.6 3.2 6.3 12.5 25 50 Ra, µm ANGULAR DIMENSIONS: 1 ANGULAR DIMENSIONS: 1
REFERENCE DRAWING LIST DRAWING NO. DRAWING TITLE 169-D-GG-000-1001 LAYOUT
TAG NUMBER
DESCRIPTION
11
CC-070
COMBUSTION CHAMBER
STEAM GENERATION COMPONENTS DESIGN SPECIFICATIONS
526
WATER WALL CONSTRUCTION
INLET SYNGAS FLOW RATE
172 Nm3/hr
OUTLET FLUEGAS FLOW RATE
876 Nm3/hr
DESIGN TEMPERATURE
1200 deg C
SYNGAS TEMPERATURE
900 degC
SYNGAS INLET PRESSURE
-5 TO 0 mmWC *
PREHEATING BURNER CAPACITY 0.125 MMkcal/hr *
1628
2684
CONSTRUCTION
MAXIMUM SKIN TEMPERATURE
150 deg C
THE OUTER SHELL SHOULD BE INSULATED WITH 2" CERAMIC WOOL WITH GI CLADDING. ( SUBJECTED TO CHANGE AS PER DESIGN REQUIREMENT 26 0
°
TOP VIEW
REFER BURNER MOUNTING FLANGE DIMENSIONS
8" DENSE PHASE REFRACTORY LINED FLUE GAS OUTLET DUCT ( NOT SHOWN )
BURNER MOUNTING FLANGE
WATER WALLED CONSTRUCTION
SUITABLE AIR TIGHT SEALING ARRANGEMENT MUST BE CONSIDERED BETWEEN COMBUSTION CHAMBER AND ASH DISCHARGE MECHANISM
ISOMETRIC VIEW 266
784
467
692
829
FROM GASIFIER
929
FLUE GAS EXIT
1777
114
114
3633
SIDE VIEW
FRONT VIEW
REFER EQUIPMENT SPECIFICATION SHEET FOR MORE DETAILS - THE MODEL SHOWN IN THE DRAWING IS ONLY FOR REFERENCE * SUBJECTED TO CHANGE
NOTES: - THIS IS A PRELIMINARY DRAWING ISSUED FOR RFQ PURPOSE ONLY, NOT FOR CONSTRUCTION OR INSTALLATION. - EQUIPMENT SIZE, DIMENSION AND SHAPE ARE SUBJECT TO CHANGE BASED ON FINAL SITE CONDITIONS AND DESIGN. REVISIONS REV.
DATE
DRAWING TITLE
PROJECT NAME
DESCRIPTION
2 TPD ROTARY KILN GASIFICATION SYSTEM
COMBUSTION CHAMBER
ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE SPECIFIED. DO NOT SCALE DRAWING. CAD By: DATE:
PC
25-JUN-2021
CHD By: DATE:
GK
30-JUN-2021
APPD By: DATE:
AM
02-JUL-2021
PROJECT NO:
169
DRAWING NO:
169-D-GG-570-1000
REV NO:
0
VER NO:
0
SCALE :1:20
690
554
685
C
REFRACTORY LINED INLET
SHEET:1 OF 1
PROJECTION
169-D-GG-500-2000
COMPONENT NO.
4 13
MACHINING TOLERANCE FOR LINEAR GENERAL TOLERANCE FOR LINEAR SURFACE FINISH SYMBOLS DIMENSIONS, IS-2102(MEDIUM) DIMENSIONS, IS-2102(COARSE) ⁓ 30 120 400 1000 2000 OVER 0.5 3 30 120 400 1000 2000 ROUGHNESS 6 OVER 0.5 3 6 SYMBOL 30 120 400 1000 2000 4000 UPTO 3 6 30 120 400 1000 2000 4000 UPTO 3 6 N1 N2 N3 N4 N5 N6 N7 N8 N9 3.0 1.2 4.0 2.0 0.2 0.3 0.5 0.8 1.2 2.0 0.1 0.1 0.2 0.3 0.5 0.8 TOL TOL 0.2 0.4 0.8 1.6 3.2 6.3 12.5 25 50 Ra, µm ANGULAR DIMENSIONS: 1 ANGULAR DIMENSIONS: 1
REFERENCE DRAWING LIST DRAWING NO. DRAWING TITLE 169-D-GG-000-1001 LAYOUT
DRAWING TITLE
169-D-GG-000-1001
LAYOUT
169-D-GG-600-2000
FLUEGAS CLEANUP COMPONENTS
343
315
345
433
TAG NUMBER
DESCRIPTION
22
CF-620
CARON BED FILTER
DESIGN SPECIFICATIONS ADSORBENT MATERIAL
ACTIVATED CARBON. RE-USABLE CARTRIDGE SIZE-L 300mmX W 600mmX T 50mm,2 NOS
MAXIMUM TEMPERATURE
120 deg C
FILTRATION EFFICIENCY
90% TO 99%
PARTICLE REMOVAL SIZE
UPTO 3 MICRONS
FILTER EFFICIENCY RATING MERV 7 CARBON CONCENTRATION
300 g/ft3
NOTE:ACTIVATED CARBON CARTRIDGES NOT SHOWN IN THE DRAWING
558
REFER EQUIPMENT SPECIFICATION SHEET FOR MORE DETAILS THE MODEL SHOWN IN THE DRAWING IS ONLY FOR REFERENCE * SUBJECTED TO CHANGE
758 TOP VIEW ISOMETRIC VIEW
INLET NOZZLE 8" ANSI 150 CLASS FLANGE 3
MOC: CARBON STEEL
EXIT NOZZLE 8" ANSI 150 CLASS FLANGE
356
93
175
ACCESS DOOR WITH QUICK RELEASE LATCHES
886
°
255
54
435
FLUE GAS INLET
100
A
°
TYP.25
SIDE VIEW
SECTION A-A
A FRONT VIEW FLUE GAS EXIT
REV.
DATE
DRAWING TITLE
PROJECT NAME
DESCRIPTION
ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE SPECIFIED. DO NOT SCALE DRAWING.
2 TPD ROTARY KILN GASIFICATION SYSTEM
CARBON BED FILTER CAD By: DATE:
PC
25-JUN-2021
CHD By: DATE:
GK
30-JUN-2021
APPD By: DATE:
AM
02-JUL-2021
PROJECT NO:
169
DRAWING NO:
169-D-GG-620-1000
REV NO:
0
VER NO:
0
SCALE :1:10
REVISIONS
C
NOTES: - THIS IS A PRELIMINARY DRAWING ISSUED FOR RFQ PURPOSE ONLY, NOT FOR CONSTRUCTION OR INSTALLATION. - EQUIPMENT SIZE, DIMENSION AND SHAPE ARE SUBJECT TO CHANGE BASED ON FINAL SITE CONDITIONS AND DESIGN. SHEET:1 OF 1
PROJECTION
DRAWING NO.
COMPONENT NO.
79
MACHINING TOLERANCE FOR LINEAR GENERAL TOLERANCE FOR LINEAR SURFACE FINISH SYMBOLS DIMENSIONS, IS-2102(MEDIUM) DIMENSIONS, IS-2102(COARSE) ⁓ 30 120 400 1000 2000 OVER 0.5 3 30 120 400 1000 2000 ROUGHNESS 6 OVER 0.5 3 6 SYMBOL 30 120 400 1000 2000 4000 UPTO 3 6 30 120 400 1000 2000 4000 UPTO 3 6 N1 N2 N3 N4 N5 N6 N7 N8 N9 3.0 1.2 4.0 2.0 0.2 0.3 0.5 0.8 1.2 2.0 0.1 0.1 0.2 0.3 0.5 0.8 TOL TOL 0.2 0.4 0.8 1.6 3.2 6.3 12.5 25 50 Ra, µm ANGULAR DIMENSIONS: 1 ANGULAR DIMENSIONS: 1
REFERENCE DRAWING LIST
20
H-540/SC550/RV-560 SORBENT INJECTION SYSTEM
20
BF-600 & FGD-675
21
BAG FILTER & FLUE GAS DESULPHURIZER
DESIGN SPECIFICATIONS FOR BAG FILTER & FLUEGAS DESULPHURIZER
2320 21 FLUE GAS INLET
FLUE GAS EXIT
1922
TOP VIEW
ISOMETRIC VIEW
1400 Nm3/hr
GAS TEMPERATURE
150 degC
SOLIDS BULK DENSITY
100 TO 200 kg/m3
FILTER SIZE
2 MICRONS
FILTRATION EFFICIENCY
99.99% FOR TWO MICRON AND LARGER
SOLID CONCENTRATION
0.9 gm/m3
CONE ANGLE
70 DEG
NO. OF BAGS
28
BAG DIAMETER
160 mm
BAG LENGTH
2000 mm
1350 4" SORBENT INJECTION NOZZLE
INLET NOZZLE 8" SCH40 ANSI CLASS FLANGE
HOPPER CAPACITY
1349
FINE ASH EXIT
SIDE VIEW
FRONT VIEW
REVISIONS DATE
NORMAL DISCHARGE RATE
4 kg/hr
MAX. DISCHARGE RATE
8 kg/hr
TURN DOWN RATIO
5:1
BULK DENSITY OF SORBENT
600 TO 700 kg/m3
REFER EQUIPMENT SPECIFICATION SHEET FOR MORE DETAILS
NOTES: - THIS IS A PRELIMINARY DRAWING ISSUED FOR RFQ PURPOSE ONLY, NOT FOR CONSTRUCTION OR INSTALLATION. - EQUIPMENT SIZE, DIMENSION AND SHAPE ARE SUBJECT TO CHANGE BASED ON FINAL SITE CONDITIONS AND DESIGN.
REV.
DISCHARGE
THROUGH ROTARY AIRLOCK VALVE-VENTURY WITH COMPRESSED AIR LIME AUTOMIZATION
*ALL PLATFORMS AND STAIRCASES SHOULD HAVE HANDRAILS AS PER INDIAN STANDARDS. ASH HOPPER AND SEALED MECHANISM NOT SHOWN IN THE DRAWING ACCESS LADDERS MUST BE CONSIDERED FLUE GAS DUCT FLUSHING AND DRAIN POINTS NOT LESS THAN 2" MUST BE CONSIDERED BY-PASS DUCT MUST BE CONSIDERED-REFER P&ID
1380
FINE ASH DISCHARGE NOZZLE 6" SCH40 ANSI CLASS FLANGE
4809
C CHANNEL 100X10
INTEGRATED LIME REACTION CHAMBER, STORAGE HOPPER WITH BOTTOM CONICAL DISCHARGE 25 kg
TYPE
2238
C CHANNEL 100X10
6858
DESIGN SPECIFICATIONS FOR SORBENT INJECTION SYSTEM
1204
DISCHARGE NOZZLE 8" SCH40 ANSI CLASS FLANGE
2054
PIPE 1 1/4"
DRAWING TITLE
PROJECT NAME
DESCRIPTION
ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE SPECIFIED. DO NOT SCALE DRAWING.
BAG FILTER & FLUE GAS DE-SULPHURIZER CAD By: DATE:
PC
25-JUN-2021
CHD By: DATE:
GK
30-JUN-2021
APPD By: DATE:
AM
02-JUL-2021
PROJECT NO:
169
2 TPD ROTARY KILN GASIFICATION SYSTEM DRAWING NO:
169-D-GG-675-1000
REV NO:
0
VER NO:
0
SCALE :1:50
1500
GAS FLOW RATE
C
1244
DESCRIPTION
SHEET:1 OF 1
PROJECTION
MACHINING TOLERANCE FOR LINEAR GENERAL TOLERANCE FOR LINEAR SURFACE FINISH SYMBOLS DIMENSIONS, IS-2102(MEDIUM) DIMENSIONS, IS-2102(COARSE) ⁓ 30 120 400 1000 2000 OVER 0.5 3 30 120 400 1000 2000 ROUGHNESS 6 OVER 0.5 3 6 SYMBOL 30 120 400 1000 2000 4000 UPTO 3 6 30 120 400 1000 2000 4000 UPTO 3 6 N1 N2 N3 N4 N5 N6 N7 N8 N9 3.0 1.2 4.0 2.0 0.2 0.3 0.5 0.8 1.2 2.0 0.1 0.1 0.2 0.3 0.5 0.8 TOL TOL 0.2 0.4 0.8 1.6 3.2 6.3 12.5 25 50 Ra, µm ANGULAR DIMENSIONS: 1 ANGULAR DIMENSIONS: 1
COMPONENT TAG NUMBER NO.
REFERENCE DRAWING LIST DRAWING NO. DRAWING TITLE 169-D-GG-000-1001 LAYOUT 169-D-GG-600-2000 FLUEGAS CLEANUP COMPONENTS
9. REFERENCES This section contains the reference information for the equipment specifications section. Table 5: Specifications for Syngas Analyzer – (AI-680)
The primary purpose of the Gas Analyzer is to measure the composition of Syngas. The analyzer is placed at the exit of gasifier. Syngas analyzer package should be a combination of sampling system and analyzer. The specification of syngas analyzer is as follows: Design Parameter Type Syngas Temperature at sampling system inlet Measuring Range
Value Online Continuous monitoring 100-150 0C CO
0 - 50 %
v/v
H2
0 - 50 %
v/v
CH4
0 - 20 %
v/v
O2
0 - 25%
v/v
CO2
0 - 25 %
v/v
Particulates in Syngas
2 to 5 g/m3
Accessories
1. Integrated sampling system to be included 2. Provision for data feedback to PLC Slightly negative, -5 mm WC 415V, 3 Phase, 50 Hz 230V, 1 Phase, 50 Hz
Syngas Pressure Power Supply
Notes
Suction pump must be considered
Documents to be supplied: 1. 2. 3. 4.
General arrangement drawings Equipment specification Operating instructions Catalogues or cut sheets for bought out items
Page 24 of 32 Appendix 1 - 2TPD 190821
Table 6: Specifications Flue Gas Analyzer (AI-710)
The primary purpose of the flue gas analyzer is to measure the composition of flue gas. The analyzer is placed at the exit of ID fan. Flue gas analyzer package should be a combination of sampling system and analyzer. The design requirement for the flue gas analyzer is as follows: Design Parameter
Value
Notes
Type
Online Continuous monitoring
Flue gas Temperature at Sampling system inlet Measuring Range
~ 150 0C NOx
0 - 2000 ppm
v/v
SOx
0 - 2000 ppm
v/v
CO
0 - 9999 ppm
v/v
CO2
0 - 20%
v/v
0 - 25 %
v/v
O2 3
Particulates in Syngas
0 to 1 mg/m
Accessories
1. Integrated sampling system to be included 2. Provision for data feedback to PLC 100 mm WC
Syngas Pressure Power Supply
Suction pump must be considered
415V, 3 Phase, 50 Hz 230V, 1 Phase, 50 Hz
Documents to be supplied: 1. 2. 3. 4.
General arrangement drawings Equipment specification Operating instructions Catalogues or cut sheets for bought out items
Table 7: List of Instruments Table 8: List of Control Valves Table 9: List of Manual Valves
Page 25 of 32 Appendix 1 - 2TPD 190821
Table 7: List of Instruments
Item
Tag
Description
Working Medium
Signal Type
Water
N
1
FE-300
Flow Measuring Orifice for Process Water Flow to RX300
2
FT-300
Flow Transmitter for Process Water Flow to RX-300
-
4-20mA
3
PT-307A
Pressure Transmitter for Gasifier RX-300 Inlet Hood
Syngas
4-20mA
4
PT-307B
Pressure Transmitter for Gasifier RX-300 Outlet Hood
Syngas
4-20mA
5
FE-330
Flow Measuring Orifice for Process Air Flow to RX-300
6
FT-330
Flow Transmitter for Process Air Flow to RX-300
7
FE-360
Flow Measuring Orifice for oxygen Flow to RX-300
8
FT-360
Flow Transmitter for Oxygen to RX-300
9
PG-330
Pressure Gauge for Process Air to RX-300
10
TE-311
Temperature Control Element at RX-300 Zone-1
11
TI-311
Temperature Indicator at RX-300 Zone-1
12
TE-314
Temperature Control Element at RX-300 Zone-4 Temperature Indicator at RX-300 Zone-4
Range, Min
Range, Max
Range, Unit
Thermo well
Probe length
Line Size
MOC
Metal Tube Rotameter
0
20
lph
-
-
1/4"
SS-304
Flow Transmitter
0
20
lph
-
-
-
-25
25
mmWC
-
-25
25
mmWC
-
Type
Piezo resistive Sensor Piezo resistive Sensor
-
-
-
-
-
-
1
-
-
YES
-
SS-310
1/2" BSP
0.1
-
-
YES
-
SS-310
1/2" BSP
0.1
-
-
YES
SS-304
3" ANSI 150 Flange
-
-
-
-
-
0.1
-
-
YES
CS-Zn Coated
N
Oxygen
N
-
4-20mA
Air
N
Diaphragm Gauge
0
250
Syngas
N
K Type thermocouple
0
1500
0
-
-
-
-
-
YES
10 feet
1/2"
SS-310
1/2" BSP
N
Nm3/hr
Casing
4-20mA
4-20mA
250
Dial Size
-
-
0
Accuracy (% Span)
Air
Syngas
Orifice Plate
Process Connection 1/4" ANSI 150 Flange
DP Transmitter Orifice Plate
0
30
Nm3/hr
DP Transmitter mmWC C
3"
-
-
-
-
-
-
1/2"
SS-304
1/2" ANSI 150 Flange
-
-
-
-
-
-
-
-
0.1
-
-
YES
-
3"
SS-304
1/2" BSP
-
-
-
-
1/2"
SS-310
1/2" BSP
-
-
-
-
CS-Zn Coated
0
1500
0
1500
0
-
-
-
-
-
0.1
-
C
YES
1 feet
1/2"
SS-304
1/2" BSP
-
-
bar
-
-
-
SS-304
1/2" BSP
0.1
YES
1 feet
1/2"
SS-304
1/2" BSP
2
-
4-20mA
0
1500
0
Air
N
Temperature Gauge
0
100
0
Oxygen
N
Diaphragm Gauge
0
2
Oxygen
N
Temperature Gauge
0
100
0.1
-
-
YES
-
-
-
-
-
YES
CS-Zn Coated
-
-
-
-
-
-
-
-
-
-
-
13
TI-314
14
TG-330
15
PG-360
16
TG-360
17
PG-382
Upstream Pressure Gauge for PCV-382
LPG
18
PG-383
Downstream Pressure Gauge for PCV-382
LPG
19
PSL-384
Low Pressure Switch for LPG to BRN-310
LPG
24VDC
Pressure Switch
20
PSH-384
High Pressure Switch for LPG to BRN-310
LPG
24VDC
Pressure Switch
21
LG-720
Level gauge for TK-700
Water
Gauge Glass
-
-
-
-
-
-
-
-
-
-
-
-
-
22
PG-705A
Pressure Gauge at the discharge of P-705A
Water
N
Bourdon Gauge
0
10
Bar
-
-
3/4"
SS-304
1/2" BSP
-
4"
-
-
-
23
PG-705B
Pressure Gauge at the discharge of P-705B
Water
N
Bourdon Gauge
0
10
Bar
-
-
3/4"
SS-304
1/2" BSP
-
4"
-
-
-
24
PSL-705
Pressure switch at the discharge of P-705A/B
Water
N
Low pressure switch
0
10
Bar
-
-
1"
-
1/2" BSP
-
-
-
-
-
25
TE-500
Temperature Control Element for CC-570
Syngas
N
K Type thermocouple
0
1500
0
YES
3 feet
SS-304
1/2" BSP
-
-
-
-
-
26
TI-500
Temperature Indicator Controller for CC-570
-
4-20mA
Transmitter
0
1500
0
-
-
-
-
-
-
-
YES
CS-Zn Coated
27 28
LG-510 PG-520A
Level gauge for TK-510 Pressure Gauge at the discharge of P-520A
Water Water
N N
Gauge Glass Pressure Gauge
29
PG-520B
Pressure Gauge at the discharge of P-520B
Water
N
Pressure Gauge
30
PSL-920
Pressure switch at the discharge of P-520A/B
Water
N
Pressure Switch
31
PG-530
N
Bourdon Gauge
0
5
-
-
2"
SS-304
1/2" BSP
-
-
-
-
TE-530
Pressure Gauge for Steam at Steam Drum Header Temperature Control Element for Steam Temperature at Steam Drum Header
Steam
32
Steam
N
K Type thermocouple
0
300
0
YES
1 feet
2"
SS-304
1/2" BSP
-
-
-
33
TI-530
Temperature Indicator for Steam at Steam Drum Header
-
4-20mA
Transmitter
0
300
0
C
-
-
-
-
-
-
-
-
YES
34
PT-530
Pressure Transmitter for Steam at Steam Drum Header
Steam
4-20mA
Piezo resistive Sensor
0
5
Bar
-
-
2"
SS-304
1/2" BSP
0.1
-
-
YES
35
FE-530
Flow Measuring Orifice for Steam Flow from Steam Drum
Steam
N
Orifice Plate
0
500
Kg/hr
-
-
2"
SS-304
1" ANSI 150 Flange
-
-
-
-
-
YES
CS-Zn Coated
Temperature Control Element for Process Air to RX-300 Pressure Transmitter for Process air to RX-300 Temperature Control Element for Process Air to RX-300
C
CS-Zn Coated -
10 feet
K Type thermocouple Temperature Transmitter
CS-Zn Coated CS-Zn Coated CS-Zn Coated
-
0
C
Mounting Bracket
YES
Temperature Transmitter
C
Local Display
0
C
Preessure Gauge Preessure Gauge
36
FT-530
Flow Transmitter for Steam Flow from Steam Drum
37 38 39 40
LSL-530 LSLL-530 LSH-530 PG-581
Level Sensor for Steam Drum Low Level Level Sensor for Steam Drum Low Low Level Level Sensor for Steam Drum High Level Upstream Pressure Gauge for PCV-580
-
4-20mA
Water Water Water LPG
NO-Contact NO-Contact NO-Contact N
DP Transmitter
41
PG-582
Downstream Pressure Gauge for PCV-580
LPG
N
Pressure Gauge
42
PSL-580
Low Pressure Switch for LPG to BRN-580
LPG
N/O Contact
Pressure Switch
43
PSH-580
High Pressure Switch for LPG to BRN-580
LPG
N/C Contact
Pressure Switch
Mobrey Level Switch Mobrey Level Switch Mobrey Level Switch Pressure Gauge
Burner - Manufacturers's Recommendation
C C
-
Boiler - Manufacturers's Recommendation
0
500
Bar C
Kg/hr
-
-
-
-
-
Boiler - Manufacturers's Recommendation
Burner - Manufacturers's Recommendation
0.1
-
-
CS-Zn Coated CS-Zn Coated
Table 7: List of Instruments
Item
Tag
Description
Working Medium
Signal Type
Type
44
FE-570
Flow Measuring Orifice for Air flow to CC-570
Air
N
45
FI-570
Flow Measuring Orifice indicator for Air flow to CC-570
Air
4-20mA
46
TG-570
Temperature Gauge on Combustion Air line
Temperature Gauge
47
PG-570
Pressure Gauge on Combustion Air line
Diaphragm Gauge
48
TE-550
Temperature Control Element at B-500 Outlet
Flue Gas
N
Orifice Plate
Range, Min
Range, Max
Range, Unit
Thermo well
Probe length
Line Size
MOC
0
900
Nm3/hr
-
-
4"
-
-
-
8"
-
-
-
-
YES
6"
DP Transmitter
K Type thermocouple
100 0C 500 mmWC 0
250
0
0
C
Process Connection 6" ANSI 150 Flange
Accuracy (% Span)
Dial Size
Casing
Local Display
Mounting Bracket
-
-
-
-
-
-
0.1
-
-
YES
-
-
-
-
-
-
-
CS-Zn Coated -
-
-
-
-
-
-
-
-
8"
-
1/2" BSP
-
-
-
-
-
-
Transmitter
0
250
C
-
-
-
-
-
0.1
-
-
No
Glass tube
-
-
-
-
-
-
-
-
-
-
-
-
CS-Zn Coated -
4-20mA
Analyzer
0
50
%
-
-
-
-
-
-
-
-
-
-
Syngas
4-20mA
Analyzer
0
50
%
-
-
-
-
-
-
-
-
-
-
Gas Analyser(AI-680)
Syngas
4-20mA
Analyzer
0
20
%
-
-
-
-
-
-
-
-
-
-
AI-680-CO2
Gas Analyser(AI-680)
Syngas
4-20mA
Analyzer
0
25
%
-
-
-
-
-
-
-
-
-
-
55
AI-680-O2
Gas Analyser(AI-680)
Syngas
4-20mA
Analyzer
0
25
%
-
-
-
-
-
-
-
-
-
56
TI-315
Combustion chamber temperature element
Flue Gas
N
K Type thermocouple
0
1500
0
-
-
-
-
-
0.1
-
-
No
57
TE-315
Combustion chamber temperature indicator
Flue Gas
4-20mA
Transmitter
0
1500
0
C
YES
10"
-
-
1/2" BSP
-
-
-
CS-Zn Coated -
58
AI-710-NOx
Flue Gas monitor(AI-710)
Flue gas
4-20mA
Analyzer
0
2000
ppm
-
-
-
-
-
-
-
-
-
-
59
AI-710-SOx
Flue Gas monitor(AI-710)
Flue gas
4-20mA
Analyzer
0
2000
ppm
-
-
-
-
-
-
-
-
-
-
60
AI-710-CO
Flue Gas monitor(AI-710)
Flue gas
4-20mA
Analyzer
0
9999
ppm
-
-
-
-
-
-
-
-
-
-
61
AI-710-CO2
Flue Gas monitor(AI-710)
Flue gas
4-20mA
Analyzer
0
20
%
-
-
-
-
-
-
-
-
-
-
62
AI-710-O2
Flue Gas monitor(AI-710)
Flue gas
4-20mA
Analyzer
0
25
%
-
-
-
-
-
-
-
-
-
-
63
LSL-540
Level Sensor for H-540 Low Level
Lime
4-20mA
Level Switch
-
-
-
-
-
-
-
1/2" BSP
-
-
-
-
-
64
PG-600A
Pressure Gauge for Compressed Air Header to FGD-675
Compr Air
N
Bourdon gauge
0
7
Bar
-
-
1"
SS-304
1/2" BSP
4"
-
-
-
65 66
TE-600 TI-600
Temperature Element at FGD-675 Intlet Temperature Indicator at FGD-675 Intlet
Flue Gas
N 4-20mA
0 0
250 250
C 0 C
YES -
6" -
8" -
SS-304 -
1/2" BSP -
0.1
-
-
No
67
PT-600
Pressure Transmitter for CF-620 Outlet Pressure
Flue gas
4-20mA
-1250
100
mmWC
-
-
8"
SS-304
1/2" BSP
0.1
-
-
No
CS-Zn Coated
69
PT-660
Pressure Transmitter for CF-620Outlet Pressure
Flue gas
4-20mA
0
200
mmWC
-
-
8"
SS-304
1/2" BSP
-
-
-
-
71
PDIT-600
Differential Pressure Across FGD-675
Flue gas
4-20mA
0
300
mmWC
YES
-
8"
SS-304
1/2" BSP
0.1
-
-
YES
72
TE-660
Temperature Control Element at CF-620 Outlet
Flue gas
N
RTD Transmitter Piezo resistive sensor Piezo resistive sensor Piezo resistive sensor RTD
73
TI-660
Temperature Indicator at CF-620 Outlet
-
4-20mA
74
FE-660
Flow Measuring Orifice at CF-620 exit
75
FT-660
Flow Measuring Orifice transmitter CF-620 exit
76
TMR-600
Timer for CF-620 Purging
Compr Air
NO-Contact
77
PDI-620
Differential Pressure Across CF-620
Flue gas
N
78
PG-900
Pressure Gauge for Compressed Air Header
Air
79
PT-900
Pressure Transmitter for Compressed Air Header
Air
49
TI-550
Temperature Indicator Element at B-500 Outlet
50
LG-695
Level gauge for TK-695
-
51
AI-680-CO
Gas Analyser(AI-680)
Syngas
52
AI-680-H2
Gas Analyser(AI-680)
53
AI-680-CH4
54
4-20mA
Water
Flue gas
N 4-20mA
C
0
0
250
0
YES
3 feet
8"
SS-304
1/2" BSP
-
-
-
-
Transmitter
0
250
0
C
-
-
-
-
-
0.1
-
-
No
Averaging Pitot Tube
0
1100
Nm3/hr
-
-
8"
SS-304
1/2" BSP
-
-
-
DP Transmitter
0
1100
Nm3/hr
-
-
-
-
0.1
-
-
YES
-
-
-
-
-
-
YES
C
Timer Panel
-
-
-
-
-
1"
-
-
Bourdon Gauge
0
300
mmWC
YES
-
8"
SS-304
1/2" BSP
N
Bourdon Gauge
0
7
Bar
-
-
2"
SS-304
1/2" BSP
-
4"
-
-
4-20mA
Piezo resistive Sensor
0
7
Bar
-
-
1"
SS-304
1/2" BSP
-
-
-
YES
0.1
-
CS-Zn Coated CS-Zn Coated CS-Zn Coated CS-Zn Coated CS-Zn Coated
Table 8: List of Control Valves
Item
Tag
1
FCV-300
2
FCV-320 Flow control valve for BL-320
3 4
Description Flow Control Valve for Process Water to RX-300
Flow Control Valve for Process Air to RXFCV-330 300 Inlet Hood Flow Control Valve for Oxygen to RX-300 FCV-360 Inlet Hood Shut Off Valve for Air to BRN-310
Working Medium Water Air Air Oxygen Air
Type Globe Valve Butterfly Valve Butterfly Valve Butterfly Valve Butterfly Valve
Feedback
Positioner Input
Operating Temp
Operating Press.
Flow Rate, Min
Flow Rate, Max
Unit
Line Size
Air to Open
NO
4-20 mA
25 deg C
5 Bar
0
20
lph
1/4"
Pneumatic
Air to Open
NO
4-20 mA
25 deg C
250 mmWC
0
250
Nm3/hr
3"
Pneumatic
Air to Open
NO
4-20 mA
25 deg C
250 mmWC
0
250
Nm3/hr
3"
Pneumatic
Air to Open
NO
4-20 mA
25 deg C
250 mmWC
0
30
Nm3/hr
1/2"
Air to Open
Open / Close
25 deg C
250 mmWC
A 216 WCC
Class IV
3"
Actuator type
Action
Pneumatic
5
XV-320
6
XV-385A Shut Off Valve for LPG Line to BRN-310
LPG
Ball valve
Pneumatic
7
XV-385B Shut Off Valve for LPG Line to BRN-310
LPG
Ball valve
Pneumatic
8
FCV-525 Flow control valve for BL-585
Air
Butterfly Valve Globe Valve Butterfly Valve
Pneumatic
Pneumatic
Air to Open
NO
4-20 mA
25 deg C
Pneumatic
Air to Open
NO
4-20 mA
Pneumatic
Air to Open
NO
4-20 mA
9 10
FCV-570 Flow Control Valve for Air to CC-570
11
XV-583A Shut Off Valve for LPG Line to BRN-580
LPG
Ball valve
Pneumatic
12
XV-583B Shut Off Valve for LPG Line to BRN-580
LPG
Ball valve
Pneumatic
13
XV-530
Water
Ball valve
Pneumatic
Air to Open
Pneumatic
Air to Open
Pneumatic
Air to Open
Pneumatic
Air to Open
Pneumatic
Air to Open
Shutoff Valve for Water to Steam Drum Shut Off Valve for Process Air to BRN-580
Air
14
XV-525
15
XV-601A Shut Off Valve at Inlet of FGD-675
Flue gas
16
XV-601B Shut Off Valve at Outlet of CF-620
Flue gas
17
XV-601C Bypass Shut Off Valve for CF-620
Flue gas
18
SV-600
Solenoid Valve for FGD-675 Purging
Air
Air
Butterfly Valve Butterfly Valve Butterfly Valve Butterfly Valve
Lug End
1/4" NPT 3" ANSI 150 Flange 3" ANSI 150 Flange 1/2" ANSI 150 Flange Lug End
A 216 WCC A 216 WCC A 216 WCC A 216 WCC A 216 WCC
Class IV Class IV Class IV Class IV Class IV
Burner - Manufacturers's Recommendation
Flow Control Valve for Steam from Steam FCV-530 Drum
Steam
24 V DC
Process Leakage Body MOC Connection Class
250 mmWC
0
250
Nm3/hr
3"
300 deg C
5 bar
0
25 deg C
500 mmWC
0
500
kg/hr
2"
900
Nm3/hr
6"
3" ANSI 150 Flange 1"ANSI 150 Flange 6" ANSI 150 Flange
A 216 WCC A 216 WCC A 216 WCC
Class IV Class IV Class IV
Burner - Manufacturers's Recommendation Open / Close Open / Close Open / Close Open / Close Open / Close
24 V DC
25 deg C
10 Bar
-
-
-
3/4"
Lug End
24 V DC
25 deg C
250 mmWC
-
-
-
3"
Lug End
24 V DC
200 deg C
-750 mmWC
-
-
-
8"
Lug End
24 V DC
200 deg C
-750 mmWC
-
-
-
8"
Lug End
24 V DC
200 deg C
-750 mmWC
-
-
-
8"
Lug End
Flue Gas Desulphuriser - Manufacturers's Recommendation
A 216 WCC A 216 WCC A 216 WCC A 216 WCC A 216 WCC
Class IV Class IV Class IV Class IV Class IV
Table 9: List of Manual Valves
Item
Tag
Description
Working fluid Syngas Syngas Water
Line Size 1/2" 1/2" 1/4"
Ball Valve Ball Valve Ball Valve
Operating Temp degC 200 200 77
Operating Pressure -2 mmwc -2 mmwc 3 bar
Type
A 105 A 105 A 105
Ball/Globe/ Gate/ Butterfly MOC SS 304 SS 304 SS 304
Seat MOC PTFE PTFE PTFE
Leakage Class Class IV Class IV Class IV
End connection BSP BSP BSP
2 Piece Design 2 Piece Design 2 Piece Design
3 bar 3 bar
A 105 A 105
SS 304 SS 304
PTFE PTFE
Class IV Class IV
BSP BSP
2 Piece Design 2 Piece Design
Body MOC
Remarks
1 2 3
MV-307A MV-307B MV-300A
Isolation Valve for PT-307A Isolation Valve for PT-307B Upstream Isolation Valve for FCV-300
4 5
MV-300B MV-300C
Downstream Isolation for FCV-300 Bypass Isolation for FCV-300
Water Water
1/4" 1/4"
Ball Valve Globe Valve
77 30
6
MV-300D
Water Isolation Valve
Water
1/4"
Ball Valve
77
3 bar
A 105
SS 304
PTFE
Class IV
BSP
2 Piece Design
7 8
MV-330D MV-330
Isolation Valve for PG-330 Process Air Isolation Valve
Air Air
3" 3"
Ball Valve Butterfly Valve
30 30
250 mmWC 250 mmWC
A 105 ASTM A182
SS 304 SS 304
PTFE PTFE
Class IV Class IV
BSP Wafer type
2 Piece Design -
9
NRV-330
NRV for Process air line
10 11
NRV-360 MV-330A
NRV for Oxygen line Upstream Isolation Valve FCV-330
Air
3"
Non return valve
30
250 mmWC
A 105
SS 304
PTFE
Class IV
Sandwich type
-
Oxygen Air
1/2" 3"
Non return valve Butterfly Valve
30 30
6 bar 250 mmWC
A 105 A 105
SS 304 SS 304
PTFE PTFE
Class IV Class IV
Sandwich type Wafer type
-
12 13
MV-330B MV-330C
Downstream Isolation Valve for FCV-330 Bypass Isolation for FCV-330
Air Air
3" 3"
Butterfly Valve Butterfly Valve
30 30
250 mmWC 250 mmWC
A 105 A 105
SS 304 SS 304
PTFE PTFE
Class IV Class IV
Wafer type Wafer type
-
14
MV-360
15 16
MV-360A MV-360B
Oxygen Isolation Valve
Oxygen
1/2"
Ball Valve
30
6 bar
ASTM A182
SS 304
PTFE
Class IV
BSP
2 Piece Design
Up stream Isolation for FCV-360 Downstream Isolation for FCV-360
Oxygen Oxygen
1/2" 1/2"
Ball Valve Ball Valve
30 30
6 bar 6 bar
ASTM A182 ASTM A182
SS 304 SS 304
PTFE PTFE
Class IV Class IV
BSP BSP
2 Piece Design 2 Piece Design
17 18 19
MV-360C
Bypass Isolation for FCV-360
Oxygen
1/2"
Globe Valve
30
6 bar
ASTM A182
SS 304
PTFE
Class IV
BSP
3 Piece Design
MV-360D MV-382
PG-360 Isolation valve Isolation Valve for PG-382
Oxygen LPG
1/2" 1/2"
Ball Valve
30
6 bar
ASTM A182
SS 304
PTFE
Class IV
BSP
2 Piece Design
20 21 22 23 24 25 26 27 28 29 30 31 32 33
MV-383 MV-381 PCV-382 NRV-300 FV-700 MV-700A MV-700 MV-700B MV-705A1 MV-705A2 MV-705A NRV-705A MV-706A MV-706C
Isolation Valve for PG-383 LPG Isolation Valve PressureRegulator for LPG to Gasifier RX-300 NRV for Process water line Float valve for TK-700 Isolation valve for TK-700 from Site water Isolation valve from TK-700 Drain for TK-700 P-705A Suction Valve Discharge Isolation Valve for outlet of P-705A Isolation Valve for PG-705A NRV for P-705A Process water header isolation PSL-705 isolation
LPG LPG LPG Water Water Water Water Water Water Water Water Water Water Water
1/2" 1/2" 1/2" 1/4" 2" 2" 1" 1/2" 1" 3/4" 1/2" 3/4" 1/4" 1/2"
Class Class Class Class Class Class Class Class Class Class Class
BSP BSP BSP BSP BSP BSP BSP BSP BSP BSP BSP
34
PCV-700
Pressure Control Valve for TK-700
Water
1/2"
35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54
MV-500A MV-580 MV-581 MV-582 MV-500B MV-570 MV-570A MV-570 B MV-570 C NRV-530 MV-530 MV-530A MV-530B MV-530C MV-530D ST-530 MV-532A MV-532B MV-532C MV-695A
Blow down valve for B-500 Isolation Valve from LPG Isolation Valve for PG-511 Isolation Valve for PG-512 Residue discharge isolation valve for B-500 Combustion Air Isolation Valve PG-570 Isolation Valve Isolation valve for Combustion air in CC-570 Isolation valve for Combustion air in CC-570 NRV for SD-530 Isolation Valve for PT-530 & PG-530 Upstream Isolation Valve for FCV-530 Down stream Isolation Valve for FCV-530 Bypass Isolation Valve for FCV-530 Steam outlet of SD-530 Steam trap for SD-530 Isolation Valve for LSH-530 Isolation Valve for LSL-530 Isolation Valve for LSLL-530 Isolation Valve Syngas to TK-695
Water LPG LPG LPG Ash Air Air Air Air Water Steam Steam Steam Steam Steam Steam Steam Steam Steam Water
3/4" 1/2" 1/2" 1/2" 1" 6" 1/2" 4" 1/2" 1" 1/2" 2" 2" 2" 2" 1/2" 1/2" 1/2" 1/2" 1/2"
Burner - Manufacturers's Recommendation
Non return valve Ball Valve Ball Valve Ball Valve Ball Valve Ball Valve Ball Valve Ball Valve Non return valve Ball Valve Ball Valve Back Pressure Regulating Valve Globe Valve
30 30 30 30 30 30 30 30 30 30 30
6 3 3 3 3 6 6 6 6 6 6
bar bar bar bar bar bar bar bar bar bar bar
A A A A A A A A A A A
105 105 105 105 105 105 105 105 105 105 105
304 304 304 304 304 304 304 SS 304 SS 304
PTFE PTFE PTFE PTFE PTFE PTFE PTFE PTFE PTFE PTFE PTFE
SS SS SS SS SS SS SS
IV IV IV IV IV IV IV IV IV IV IV
Piece Design Piece Design Piece Design Piece Design Piece Design Piece Design Piece Design 2 Piece Design 2 Piece Design 2 2 2 2 2 2 2
30
-
-
-
-
-
BSP
-
100
5 bar
-
Boiler Grade
-
Class IV
BSP
-
Lug type Wafer type BSP Wafer type BSP Sandwich type BSP ANSI flange ANSI flange ANSI flange ANSI flange BSP BSP BSP BSP BSP
2 Piece Design 2 Piece Design 2 Piece Design 2 Piece Design
Burner - Manufacturers's Recommendation Ball Valve Butterfly Valve Ball Valve Butterfly Valve Ball Valve Non return valve Globe Valve Globe Valve Globe Valve Globe Valve Globe Valve Threaded Globe Valve Globe Valve Globe Valve Ball Valve
150 30 30 30 30 30 200 200 200 200 200 300 200 200 200 1000
-10 mmWC 500 mmWC 500 mmWC 500 mmWC 500 mmWC 6 bar 5 bar 5 bar 5 bar 5 bar 5 bar 5 bar 5 bar 5 bar 5 bar -2 mmwc
A 105 A 105 A 105 A 105 A 105 A 105 A 105 A 105 A 105 A 105 A 105 AISI 420 A 105 A 105 A 105 A 105
SS304 SS 304 SS 304 SS 304 SS 304 SS 304 SS 304 SS 304 SS 304 SS 304 SS 304 SS 304 SS 304 SS 304 SS 304
PTFE PTFE PTFE PTFE PTFE PTFE PTFE PTFE PTFE PTFE PTFE PTFE PTFE PTFE PTFE
Class Class Class Class Class Class Class Class Class Class Class Class Class Class Class Class
IV IV IV IV IV VI VI VI VI VI VI VI VI VI VI VI
Table 9: List of Manual Valves
Item
Tag
Description Isolation valve for Process water to TK-695 Isolation valve for Drain to TK-695 Pressure Regulator for LPG to BRN-580
Working fluid Water Water LPG
Line Size 1/4" 1/2" 1/2"
Ball Valve Ball Valve Regulator
Operating Temp degC 30 30 30
Operating Pressure 6 bar 1 bar 2 bar
2" 2"
Safety Valve Safety Valve
150 150
4.7 bar 4.9 bar
Type
Body MOC
Seat MOC PTFE PTFE -
Leakage Class Class VI Class VI -
End connection BSP BSP BSP
2 Piece Design 2 Piece Design -
ANSI flange ANSI flange
-
Remarks
55 56 57
MV-695B MV-695C PCV-580
58 59
PSV-530A Pressure Safety Valve for Stream Drum PSV-530B Pressure Safety Valve for Stream Drum
Steam Steam
60
MV-705B1 P-705B Suction Isolation Valve
Water
1"
Ball Valve
30
6 bar
A 105
SS 304
PTFE
Class IV
BSP
2 Piece Design
61 62
MV-705B2 Discharge Isolation Valve for outlet of P-705B NRV-705B NRV for P-705B
Water Water
3/4" 3/4"
Ball Valve Non return valve
30 30
6 bar 6 bar
A 105 A 105
SS 304 -
PTFE PTFE
Class IV Class IV
BSP BSP
2 Piece Design -
63
MV-705B
Isolation Valve for PG-705B
Water
1/2"
Ball Valve
30
6 bar
A 105
SS 304
PTFE
Class IV
BSP
2 Piece Design
64 65
MV-706B MV-510
Process water isolation for RX-300 Boiler feed water isolation
Water Water
1/4" 1"
Ball Valve Ball Valve
30 30
6 bar 1 bar
A 105 A 105
SS 304 SS 304
PTFE PTFE
Class IV Class IV
BSP BSP
2 Piece Design 2 Piece Design
66 67
MV-510A FV-510
Process water isolation for TK-510 Float valve for TK-510
Water Water
1" 1"
Ball Valve Float Valve
30 30
1 bar 1 bar
A 105 A 105
SS 304 -
PTFE -
Class IV Class IV
BSP -
2 Piece Design -
68
MV-510B
Drain for TK-510
Water
2"
Ball Valve
30
1 bar
A 105
SS 304
PTFE
Class IV
BSP
2 Piece Design
69 70
MV-521A P-520A Suction Valve NRV-520A NRV for P-520A
Water Water
3/4" 3/4"
Ball Valve Non return valve
30 30
6 bar 6 bar
A 105 A 105
SS 304 -
PTFE -
Class IV Class IV
BSP BSP
2 Piece Design -
71
MV-520A
Water
1/2"
Ball Valve
30
6 bar
A 105
SS 304
PTFE
Class IV
BSP
2 Piece Design
72 73
MV-521C P-520B Suction Valve NRV-520B NRV for P-520B
Water Water
1" 3/4"
Ball Valve Non return valve
30 30
1 bar 6 bar
A 105 A 105
SS 304 -
PTFE -
Class IV Class IV
BSP BSP
2 Piece Design -
74 75 76 77 78 79 80 81 82 83 84 85 86 87 88
MV-521D MV-520B MV-522B MV-660B MV-600A MV-600B MV-620C MV-661A MV-900A MV-900B MV-900C MV-901A MV-901B MV-901C MV-901D
Water Water Water Air Fluegas Fluegas Ash Fluegas Air Air Air Air Air Air Air
3/4" 1/2" 3/4" 1/2" 1/2" 1/2" 6" 1/2" 1" 1/2" 1/2" 1" 1" 1" 1"
Ball Valve Ball Valve Ball Valve Ball Valve Ball Valve Ball Valve Ball Valve Ball Valve Ball Valve Ball Valve Ball Valve Ball Valve Ball Valve Ball Valve Ball Valve
30 30 30 30 200 200 150 200 30 30 30 30 30 30 30
6 bar 6 bar 6 bar 7 bar -750 mmWC -750 mmWC -750 mmWC 100 mmWC 7 bar 7 bar 7 bar 7 bar 7 bar 7 bar 7 bar
A A A A A A A A A A A A A A A
SS SS SS SS SS SS SS SS SS SS SS SS SS SS SS
PTFE PTFE PTFE PTFE PTFE PTFE PTFE PTFE PTFE PTFE PTFE PTFE PTFE PTFE PTFE
Class Class Class Class Class Class Class Class Class Class Class Class Class Class Class
BSP BSP BSP BSP BSP BSP BSP BSP BSP BSP BSP BSP BSP BSP BSP
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Isolation Valve for PG-520A
Discharge Isolation Valve for outlet of P-520B Isolation Valve for PG-520B Boiler Water Isolation for HRGS Isolation valve for PG-600 Upstream Isolation Valve for PDIT-600 Downstream Isolation Valve for PDIT-600 Residue discharge isolation valve for CF-620 Isolation valve for PT-660 Isolation valve for C-900 discharge Isolation Valve for PT-900 Isolation Valve for PG-900 Service Air Header Isolation Gasifier Instrument Air Header Isolation HRSG Instrument Air Header Isolation Gas Cleanup Instrument Air Header Isolation
A 105 A 105 -
Ball/Globe/ Gate/ Butterfly MOC SS 304 SS 304 Boiler Grade
105 105 105 105 105 105 105 105 105 105 105 105 105 105 105
304 304 304 304 304 304 304 304 304 304 304 304 304 304 304
IV IV IV IV IV IV IV IV IV IV IV IV IV IV IV
Piece Piece Piece Piece Piece Piece Piece Piece Piece Piece Piece Piece Piece Piece Piece
Design Design Design Design Design Design Design Design Design Design Design Design Design Design Design
Table 10: Electrical Cable Requirement and Specifications
Two categories of cables shall be included in the scope of supply. Power cables for motors and signal cables for field instruments and valves. • • • • • • • •
All cables supplied shall be as per Indian Standards or equivalent All cable shall be of reputed make with CE or equivalent marking on it All cable shall be suitable for outdoor use All power cable shall be suitable for operating at 415V/3Ph/50Hz power supply All signal cables shall be suitable for 24VDC supply All cables for analog signals shall be shielded cables Insulations to follow Indian Standards All cable shall have the voltage ratings marked on the outer sheath
Reference: 1. Table 11: Motor Control Centre Specifications 2. Table 12: List of Motors 3. Table 7: List of Instruments Table 11: Motor Control Center (MCC) Specification
The design specification for the motor control center specification is as follows: Section
Objective
Scope
This section includes requirements for a Motor Control Center (MCC) and all required control devices and to be part of the MCC equipment.
Standards
Equipment shall be manufactured, designed and tested to the following standards: • Applicable Indian Standards • All components shall be CE marked • Enclosed Switchgear shall be rated for Internal Arcing Faults • MCCs shall be provided with documentation and labeling indicating equipment is rated for these applications
General Specification
• • • • • •
All the devices shall be sized for altitude of 100m Power: 415VAC, 50Hz, 3Ph+1N+GND Control Voltage 24VDC Cable entry: Rear Bottom Disconnect switches sized to system load. A lever handle operator must be provided A mechanical interlock shall prevent the operator from opening the unit door when the disconnect is in the ON position Page 26 of 32
Appendix 1 - 2TPD 190821
Section
Objective • • • •
Another mechanical interlock shall prevent the operator from placing the disconnect in the ON position while the unit door is open Pilot devices shall be rated IS Type Power status indicator lights shall be mounted on the enclosure door 230V outlet and RJ45 Ethernet connector mounted on the enclosure door
Motor Control Equipment
Electrical Ratings: • Variable Frequency AC drive controller unit shall be designed to operate from an input voltage of 415VAC ±10% • The AC drive controller unit shall operate from an input voltage frequency range of 50 ± 10% Hz • Protection: Motors and drives shall be protected by MPCBs (motor protection circuit board) • Control: • Pilot devices shall be industrial rated [22mm] [30mm] type control operators and used independently of the keypad display • Drives shall include network communication interface for data acquisition over Modbus TCP/IP • Each motor control shall be mounted on the enclosure door and include the following: o Local/Remote selector switch o Combo Start/Stop illuminated pushbutton o Motor Trip indicator (amber) o VFD’s keypad mounted on the panel
Control System
PLC: • Modular design with metal rack enclosure, power supply, controller CPU and user selectable I/O module • All I/O points shall be protected by fuses with burned fuse indicator • Interface relays • Separate Ethernet switches for remote I/O and remote access • Ethernet router with external antenna mounted on the enclosure with external range of 100m
DC Power Supply and Battery Backup
• • •
Individual power supplies for control signal, Digital I/O and Analog I/O Power supplies status indicator (blue) mounted on the door All control systems must have powered through the UPS system with external battery
Power Monitoring
•
Power Monitor with display mounted on the enclosure door
Page 27 of 32 Appendix 1 - 2TPD 190821
Section Enclosure and Terminals
Objective • •
• • • • •
•
Cabling
• •
• • •
Spare
The overall height of the MCC shall not exceed 2.1 meters Structures shall be totally enclosed, dead-front, free-standing assemblies Structure shall be capable of being bolted together to form a single assembly IP52 type enclosure Panel suitable to install inside a building The main horizontal bus shall be sized to system load extend the full length of the MCC Bus ratings shall be based on 65° C maximum temperature rise in a 40° C ambient Terminal blocks shall be the pull-apart type with a minimum rating of 250VAC for control and 600V for power. All current carrying parts shall be tin plated Terminals shall be accessible from inside the unit when the unit door is opened. Terminal blocks shall be DIN rail mounted with the stationary portion of the block secured to the unit bottom plate. All the low voltage cables shall be a minimum rating of 300VAC for control and 600V for power The Ethernet (Modbus TCP) communications network shall be configured in a star topology and connected to a central Ethernet switch unit located in the MCC The industrial Ethernet cable shall be 600V CE Category 6e Cable entry shall be provided from the top of the cabinet Cord grips shall be provided from the bottom of the cabinet for external cabling
Additional 10% space required for future modification if needed on: • Bus Bar • Din Rail • Sub Panel
Page 28 of 32 Appendix 1 - 2TPD 190821
Table 12: List of Motors Rated Power, HP
Rated Voltage, V
Rated Frequency, Hz
Rated Current, A
Control Method
10.00
415
50
12.99
Contactor
2.00
415
50
2.60
VFD
2.00
415
50
2.60
VFD
3.00
415
50
3.90
VFD
1.50
415
50
1.95
Contactor
1.50
415
50
1.95
VFD
Motor for Boiler Feed Water Pump
1.50
415
50
1.95
P-520B
Motor for Boiler Feed Water Pump
1.50
415
50
1.95
M-585
BL-585
Motor for Burner for CC-570
1.50
415
50
1.95
Contactor
10
M-590
BL-590
Motor for Combustion Chamber blower
4.00
415
50
5.20
Contactor
11
M-560
RV-560
Rotary Valve for SC550
0.25
415
50
0.32
Contactor
12
M-900
C-900
Motor for Air compressor
10.00
415
50
12.99
Contactor
13
M-705A
P-705A
Motor for Process Water Pump A
1.00
415
50
2.60
Contactor
14
M-705B
P-705B
Motor for Process Water Pump B
1.00
415
50
2.60
15
M-660
BL-660
Motor for ID Blower
15.00
415
50
19.48
VFD
16
M-550
SC-550
Motor for Vibro Feeder
0.25
415
50
0.32
VFD
Item
Tag
Equip. Tag No
1
M-010
SH-010
2
M-020
BC-020
3
M-070
SC-070
4
M-300
RX-300
5
M-320
BL-320
6
M-330
BL-330
7
M-520A
P-520A
8
M-520B
9
Description Motor for Shredder Motor for Waste transfer Conveyor Motor for Gasifier Screw feeder Motor for Gasifier Motor for Startup burner Blower Motor for Process Air Blower
Contactor Contactor
Contactor
Page 29 of 32 Appendix 1 - 2TPD 190821
Table 13: Control System Specifications
The control system for the 2 TPD Rotary Kiln Gasification System for High CV Syngas Production comprises of a control station within the facility, a bunch of field instruments, a programmable logic controller (PLC), interface between field instruments and PLC, a human machine interface (HMI) for communicating with the PLC and a set of hardware required for the network. This document provides basic specifications of the control system requirements for the project. The bidder shall provide basic programming of the PLC system during the installation of the pilot plant. This programming will include interlocks, control algorithms and any safety functions. Any costs associated with this shall be included in the cost of the control system. The details of this will be provided after the contract is awarded. Programmable Logic Controller (PLC) Specifications – PLC Model
Honeywell or equivalent
No of Analog Inputs
48
No of Analog Outputs
24
No of Digital Inputs
96
No of Digital Outputs
32
Communication Protocols
Modbus TCP/IP, Ethernet TCP/IP
Redundancy
Not required
Scan Time
<100 mS
Input/output Modules
To suit the selected controller
Power Supply Module
To suit the selected controller
IO Racks
To suit the selected controller
Human Machine Interface HMI Display Size
Min 15” Touch Screen
Processing Monitoring
Graphic Pages
Individual Tag Control
Faceplates
Data Input
Numeric/Slide Bar
Data Trends
-
Needed (1s/5s/1min/5min data point) Min 8 pens per trend set
History Data Capture
-
Needed Standard -1 min data points Other – 5 min/20 min Daily reports Event logging Alarms
Communication with PLC
Ethernet TCP/IP Page 30 of 32
Appendix 1 - 2TPD 190821
Table 14: Specifications of Pipes and Fittings Pipes and fittings required for the 2 TPD Rotary Kiln Gasification system is as follows: Description
Line Size, NB
Process Water line
8
Oxygen Line
15
Process Air Line
80
Start Up Burner Line
80
LPG line
15
Steam Line
50
Syngas Sample line
15
Process Water for Boiler
20
Combustion Air line for burner for combustion chamber LPG line for Combustion Chamber Combustion air line for syngas combustion
Material of Construction ASTM A 53 ERW Gr B or Equivalent ASTM A312 TP304 or Equivalent ASTM A106 ERW or Equivalent ASTM A106 ERW or Equivalent ASTM A106 Seamless or Equivalent ASTM A106 Seamless or Equivalent ASTM A312 TP304 or Equivalent ASTM A53 ERW Gr B or Equivalent
Type
Medium
Length, m
Quantity, Nos
Schedule 40
Water
30
5
Schedule 40
Oxygen
15
3
Schedule 10
Air
24
4
Schedule 10
Air
6
1
Schedule 40
LPG
12
2
Schedule 40
Steam
20
3
Schedule 40
Syngas
6
1
Schedule 40
RO Water
12
2
200
ASTM A106 ERW or Equivalent
Schedule 10
Air
8
2
15
ASTM A53 ERW Gr B or Equivalent
Schedule 40
LPG
12
2
150
ASTM A106 ERW or Equivalent
Schedule 10
Air
12
2
As per drawing
Syngas
3
1
Schedule 10
Flue Gas
23
4
Schedule 40
Compressed Air
40
7
ANSI 150
-
-
14
ANSI 150
-
-
6
Syngas ducting
750
Flue gas ducting
200
Compressed air line
25
Flanges
80
Flanges
15
ASTM A53 ERW Gr B or Equivalent ASTM A53 ERW Gr B or Equivalent ASTM A106 ERW or Equivalent ASTM A 105N or Equivalent ASTM A 105N or Equivalent
Page 31 of 32 Appendix 1 - 2TPD 190821
Description
Line Size, NB
Flanges
15
Flanges
20
Flanges
50
Flanges
80
Flanges
200
Flanges
750
Couplings
15
Couplings
25
Bend
50
Bend
80
Bend
80
Bend
15
Bend
20
Bend
200
Bend
8
Bend
25
Material of Construction ASTM A182 F304 or Equivalent ASTM A 105N or Equivalent ASTM A 105N or Equivalent ASTM A182 F304 or Equivalent ASTM A 105N or Equivalent ASTM A181 or Equivalent ASTM A 234 Gr B or Equivalent ASTM A234 Gr B/ASTM A105 or Equivalent ASTM A234 Gr B or Equivalent ASTM A234 Gr B or Equivalent ASTM A403 WP304 or Equivalent ASTM A234 Gr B or Equivalent ASTM A234 Gr B or Equivalent ASTM A234 Gr B or Equivalent ASTM A 234 Gr B or Equivalent ASTM A234 Gr B or Equivalent
Type ANSI 150 ANSI 150 ANSI 150
Medium
Length, m
-
-
-
-
Steam Line
-
-
-
-
-
-
-
-
-
BSP, Class 3000
-
-
Schedule 40
Steam Line
Short Bend, Schedule 40
-
-
-
-
ANSI 150 ANSI 150 As per drawing BSP, Class 3000
-
Schedule 40 Schedule 40 Schedule 40 Schedule 40 Schedule 40 Schedule 40
Quantity, Nos 6 6 6 8 12 4 20 20 6 10 6
-
-
-
-
-
-
-
-
-
-
10 4 2 10 10
Page 32 of 32 Appendix 1 - 2TPD 190821