DETAILING AND WORKING DRAWINGS - IDS60804
DONE BY: IVAN KHOO YUN FAN | 0344608
TAUGHT BY: SEMESTER 4 BACHELOR (HONS) IN INTERIOR ARCHITECTURE
MS. AZIAH HASSAN MS. NORJI NASIR
TABLE OF CONTENT
ASSIGNMENT 3 WORKING DRAWINGS + SYSTEM INTEGRATION
ASSIGNMENT 2 PRECEDENT STUDIES : A BUREAU
ASSIGNMENT 1 WORK FROM HOME : DOORS & WINDOWS
INTRODUCTION In
this
assignment
,
I
am
required
to
complete
a
series of working drawings that integrate with the collaborative design module for this project. The aim of this project is to be able to produce documents that
Assignment
03
integrate
working
building
collaboratively
providing
answers
to
in
services the
design
components
design
process
issues
with
by and
interior
design concepts of appropriate building scale.
WORKING DRAWINGS + SYSTEM INTEGRATION
DETAILING AND WORKING DRAWINGS [IDS60804]
ASSIGNMENT 3 : WORKING DRAWINGS + SYSTEM INTEGRATION
Name : Ivan Khoo Yun Fan Student ID : 0344608 Lecturer: Ms. Norji Bachelor of Art (HONS) in Interior Architecture
REVISION TRACKING DRAWING NO.
SHEET NAME
CURRENT REVISION
DATE
DESCRIPTION
ISSUED
1 SW_DWD_IK_SOA_01a
SCHEDULE OF ACCOMODATION 1
3
19/10/2021
ISSUED FOR CONSTRUCTION
NO
SW_DWD_IK_SOA_01b
SCHEDULE OF ACCOMODATION 2
3
19/10/2021
ISSUED FOR CONSTRUCTION
NO
SW_DWD_IK_ST_02
SETTING OUT PLAN
3
19/10/2021
ISSUED FOR CONSTRUCTION
NO
SW_DWD_IK_FLP_03
FURNITURE LAYOUT PLAN
3
19/10/2021
ISSUED FOR CONSTRUCTION
NO
SW_DWD_IK_FF_04
FOOR FINISHES PLAN
3
19/10/2021
ISSUED FOR CONSTRUCTION
NO
SW_DWD_IK_FE_05a
SCHEDULE OF FF&E 1
2
26/10/2021
ISSUED FOR CONSTRUCTION
NO
SW_DWD_IK_FE_05b
SCHEDULE OF FF&E 2
2
26/10/2021
ISSUED FOR CONSTRUCTION
NO
SW_DWD_IK_FE_05c
SCHEDULE OF FF&E 3
2
26/10/2021
ISSUED FOR CONSTRUCTION
NO
SW_DWD_IK_FE_05d
SCHEDULE OF FF&E 4
1
15/11/2021
ISSUED FOR CONSTRUCTION
NO
SW_DWD_IK_FE_05e
SCHEDULE OF FF&E 5
1
15/11/2021
ISSUED FOR CONSTRUCTION
NO
SW_DWD_IK_FE_05f
SCHEDULE OF FF&E 6
1
15/11/2021
ISSUED FOR CONSTRUCTION
NO
SW_DWD_IK_FE_05g
SCHEDULE OF FF&E 7
1
15/11/2021
ISSUED FOR CONSTRUCTION
NO
SW_DWD_IK_RCP_06
REFLECTED CEILING PLAN
1
2/11/2021
ISSUED FOR CONSTRUCTION
NO
SW_DWD_IK_LE_07
LIGHTING & ELECTRICAL PLAN
1
2/11/2021
ISSUED FOR CONSTRUCTION
NO
SW_DWD_IK_SC_08
SECTION
1
9/11/2021
ISSUED FOR CONSTRUCTION
NO
SW_DWD_IK_BT_09a
WORKSTATION LAYOUT PLAN
1
15/11/2021
ISSUED FOR CONSTRUCTION
NO
SW_DWD_IK_DT_09b
WORKSTATION ELEVATION
1
15/11/2021
ISSUED FOR CONSTRUCTION
NO
SW_DWD_IK_DT_9c
WORKSTATION SECTION
1
15/11/2021
ISSUED FOR CONSTRUCTION
NO
SW_DWD_IK_DT_9d
WORKSTATION BLOW-UP DETAILS
1
15/11/2021
ISSUED FOR CONSTRUCTION
NO
-
VIEW AT CO-WORKING ZONE (CODE)
1
16/11/2021
ISSUED FOR CONSTRUCTION
NO
-
VIEW AT CO-WORKING ZONE (SPECIFICATIONS)
0
20/11/2021
ISSUED FOR CONSTRUCTION
NO
-
BILL OF QUANTITIES
1
20/11/2021
ISSUED FOR CONSTRUCTION
NO
2
3
CHANGES
NOTE: THIS DRAWING IS COPYRIGHTED. THE AUTHORIZED USER IS TO CHECK ALL DIMENSIONS ON SITE. ONLY FIGURED DIMENSIONS ARE TO BE WORKED ON. DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO PARTNERSHIP BEFORE PROCEEDING. NO.
DESCRIPTION
CLIENT : SPORTSWORK GROUP SDN. BHD.
ARCHITECT :
NRY ARCHITECTS SDN. BHD.
INTERIOR DESIGN CONSULTANT : NINEPLUS INTERIOR DESIGN (M) SDN BHD
QUANTITY SURVEYOR : SANG QS CONSULT
PROJECT TITLE :
PROPOSE INTERIOR DESIGN AT NO.1, JALAN TAYLORS, 47500 ,SUBANG JAYA, SELANGOR. FOR SPORTSWORK
DRAWING TITLE : SCHEDULE OF ACCOMODATION 1 GROUND FLOOR SCALE :
DATE :
1:100
19 OCTOBER 2021
DATE B1-2-9, BLOCK B1,SOLARIS 15TH FLOOR, MENARA TEO CHEW, DUTAMAS,NO.1, JALAN DUTAMAS NO. 1, JALAN LUMUT 50400 KUALA 1,KUALA LUMPUR,50480 ,MALAYSIA. LUMPUR, MALAYSIA. 03-6411 6411 03-4043 1348 info@sportswork.net nry.com.my
C-11-4, Level 4, Jalan 3/144a, Medan Connaught, 56000 Kuala Lumpur, Wilayah Persekutuan Kuala Lumpur. +6012-323 3282 info@9plusinterior.com
22C, Jalan SS 19/1d, Ss 19, 47500 Subang Jaya, Selangor. 03-5613 5796 sang@sangqs.com
CHECKED BY :
DRAWN BY :
MS. NORJI
IVAN KHOO YUN FAN
DRAWING NO :
REV NO :
SW_DWD_IK_SOA_01a
03
NOTE: THIS DRAWING IS COPYRIGHTED. THE AUTHORIZED USER IS TO CHECK ALL DIMENSIONS ON SITE. ONLY FIGURED DIMENSIONS ARE TO BE WORKED ON. DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO PARTNERSHIP BEFORE PROCEEDING. NO.
DESCRIPTION
CLIENT : SPORTSWORK GROUP SDN. BHD.
ARCHITECT :
NRY ARCHITECTS SDN. BHD.
INTERIOR DESIGN CONSULTANT : NINEPLUS INTERIOR DESIGN (M) SDN BHD
QUANTITY SURVEYOR : SANG QS CONSULT
DATE 15TH FLOOR, MENARA TEO CHEW, B1-2-9, BLOCK B1,SOLARIS NO. 1, JALAN LUMUT 50400 KUALA DUTAMAS,NO.1, JALAN DUTAMAS LUMPUR, MALAYSIA. 1,KUALA LUMPUR,50480 ,MALAYSIA. 03-6411 6411 03-4043 1348 info@sportswork.net
nry.com.my
C-11-4, Level 4, Jalan 3/144a, Medan Connaught, 56000 Kuala Lumpur, Wilayah Persekutuan Kuala Lumpur. +6012-323 3282 info@9plusinterior.com
22C, Jalan SS 19/1d, Ss 19, 47500 Subang Jaya, Selangor. 03-5613 5796 sang@sangqs.com
PROJECT TITLE :
DRAWING TITLE : SCHEDULE OF ACCOMODATION 2 2ND FLOOR OFFICE LEVEL
PROPOSE INTERIOR DESIGN AT NO.1, JALAN TAYLORS, 47500 ,SUBANG JAYA, SELANGOR. FOR SPORTSWORK
SCALE :
DATE :
1:100
19 OCTOBER 2021
CHECKED BY :
DRAWN BY :
MS. NORJI
IVAN KHOO YUN FAN
DRAWING NO :
REV NO :
SW_DWD_IK_SOA_01b
03
LEGEND:
1
2
550
3
5500
4
5500
5
6
SYM.
29600
DOOR
5500
D1
5500
5500
550
D2
QTY.
DESCRIPTION
2150MM (W)X 2400MM (H) X 12MM (THK) SWING DOUBLE DOOR W/ TEMPERED GLASS FIXED PANEL 900MM (W)X 2100MM (H) X 50MM (THK) SINGLE SWING FIBERGLASS DOOR W/ CLEAR GLASS PANEL
4
6
WINDOW
A
4900MM (L) X 3400MM (H)
1880
12
2
GAMIFY TRAINING AREA 68 m²
11
3
10
4
9 5
8 6
P1
1 13
D1
D2
CO-WORKING AREA #SWING 14 m²
4000MM (W)X 2400MM (H) X 30MM (THK) CORRUGATED METAL SHEET PANEL WALL DESIGN IN BLACK POWDER COATING FINISH
2
P2 5500MM (H) X 150MM (THK) FULL
4
2400MM (H) X 30MM (THK) BRICK WALL
2
P1
HEIGHT CONCRETE WALL
P3
1690
UP
1100
D2
OKU 4 m²
P4
5200
15200
MALE TOILET 12 m²
D2 ELECTRICAL RISE 4 m²
1140
R1610
D2
UP
BROADCAST STUDIO 10 m²
MEETING AREA 16 m² 3750
5450
B
LIFT LOBBY 11 m²
2400MM (H) X 30MM (THK) FRAMELESS TEMPERED GLASS
P4 PARTITION INCLUDING ALL
2140
FFL= +460.00
SYMBOL
EXISTING CURTAIN WALL (100MM)
1100
4000
330 UP
MEET-UP 6 m²
1550
80 16
P2
D1
NEW INTERNAL BRICK WALL (150MM)
P3
EVERY STEP! 10 m²
ALL-EVENT 18 m²
P1
W1
NEW INTERNAL CORRUGATED METAL PARTITION WALL (100MM)
CO-WORKING AREA #RIDE 28 m²
D2
NEW INTERNAL CORRUGATED METAL PARTITION WALL (100MM)
FFL= +26.00
D1
ST L2
A
FFL= +46.00
D1
TOWER A- 2ND FLOOR LEVEL : SETTING OUT PLAN SCALE 1:100
NOTE:
CLIENT :
THIS DRAWING IS COPYRIGHTED. THE AUTHORIZED USER IS TO CHECK ALL DIMENSIONS ON SITE. ONLY FIGURED DIMENSIONS ARE TO BE WORKED ON. DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO PARTNERSHIP BEFORE PROCEEDING. DESCRIPTION
1600
15 m²
D
NO.
1400
2230
A
1740 CLUB GATHER
580
1960
1230
1070
920
720
NEW INTERNAL GLASS PARTITION WALL (100MM)
1390
2480
NEW INTERNAL BRICK WALL (150MM)
490 820 FFL= +520.00 740 550
DESCRIPTION EXISTING CONCRETE WALL (150MM)
UP
FEMALE TOILET 12 m²
1
NECESSARY FIXING ACCESSORIES
D2
C
4
WALL & PARTITION
3 2 12
80 16
43 10
4
10 11
1960
7
5
9
ALUMINIUM FRAME IN POWDER COATING FINISH
20 50
1880
4000
COACH LINKER 20 m²
6
2920
7 8
1
FFL= +460.00
W1 CURTAIN WALL W/
W1
620330 1030
12
DOWN
60
620 370 990
SPORTSWORK GROUP SDN. BHD.
ARCHITECT : NRY ARCHITECTS SDN. BHD.
INTERIOR DESIGN CONSULTANT : NINEPLUS INTERIOR DESIGN (M) SDN BHD
QUANTITY SURVEYOR : SANG QS CONSULT
PROJECT TITLE :
PROPOSE INTERIOR DESIGN AT NO.1, JALAN TAYLORS, 47500 ,SUBANG JAYA, SELANGOR. FOR SPORTSWORK
DATE 15TH FLOOR, MENARA TEO CHEW, B1-2-9, BLOCK B1,SOLARIS NO. 1, JALAN LUMUT 50400 KUALA DUTAMAS,NO.1, JALAN DUTAMAS LUMPUR, MALAYSIA. 1,KUALA LUMPUR,50480 ,MALAYSIA. 03-6411 6411 03-4043 1348 nry.com.my info@sportswork.net
C-11-4, Level 4, Jalan 3/144a, Medan Connaught, 56000 Kuala Lumpur, Wilayah Persekutuan Kuala Lumpur. +6012-323 3282 info@9plusinterior.com
22C, Jalan SS 19/1d, Ss 19, 47500 Subang Jaya, Selangor. 03-5613 5796 sang@sangqs.com
DRAWING TITLE : SETTING OUT PLAN 2ND FLOOR OFFICE LEVEL SCALE :
DATE :
1:100
19 OCTOBER 2021
CHECKED BY :
DRAWN BY :
MS. NORJI
IVAN KHOO YUN FAN
DRAWING NO :
REV NO :
SW_DWD_IK_ST_02
03
1
2
4
3
5
6
29600 550
5500
5500
5500
5500
5500
550
LEGEND: SYM.
QTY.
DESCRIPTION
TABLE/DESK /COUNTER (BUILT-IN FURNITURE)
T1
2800 T1
6
7 8
5
1
11
COACH LINKER 20 m²
12
5
8 6
7
1 13
GAMIFY TRAINING AREA 68 m²
9
4
2
11
10
M3
B
BROADCAST STUDIO 10 m²
UP
MALE TOILET 12 m²
M2
OKU 4 m²
5200
740
MEETING AREA 16 m²
1
T4
600MM(H) CYCLE STANDING BIKE C/W ABS PLASTIC DESK
4
460
2330
FEMALE TOILET 12 m² T4
700
A
4000MM(H) PNEUMATIC TUBING SYSTEMS
1
M2
BROADCAST STUDIO PUBLIC SPEAKING VOICE RECORDER
1
M3
BROADCAST STUDIO PODCAST HEADPHONES STATION
1
M4
STREAMING CURVE DISPLAY PANEL
1
M6
ALL-EVENT 18 m²
UP
2170
1050 MEET-UP 6 m²
T4
C2
FFL= +26.00
D
T3
M7
CO-WORKING AREA #RIDE 28 m²
T2
600MM X 600MM OFFICE PRINTER / PHOTOCOPY MACHINE TO DESIGNERS APPROVAL
1
1800MM(H) X 3000MM(L) TRIPLE LAYER WHITEBOARD TO DESIGNERS APPROVAL
1
5330
2270
1430
T2
EVERY STEP! 10 m²
80 0
UP
T2
1050
1130
4000
CLUB GATHER 15 m²
M1
1
M1
1440 0
2160MM(L) X 2160MM(W) X400MM(H) PLUSH FABRIC PEBBLE MODULAR SOFA
10
MACHINES ( LOOSE FURNITURE)
1430
45
450MM X 450MM OFFICE CHAIRS FOR MEETING AREA TO DESIGNERS APPROVAL
MACHINES ( BUILT-IN FURNITURE)
M7 UP
C
450MM X 450MM SELF CHECK-OUT KIOSK TO DESIGNERS APPROVAL
C2
M6
990
LIFT LOBBY 11 m²
T3
C1
ELECTRICAL RISE 4 m²
UP
3
CHAIR ( LOOSE FURNITURE)
CO-WORKING AREA #SWING 14 m²
C1
3820
15200
M4
450MM X 450MM SELF CHECK-IN KIOSK TO DESIGNERS APPROVAL
3
1350
4000
2 3
2520
C1
10
12
T2
4
9
1350
DOWN
1
TABLE/ DESK / COUNTER (LOOSE FURNITURE)
1680
A
550MM (W) X 550MM (H) X 20MM (THK) PIPING WORKSTATION DESK
A
2460
FFL= +46.00
600MM(H) CYCLE STANDING BIKE C/W ABS PLASTIC DESK TO DESIGNERS APPROVAL 2160MM(L) X 2160MM(W) X400MM(H) PLUSH FABRIC PEBBLE MODULAR SOFA TO DESIGNERS APPROVAL
FLP L2
TOWER A- 2ND FLOOR LEVEL : FURNITURE LAYOUT PLAN SCALE 1:100
NOTE: THIS DRAWING IS COPYRIGHTED. THE AUTHORIZED USER IS TO CHECK ALL DIMENSIONS ON SITE. ONLY FIGURED DIMENSIONS ARE TO BE WORKED ON. DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO PARTNERSHIP BEFORE PROCEEDING. NO.
DESCRIPTION
DATE
CLIENT : SPORTSWORK GROUP SDN. BHD.
ARCHITECT :
NRY ARCHITECTS SDN. BHD.
B1-2-9, BLOCK B1,SOLARIS 15TH FLOOR, MENARA TEO CHEW, DUTAMAS,NO.1, JALAN DUTAMAS NO. 1, JALAN LUMUT 50400 KUALA 1,KUALA LUMPUR,50480 ,MALAYSIA. LUMPUR, MALAYSIA. 03-6411 6411 03-4043 1348 info@sportswork.net nry.com.my
INTERIOR DESIGN CONSULTANT : NINEPLUS INTERIOR DESIGN (M) SDN BHD
C-11-4, Level 4, Jalan 3/144a, Medan Connaught, 56000 Kuala Lumpur, Wilayah Persekutuan Kuala Lumpur. +6012-323 3282 info@9plusinterior.com
QUANTITY SURVEYOR : SANG QS CONSULT
22C, Jalan SS 19/1d, Ss 19, 47500 Subang Jaya, Selangor. 03-5613 5796 sang@sangqs.com
PROJECT TITLE :
DRAWING TITLE : FURNITURE LAYOUT PLAN 2ND FLOOR OFFICE LEVEL
PROPOSE INTERIOR DESIGN AT NO.1, JALAN TAYLORS, 47500 ,SUBANG JAYA, SELANGOR. FOR SPORTSWORK
SCALE :
DATE :
1:100
19 OCTOBER 2021
CHECKED BY :
DRAWN BY :
MS. NORJI
IVAN KHOO YUN FAN
DRAWING NO :
REV NO :
SW_DWD_IK_FLP_03
03
1
2
4
3
5
6
29600 550
5500
5500
5500
5500
5500
550 LEGEND: SYM.
A
FF1 7
6
12
8
5
4
9 1
2
10
5
8 7
43
10
8 16
1690
1100
12
0
1960
MEETING AREA 16 m² 3750
OKU SOP
FF5
ELECTRICAL RISE SOP 4 m²
1140
R1610
UP
BROADCAST STUDIO 10 m²
LIFT LOBBY 11 m²
5450
FF4
5200
15200
MALE TOILET 12 m²
FF6 4 m²
6MM (THK) POLYPROPYLENE PATTERNED CARPET
62m2
FF2 CONCRETE FLOORING
110m2
200MM(W) X 200MM (L) X 30MM FF3 (THK) SEQUOIA WOOD LOOK TILES
15m2
FF4 230MM X 230MM NOIR HEX TRAVERTINE MOSAIC TILE
11m2
FF5
300MM(W) X 300MM(L) ASIAGO GRAY PORCELAIN TILE
4m2
FF6
300MM(W) X 300MM(L) ARCADIA STONE BEIGE PORCELAIN TILE
4m2
FF7
300MM(W) X 300MM(L) BLACK SLATE EFFECT TILE MATT FINISH
24m2
FF8
30MM (THK) DIAMOND PLATED STEEL ANTI-SLIP FINISH
8m2
SOP
FF7
FF8
CO-WORKING AREA #SWING 14 m²
1 13
9
4
6
B
2
11
70
COACH LINKER 20 m²
GAMIFY TRAINING AREA 68 m²
11
3
AREA
3
20
4000
FF9
10
12
2920
60
SOP
DESCRIPTION
FEMALE TOILET FF712 m²
2140
200MM(W) X 200MM (L) X 30MM (THK) SEQUOIA WOOD LOOK TILES
600MM(W) X 600MM (L) X 20MM FF9 (THK) WHITE ORNAMENT TERRAZZO TILE
18m2
2480
720
740 550
4000
1230
1740 CLUB GATHER
SOP
SOP
1070
500
1400
330
1600
FF2
A
MEET-UP 6 m²
2230
15 m²
ALL-EVENT 18 m²
EVERY STEP! 10 m² FFL= +26.00
D
FF1
6MM (THK) POLYPROPYLENE PATTERNED CARPET
A
FFL= +46.00 SOP
FF L2
TOWER A- 2ND FLOOR LEVEL : FLOOR FINISHES PLAN SCALE 1:100
NOTE: THIS DRAWING IS COPYRIGHTED. THE AUTHORIZED USER IS TO CHECK ALL DIMENSIONS ON SITE. ONLY FIGURED DIMENSIONS ARE TO BE WORKED ON. DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO PARTNERSHIP BEFORE PROCEEDING. NO.
CO-WORKING AREA #RIDE 28 m²
1960
FF3
SOP
920
C
490 820
1390
1100
FF3 SOP
DESCRIPTION
DATE
CLIENT : SPORTSWORK GROUP SDN. BHD.
ARCHITECT :
NRY ARCHITECTS SDN. BHD.
B1-2-9, BLOCK B1,SOLARIS 15TH FLOOR, MENARA TEO CHEW, DUTAMAS,NO.1, JALAN DUTAMAS NO. 1, JALAN LUMUT 50400 KUALA 1,KUALA LUMPUR,50480 ,MALAYSIA. LUMPUR, MALAYSIA. 03-6411 6411 03-4043 1348 info@sportswork.net nry.com.my
INTERIOR DESIGN CONSULTANT : NINEPLUS INTERIOR DESIGN (M) SDN BHD
C-11-4, Level 4, Jalan 3/144a, Medan Connaught, 56000 Kuala Lumpur, Wilayah Persekutuan Kuala Lumpur. +6012-323 3282 info@9plusinterior.com
QUANTITY SURVEYOR : SANG QS CONSULT
22C, Jalan SS 19/1d, Ss 19, 47500 Subang Jaya, Selangor. 03-5613 5796 sang@sangqs.com
PROJECT TITLE :
DRAWING TITLE : FLOOR FINISHES PLAN 2ND FLOOR OFFICE LEVEL
PROPOSE INTERIOR DESIGN AT NO.1, JALAN TAYLORS, 47500 ,SUBANG JAYA, SELANGOR. FOR SPORTSWORK
SCALE :
DATE :
1:100
19 OCTOBER 2021
CHECKED BY :
DRAWN BY :
MS. NORJI
IVAN KHOO YUN FAN
DRAWING NO :
REV NO :
SW_DWD_IK_FFP_04
03
SCHEDULE OF FURNITURE, FIXTURES & EQUIPMENT NO.
CODE
IMAGE
SPECIFICATION
UNIT PRICE (RM) QUANTITY
LOCATION
SUPPLIER
CO-WORKING ZONE
1
2
3
LF-01
ALL-IN-ONE DESK BIKE V9 815MM(L)X320MM(W)X823MM(H)
LF-02
CHADWICK MODULAR OFFICE SOFA 450MM(H) POLYESTER COVER W/ POLYURETHANE FOAM
LF-03
AQUA KENT STANDING WATER DISPENSER K52 300MM (L) X 395MM ( W) X 1110MM (H)
GROUND FLOOR
GROUND FLOOR
RM1399.00
RM2500.00
RM1500.00
4
1
ZENITH PROJECTS SDN. BHD. B-15-07,The TUBE, Menara Prima, Level 13A & Level 15, unit 07, 47301 Petaling Jaya, Selangor. TEL: +603-78871733
1
AGIES RESOURCES SDN. BHD. Jalan Tembaga SD 5/2G, Bandar Sri Damansara, Sungai Buloh,52200 Kuala Lumpur. TEL: 03-6189 0333
1
RICOH (MALAYSIA) SDN. BHD No. 5, Jalan Penyair U1/44, 40150 Shah Alam, Malaysia. TEL:1-300-88-8228
1
IKEA 2, Jalan PJU 7/2, Mutiara Damansara, 47800 Petaling Jaya, Selangor.
IKEA 2, Jalan PJU 7/2, Mutiara Damansara, 47800 Petaling Jaya, Selangor.
LF-04
RICOH MPC3502PSF PHOTOCOPY MACHINE 766MM(L)X 670MM(W)X1020MM(H)
LF-05
LED DOWNLIGHT 150MM(D)X110MM(H) ALUMINUM SURFACE MOUNTED DOWNLIGHT ROUND W/ 12W BUILT-IN LED
6
LF-06
FEJKA ARTIFICIAL POTTED PLANT 900MM(D) INDOOR PLANT
GROUND FLOOR
RM199.00
1
7
LF-07
PHILIPS 58090 LED ROUND PENDANT LIGHT 800MM(D) ALUMINUM BLACK ROUND LED PENDANT LIGHT 60W LIGHT UP AND DOWN
GROUND FLOOR
RM399.00
2
4
5
NOTE: THIS DRAWING IS COPYRIGHTED. THE AUTHORIZED USER IS TO CHECK ALL DIMENSIONS ON SITE. ONLY FIGURED DIMENSIONS ARE TO BE WORKED ON. DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO PARTNERSHIP BEFORE PROCEEDING. NO.
GROUND FLOOR
FLEXISPOT Lot 2217-12, Jalan Kusta,Kampung Jaya Industrial Area,47000 Sungai Buloh, Selangor. TEL: +6017 297 1933
DESCRIPTION
DATE
CLIENT : SPORTSWORK GROUP SDN. BHD.
ARCHITECT :
NRY ARCHITECTS SDN. BHD.
GROUND FLOOR
GROUND FLOOR
INTERIOR DESIGN CONSULTANT : NINEPLUS INTERIOR DESIGN (M) SDN BHD
RM3500.00
RM20.00
QUANTITY SURVEYOR : SANG QS CONSULT
JLL ELECTRICAL SDN BHD A-G-3A, Kuchai Exchange, 43, Jalan Kuchai Maju 13, 58200 Kuala Lumpur, Malaysia. TEL: 03-7987 1266
PROJECT TITLE :
PROPOSE INTERIOR DESIGN AT NO.1, JALAN TAYLORS, 47500 ,SUBANG JAYA, SELANGOR. FOR SPORTSWORK B1-2-9, BLOCK B1,SOLARIS 15TH FLOOR, MENARA TEO CHEW, DUTAMAS,NO.1, JALAN DUTAMAS NO. 1, JALAN LUMUT 50400 KUALA 1,KUALA LUMPUR,50480 ,MALAYSIA. LUMPUR, MALAYSIA. 03-6411 6411 03-4043 1348 info@sportswork.net nry.com.my
C-11-4, Level 4, Jalan 3/144a, Medan Connaught, 56000 Kuala Lumpur, Wilayah Persekutuan Kuala Lumpur. +6012-323 3282 info@9plusinterior.com
22C, Jalan SS 19/1d, Ss 19, 47500 Subang Jaya, Selangor. 03-5613 5796 sang@sangqs.com
DRAWING TITLE : SCHEDULE OF FURNITURE , FITTINGS & EQUIPMENTS 1 2ND FLOOR OFFICE LEVEL SCALE :
DATE :
NOT TO SCALE
19 OCTOBER 2021
CHECKED BY :
DRAWN BY :
MS. NORJI
IVAN KHOO YUN FAN
DRAWING NO :
REV NO :
SW_DWD_IK_FFNE_05a
03
SCHEDULE OF FURNITURE, FIXTURES & EQUIPMENT NO.
CODE
IMAGE
SPECIFICATION
UNIT PRICE (RM) QUANTITY
LOCATION
SUPPLIER
CO-WORKING ZONE
8
9
10
E8333L1 SCHNEIDER AVATARON SWITCH SOCKET 3 GANG 1 WAY SWITCHED SOCKET 16A/250V
LF-08
LF-09
E8332L2 SCHNEIDER AVATARON SWITCH SOCKET 2 GANG 1 WAY SWITCHED SOCKET 16A/250V
LF-10
E8331L1 SCHNEIDER AVATARON SWITCH SOCKET 1GANG 1 WAY SWITCHED SOCKET 20A/250V
GROUND FLOOR
GROUND FLOOR
GROUND FLOOR
RM45.00
RM35.00
RM28.00
1
ELUXE LIGHTING SDN. BHD. K03-10-08, UOA Business Park, No.1 , Jalan Pengaturcara U1/51A, 40150 Shah Alam, Selangor,Darul Ehsan,Malaysia. TEL: + (60) 0109784868
1
ELUXE LIGHTING SDN. BHD. K03-10-08, UOA Business Park, No.1 , Jalan Pengaturcara U1/51A, 40150 Shah Alam, Selangor,Darul Ehsan,Malaysia. TEL: + (60) 0109784868
1
E-STREET No. 527a, Jalan Tiong, 3rd Miles, Jalan Ipoh, 51100 Kuala Lumpur. TEL: +603-4041 4188
5
RAJTAI SHREE D-96, Azad Nagar, Bhilwara, Rajasthan 311001 TEL: 91 94149 78622
1
AFIA MANUFACTURING SDN BHD No: 16, Jalan Cemur off Jalan Tun Razak,50400 Kuala Lumpur, Malaysia. TEL: 03- 4042 6827
MEETING AREA
LF-11
BIKE STOOL 350MM(W) X 750MM(H) INDUSTRIAL STOOL-RUSTIC SWIVEL BIKE STOOL W/ PU LEATHER SEAT
12
LF-12
TRACK WALL SLIDES 2400MM(H) X 4000MM(W)
GROUND FLOOR
RM1800.00
13
LF-07
PHILIPS 58090 LED ROUND PENDANT LIGHT 800MM(D) ALUMINUM ROUND LED PENDANT LIGHT LED BLACK 60W LIGHT UP AND DOWN
GROUND FLOOR
RM399.00
11
NOTE:
CLIENT :
THIS DRAWING IS COPYRIGHTED. THE AUTHORIZED USER IS TO CHECK ALL DIMENSIONS ON SITE. ONLY FIGURED DIMENSIONS ARE TO BE WORKED ON. DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO PARTNERSHIP BEFORE PROCEEDING. NO.
DESCRIPTION
SPORTSWORK GROUP SDN. BHD.
ARCHITECT :
NRY ARCHITECTS SDN. BHD.
GROUND FLOOR
INTERIOR DESIGN CONSULTANT : NINEPLUS INTERIOR DESIGN (M) SDN BHD
RM249.00
QUANTITY SURVEYOR : SANG QS CONSULT
2
JLL ELECTRICAL SDN BHD A-G-3A, Kuchai Exchange, 43, Jalan Kuchai Maju 13, 58200 Kuala Lumpur, Malaysia. TEL: 03-7987 1266
PROJECT TITLE :
PROPOSE INTERIOR DESIGN AT NO.1, JALAN TAYLORS, 47500 ,SUBANG JAYA, SELANGOR. FOR SPORTSWORK
DATE B1-2-9, BLOCK B1,SOLARIS DUTAMAS,NO.1, JALAN DUTAMAS 1,KUALA LUMPUR,50480 ,MALAYSIA. 03-6411 6411 info@sportswork.net
15TH FLOOR, MENARA TEO CHEW, NO. 1, JALAN LUMUT 50400 KUALA LUMPUR, MALAYSIA. 03-4043 1348 nry.com.my
C-11-4, Level 4, Jalan 3/144a, Medan Connaught, 56000 Kuala Lumpur, Wilayah Persekutuan Kuala Lumpur. +6012-323 3282 info@9plusinterior.com
22C, Jalan SS 19/1d, Ss 19, 47500 Subang Jaya, Selangor. 03-5613 5796 sang@sangqs.com
DRAWING TITLE : SCHEDULE OF FURNITURE , FITTINGS & EQUIPMENTS 2 2ND FLOOR OFFICE LEVEL SCALE :
DATE :
1:100
19 OCTOBER 2021
CHECKED BY :
DRAWN BY :
MS. NORJI
IVAN KHOO YUN FAN
DRAWING NO :
REV NO :
SW_DWD_IK_FFNE_05b
03
SCHEDULE OF FURNITURE, FIXTURES & EQUIPMENT NO.
CODE
IMAGE
SPECIFICATION
UNIT PRICE (RM) QUANTITY
LOCATION
SUPPLIER
ALL-EVENT ZONE
14
LF-13
SELF CHECK-IN KIOSK 1200MM(H) X 450MM(L) X 120MM(W)
15
LF-07
PHILIPS 58090 LED ROUND PENDANT LIGHT 800MM(D) ALUMINUM ROUND LED PENDANT LIGHT LED BLACK 60W LIGHT UP AND DOWN
16
17
18
19
LED SIGNBOARD 600MM(L) X 80MM(W) X300MM(H)
LF-14
ARTIFICIAL HANGING VINES 850MM(H) INDOOR PLANT
LF-15
E8315 SCHNEIDER AVATARON SWITCH SOCKET 1GANG SWITCHED SOCKET 13A/250V
LF-17
NOTE: THIS DRAWING IS COPYRIGHTED. THE AUTHORIZED USER IS TO CHECK ALL DIMENSIONS ON SITE. ONLY FIGURED DIMENSIONS ARE TO BE WORKED ON. DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO PARTNERSHIP BEFORE PROCEEDING. NO.
DESCRIPTION
CLIENT : SPORTSWORK GROUP SDN. BHD.
ARCHITECT :
NRY ARCHITECTS SDN. BHD.
RM3999.00
3
GROUND FLOOR
RM399.00
3
GROUND FLOOR
GROUND FLOOR
E83T25 SCHNEIDER AVATARON SWITCH SOCKET 2 GANG SWITCHED SOCKET 16A/250V
LF-16
GROUND FLOOR
GROUND FLOOR
GROUND FLOOR
INTERIOR DESIGN CONSULTANT : NINEPLUS INTERIOR DESIGN (M) SDN BHD
RM280.00
RM7.90
RM60.00
RM19.40
QUANTITY SURVEYOR : SANG QS CONSULT
DATE B1-2-9, BLOCK B1,SOLARIS 15TH FLOOR, MENARA TEO CHEW, DUTAMAS,NO.1, JALAN DUTAMAS NO. 1, JALAN LUMUT 50400 KUALA 1,KUALA LUMPUR,50480 ,MALAYSIA. LUMPUR, MALAYSIA. 03-6411 6411 03-4043 1348 info@sportswork.net nry.com.my
C-11-4, Level 4, Jalan 3/144a, Medan Connaught, 56000 Kuala Lumpur, Wilayah Persekutuan Kuala Lumpur. +6012-323 3282 info@9plusinterior.com
22C, Jalan SS 19/1d, Ss 19, 47500 Subang Jaya, Selangor. 03-5613 5796 sang@sangqs.com
WHITEBEAN A-04-03, Tamarind Square, Persiaran Multimedia Cyber 10, 63000 Cyberjaya, Selangor. TEL: 1700 81 4599
JLL ELECTRICAL SDN BHD A-G-3A, Kuchai Exchange, 43, Jalan Kuchai Maju 13, 58200 Kuala Lumpur, Malaysia. TEL: 03-7987 1266
3
VOTIGO SYSTEMS (M) SDN BHD Unit 2-1, Level 2, The Podium, Tower 3, UOA Business Park,No, 1, Jalan Pengaturcara U1/51a, Seksyen U1,40150 Shah Alam, Selangor. TEL: +03 2935 8188
8
KAISON @ SUNWAY PYRAMID LG2.17 & LG2.18, Level LG2 Sunway Pyramid Shopping Mall, No. 3, Jalan PJS 11/15, Bandar Sunway, 47500 Petaling Jaya, Selangor. TEL: 03-5611 9052
1
ELUXE LIGHTING SDN. BHD. K03-10-08, UOA Business Park, No.1 , Jalan Pengaturcara U1/51A, 40150 Shah Alam, Selangor,Darul Ehsan,Malaysia. TEL: + (60) 0109784868
1
E-STREET No. 527a, Jalan Tiong, 3rd Miles, Jalan Ipoh, 51100 Kuala Lumpur. TEL: +603-4041 4188
PROJECT TITLE :
DRAWING TITLE : SCHEDULE OF FURNITURE , FITTINGS & EQUIPMENTS 3 2ND FLOOR OFFICE LEVEL
PROPOSE INTERIOR DESIGN AT NO.1, JALAN TAYLORS, 47500 ,SUBANG JAYA, SELANGOR. FOR SPORTSWORK
SCALE :
DATE :
NOT TO SCALE
19 OCTOBER 2021
CHECKED BY :
DRAWN BY :
MS. NORJI
IVAN KHOO YUN FAN
DRAWING NO :
REV NO :
SW_DWD_IK_FFNE_05c
03
SCHEDULE OF FURNITURE, FIXTURES & EQUIPMENT NO.
CODE
IMAGE
SPECIFICATION
UNIT PRICE (RM) QUANTITY
LOCATION
SUPPLIER
EVERY STEP ZONE
20
LF-18
LCD INTERATIVE TOUCH SCREEN KIOSK 42" HD 1080P PORTRAIT SCREEN
GROUND FLOOR
RM5999.00
1
21
LF-07
PHILIPS 58090 LED ROUND PENDANT LIGHT 800MM(D) ALUMINUM ROUND LED PENDANT LIGHT LED BLACK 60W LIGHT UP AND DOWN
GROUND FLOOR
RM399.00
3
22
23
E8332L2 SCHNEIDER AVATARON SWITCH SOCKET 2 GANG 1 WAY SWITCHED SOCKET 16A/250V
LF-09
ARTIFICIAL HANGING VINES 850MM(H) INDOOR PLANT
LF-15
GROUND FLOOR
GROUND FLOOR
RM35.00
RM7.90
WHITEBEAN A-04-03, Tamarind Square, Persiaran Multimedia Cyber 10, 63000 Cyberjaya, Selangor. TEL: 1700 81 4599
JLL ELECTRICAL SDN BHD A-G-3A, Kuchai Exchange, 43, Jalan Kuchai Maju 13, 58200 Kuala Lumpur, Malaysia. TEL: 03-7987 1266
1
ELUXE LIGHTING SDN. BHD. K03-10-08, UOA Business Park, No.1 , Jalan Pengaturcara U1/51A, 40150 Shah Alam, Selangor,Darul Ehsan,Malaysia. TEL: + (60) 0109784868
8
KAISON @ SUNWAY PYRAMID LG2.17 & LG2.18, Level LG2 Sunway Pyramid Shopping Mall, No. 3, Jalan PJS 11/15, Bandar Sunway, 47500 Petaling Jaya, Selangor. TEL: 03-5611 9052
CLUB-GATHER ZONE
24
25
LF-07
PHILIPS 58090 LED ROUND PENDANT LIGHT 800MM(D) ALUMINUM ROUND LED PENDANT LIGHT LED BLACK 60W LIGHT UP AND DOWN
LF-17
E8315 SCHNEIDER AVATARON SWITCH SOCKET 1GANG SWITCHED SOCKET 13A/250V
NOTE: THIS DRAWING IS COPYRIGHTED. THE AUTHORIZED USER IS TO CHECK ALL DIMENSIONS ON SITE. ONLY FIGURED DIMENSIONS ARE TO BE WORKED ON. DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO PARTNERSHIP BEFORE PROCEEDING. NO.
DESCRIPTION
CLIENT : SPORTSWORK GROUP SDN. BHD.
ARCHITECT :
NRY ARCHITECTS SDN. BHD.
GROUND FLOOR
GROUND FLOOR
INTERIOR DESIGN CONSULTANT : NINEPLUS INTERIOR DESIGN (M) SDN BHD
RM399.00
RM19.40
QUANTITY SURVEYOR : SANG QS CONSULT
DATE B1-2-9, BLOCK B1,SOLARIS 15TH FLOOR, MENARA TEO CHEW, DUTAMAS,NO.1, JALAN DUTAMAS NO. 1, JALAN LUMUT 50400 KUALA 1,KUALA LUMPUR,50480 ,MALAYSIA. LUMPUR, MALAYSIA. 03-6411 6411 03-4043 1348 info@sportswork.net nry.com.my
C-11-4, Level 4, Jalan 3/144a, Medan Connaught, 56000 Kuala Lumpur, Wilayah Persekutuan Kuala Lumpur. +6012-323 3282 info@9plusinterior.com
22C, Jalan SS 19/1d, Ss 19, 47500 Subang Jaya, Selangor. 03-5613 5796 sang@sangqs.com
3
1
JLL ELECTRICAL SDN BHD A-G-3A, Kuchai Exchange, 43, Jalan Kuchai Maju 13, 58200 Kuala Lumpur, Malaysia. TEL: 03-7987 1266
E-STREET No. 527a, Jalan Tiong, 3rd Miles, Jalan Ipoh, 51100 Kuala Lumpur. TEL: +603-4041 4188
PROJECT TITLE :
DRAWING TITLE : SCHEDULE OF FURNITURE , FITTINGS & EQUIPMENTS 4 2ND FLOOR OFFICE LEVEL
PROPOSE INTERIOR DESIGN AT NO.1, JALAN TAYLORS, 47500 ,SUBANG JAYA, SELANGOR. FOR SPORTSWORK
SCALE :
DATE :
NOT TO SCALE
19 OCTOBER 2021
CHECKED BY :
DRAWN BY :
MS. NORJI
IVAN KHOO YUN FAN
DRAWING NO :
REV NO :
SW_DWD_IK_FFNE_05d
03
SCHEDULE OF FURNITURE, FIXTURES & EQUIPMENT NO.
CODE
IMAGE
SPECIFICATION
UNIT PRICE (RM) QUANTITY
LOCATION
SUPPLIER
MEET-UP ZONE
26
27
28
LF-05
LED DOWNLIGHT 150MM(D)X110MM(H) ALUMINUM SURFACE MOUNTED DOWNLIGHT ROUND W/ 12W BUILT-IN LED
LF-17
E8315 SCHNEIDER AVATARON SWITCH SOCKET 1GANG SWITCHED SOCKET 13A/250V
LF-10
E8331L1 SCHNEIDER AVATARON SWITCH SOCKET 1GANG 1 WAY SWITCHED SOCKET 20A/250V
GROUND FLOOR
GROUND FLOOR
GROUND FLOOR
3
IKEA 2, Jalan PJU 7/2, Mutiara Damansara, 47800 Petaling Jaya, Selangor.
1
E-STREET No. 527a, Jalan Tiong, 3rd Miles, Jalan Ipoh, 51100 Kuala Lumpur. TEL: +603-4041 4188
RM28.00
1
E-STREET No. 527a, Jalan Tiong, 3rd Miles, Jalan Ipoh, 51100 Kuala Lumpur. TEL: +603-4041 4188
RM249.00
5
RAJTAI SHREE D-96, Azad Nagar, Bhilwara, Rajasthan 311001 TEL: 91 94149 78622
RM20.00
RM19.40
COACH LINKER ZONE
29
30
31
LF-11
BIKE STOOL 350MM(W) X 750MM(H) INDUSTRIAL STOOL-RUSTIC SWIVEL BIKE STOOL W/ PU LEATHER SEAT
GROUND FLOOR
LF-07
PHILIPS 58090 LED ROUND PENDANT LIGHT 800MM(D) ALUMINUM ROUND LED PENDANT LIGHT LED BLACK 60W LIGHT UP AND DOWN
GROUND FLOOR
E8331L1 SCHNEIDER AVATARON SWITCH SOCKET 1GANG 1 WAY SWITCHED SOCKET 20A/250V
LF-10
NOTE: THIS DRAWING IS COPYRIGHTED. THE AUTHORIZED USER IS TO CHECK ALL DIMENSIONS ON SITE. ONLY FIGURED DIMENSIONS ARE TO BE WORKED ON. DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO PARTNERSHIP BEFORE PROCEEDING. NO.
DESCRIPTION
CLIENT : SPORTSWORK GROUP SDN. BHD.
ARCHITECT :
NRY ARCHITECTS SDN. BHD.
GROUND FLOOR
INTERIOR DESIGN CONSULTANT : NINEPLUS INTERIOR DESIGN (M) SDN BHD
RM399.00
RM28.00
QUANTITY SURVEYOR : SANG QS CONSULT
DATE B1-2-9, BLOCK B1,SOLARIS 15TH FLOOR, MENARA TEO CHEW, DUTAMAS,NO.1, JALAN DUTAMAS NO. 1, JALAN LUMUT 50400 KUALA 1,KUALA LUMPUR,50480 ,MALAYSIA. LUMPUR, MALAYSIA. 03-6411 6411 03-4043 1348 info@sportswork.net nry.com.my
C-11-4, Level 4, Jalan 3/144a, Medan Connaught, 56000 Kuala Lumpur, Wilayah Persekutuan Kuala Lumpur. +6012-323 3282 info@9plusinterior.com
22C, Jalan SS 19/1d, Ss 19, 47500 Subang Jaya, Selangor. 03-5613 5796 sang@sangqs.com
1
1
JLL ELECTRICAL SDN BHD A-G-3A, Kuchai Exchange, 43, Jalan Kuchai Maju 13, 58200 Kuala Lumpur, Malaysia. TEL: 03-7987 1266
E-STREET No. 527a, Jalan Tiong, 3rd Miles, Jalan Ipoh, 51100 Kuala Lumpur. TEL: +603-4041 4188
PROJECT TITLE :
DRAWING TITLE : SCHEDULE OF FURNITURE , FITTINGS & EQUIPMENTS 5 2ND FLOOR OFFICE LEVEL
PROPOSE INTERIOR DESIGN AT NO.1, JALAN TAYLORS, 47500 ,SUBANG JAYA, SELANGOR. FOR SPORTSWORK
SCALE :
DATE :
NOT TO SCALE
15 NOVEMBER 2021
CHECKED BY :
DRAWN BY :
MS. NORJI
IVAN KHOO YUN FAN
DRAWING NO :
REV NO :
SW_DWD_IK_FFNE_05e
01
SCHEDULE OF FURNITURE, FIXTURES & EQUIPMENT NO.
CODE
IMAGE
SPECIFICATION
UNIT PRICE (RM) QUANTITY
LOCATION
SUPPLIER
BROADCAST STUDIO
32
33
34
35
36
LF-19
105" CURVED UHD DISPLAY SCREEN
LF-20
PHISON PM58-C TV MOUNT CEILING 1320MM(H) CEILING LCD/LED TV MOUNT
LF-21
SONY HXR-MC88 FULL HD CAMCORDER
ALZO UPRIGHT CAMERA CEILING MOUNT 200MM(H)X 150MM(W)
LF-22
E8332L2 SCHNEIDER AVATARON SWITCH SOCKET 2 GANG 1 WAY SWITCHED SOCKET 16A/250V
LF-09
GROUND FLOOR
GROUND FLOOR
GROUND FLOOR
GROUND FLOOR
GROUND FLOOR
RM24000.00
RM225.00
RM5790.00
RM225.00
RM35.00
1
LG ELECTRONICS (M) SDN BHD 16, Jalan Pendekar 10, Taman Ungku Tun Aminah,81300 Johor Bahru, Johor. TEL: 1300-822-822
1
HOUSES LIGHTINGS 29, 31, 33, 35, Jalan BPU 6, Bandar Puchong Utama, 47100 Puchong, Selangor, Malaysia. TEL: +6012-266 3790
2
SHASHINKI SDN BHD 69, Jalan Flora 1/9, Taman Pulai Flora, 81300 Skudai, Johor, Malaysia. TEL:+607-5559567
2
SHASHINKI SDN BHD 69, Jalan Flora 1/9, Taman Pulai Flora, 81300 Skudai, Johor, Malaysia. TEL:+607-5559567
1
ELUXE LIGHTING SDN. BHD. K03-10-08, UOA Business Park, No.1 , Jalan Pengaturcara U1/51A, 40150 Shah Alam, Selangor,Darul Ehsan,Malaysia. TEL: + (60) 0109784868
37
LF-16
E83T25 SCHNEIDER AVATARON SWITCH SOCKET 2 GANG SWITCHED SOCKET 16A/250V
GROUND FLOOR
RM60.00
1
ELUXE LIGHTING SDN. BHD. K03-10-08, UOA Business Park, No.1 , Jalan Pengaturcara U1/51A, 40150 Shah Alam, Selangor,Darul Ehsan,Malaysia. TEL: + (60) 0109784868
38
LF-05
LED DOWNLIGHT 150MM(D)X110MM(H) ALUMINUM SURFACE MOUNTED DOWNLIGHT ROUND W/ 12W BUILT-IN LED
GROUND FLOOR
RM20.00
12
IKEA 2, Jalan PJU 7/2, Mutiara Damansara, 47800 Petaling Jaya, Selangor.
NOTE: THIS DRAWING IS COPYRIGHTED. THE AUTHORIZED USER IS TO CHECK ALL DIMENSIONS ON SITE. ONLY FIGURED DIMENSIONS ARE TO BE WORKED ON. DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO PARTNERSHIP BEFORE PROCEEDING. NO.
DESCRIPTION
CLIENT : SPORTSWORK GROUP SDN. BHD.
ARCHITECT :
NRY ARCHITECTS SDN. BHD.
INTERIOR DESIGN CONSULTANT : NINEPLUS INTERIOR DESIGN (M) SDN BHD
QUANTITY SURVEYOR : SANG QS CONSULT
DATE B1-2-9, BLOCK B1,SOLARIS 15TH FLOOR, MENARA TEO CHEW, DUTAMAS,NO.1, JALAN DUTAMAS NO. 1, JALAN LUMUT 50400 KUALA 1,KUALA LUMPUR,50480 ,MALAYSIA. LUMPUR, MALAYSIA. 03-6411 6411 03-4043 1348 info@sportswork.net nry.com.my
C-11-4, Level 4, Jalan 3/144a, Medan Connaught, 56000 Kuala Lumpur, Wilayah Persekutuan Kuala Lumpur. +6012-323 3282 info@9plusinterior.com
22C, Jalan SS 19/1d, Ss 19, 47500 Subang Jaya, Selangor. 03-5613 5796 sang@sangqs.com
PROJECT TITLE :
DRAWING TITLE : SCHEDULE OF FURNITURE , FITTINGS & EQUIPMENTS 6 2ND FLOOR OFFICE LEVEL
PROPOSE INTERIOR DESIGN AT NO.1, JALAN TAYLORS, 47500 ,SUBANG JAYA, SELANGOR. FOR SPORTSWORK
SCALE :
DATE :
NOT TO SCALE
15 NOVEMBER 2021
CHECKED BY :
DRAWN BY :
MS. NORJI
IVAN KHOO YUN FAN
DRAWING NO :
REV NO :
SW_DWD_IK_FFNE_05f
01
SCHEDULE OF FURNITURE, FIXTURES & EQUIPMENT NO.
CODE
IMAGE
SPECIFICATION
UNIT PRICE (RM) QUANTITY
LOCATION
SUPPLIER
GAMIFY TRAINING ZONE
39
40
41
PHILIPS 58090 LED ROUND PENDANT LIGHT 800MM(D) ALUMINUM ROUND LED PENDANT LIGHT LED BLACK 60W LIGHT UP AND DOWN
LF-07
E8332L2 SCHNEIDER AVATARON SWITCH SOCKET 2 GANG 1 WAY SWITCHED SOCKET 16A/250V
LF-09
ARTIFICIAL HANGING VINES 850MM(H) INDOOR PLANT
LF-15
NOTE: THIS DRAWING IS COPYRIGHTED. THE AUTHORIZED USER IS TO CHECK ALL DIMENSIONS ON SITE. ONLY FIGURED DIMENSIONS ARE TO BE WORKED ON. DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO PARTNERSHIP BEFORE PROCEEDING. NO.
DESCRIPTION
CLIENT : SPORTSWORK GROUP SDN. BHD.
ARCHITECT :
NRY ARCHITECTS SDN. BHD.
GROUND FLOOR
GROUND FLOOR
GROUND FLOOR
INTERIOR DESIGN CONSULTANT : NINEPLUS INTERIOR DESIGN (M) SDN BHD
RM399.00
RM35.00
RM7.90
QUANTITY SURVEYOR : SANG QS CONSULT
DATE B1-2-9, BLOCK B1,SOLARIS 15TH FLOOR, MENARA TEO CHEW, DUTAMAS,NO.1, JALAN DUTAMAS NO. 1, JALAN LUMUT 50400 KUALA 1,KUALA LUMPUR,50480 ,MALAYSIA. LUMPUR, MALAYSIA. 03-6411 6411 03-4043 1348 info@sportswork.net nry.com.my
C-11-4, Level 4, Jalan 3/144a, Medan Connaught, 56000 Kuala Lumpur, Wilayah Persekutuan Kuala Lumpur. +6012-323 3282 info@9plusinterior.com
22C, Jalan SS 19/1d, Ss 19, 47500 Subang Jaya, Selangor. 03-5613 5796 sang@sangqs.com
6
JLL ELECTRICAL SDN BHD A-G-3A, Kuchai Exchange, 43, Jalan Kuchai Maju 13, 58200 Kuala Lumpur, Malaysia. TEL: 03-7987 1266
1
ELUXE LIGHTING SDN. BHD. K03-10-08, UOA Business Park, No.1 , Jalan Pengaturcara U1/51A, 40150 Shah Alam, Selangor,Darul Ehsan,Malaysia. TEL: + (60) 0109784868
8
KAISON @ SUNWAY PYRAMID LG2.17 & LG2.18, Level LG2 Sunway Pyramid Shopping Mall, No. 3, Jalan PJS 11/15, Bandar Sunway, 47500 Petaling Jaya, Selangor. TEL: 03-5611 9052
PROJECT TITLE :
DRAWING TITLE : SCHEDULE OF FURNITURE , FITTINGS & EQUIPMENTS 7 2ND FLOOR OFFICE LEVEL
PROPOSE INTERIOR DESIGN AT NO.1, JALAN TAYLORS, 47500 ,SUBANG JAYA, SELANGOR. FOR SPORTSWORK
SCALE :
DATE :
NOT TO SCALE
15 NOVEMBER 2021
CHECKED BY :
DRAWN BY :
MS. NORJI
IVAN KHOO YUN FAN
DRAWING NO :
REV NO :
SW_DWD_IK_FFNE_05g
01
LEGEND:
1
2
3
4
5
6
CEILING SYM.
5500
5500
FINISHES -
CTX EXISTING TO BE REMAIN
29600 550
DESCRIPTION
5500
5500
5500
550
CH= ±5400MM CTX
TO CONTRUCT AND INSTALL CT1 18MM (THK) ROUND WIRE MESH CEILING PANEL W/ LIGHTING FIXTURES TO CONTRUCT AND INSTALL CT2 17MM(THK) TIMBER BATTEN CEILING
M-1
-
FIXTURES
R800
1
430
12
5430
11
5
R610
8 7
R610
3660
1
3
DL1
DL1
DL1
DL1
DL1
DL1
DL1
DL1
DL1 DL1
ELECTRICAL RISE 4 m²
OKU 4 m²
LIFT LOBBY 11 m²
1510
1510
H
840
MALE TOILET 12 m² DL1
1510
1
1
R610
DL1
1
2550
CLUB GATHER 15 m²
1020
R610
R610
DL1
CO-WORKING AREA #RIDE 28 m²
W-F 1430
3660
R610
3660
DL1 1
R610
DL1
R610
3660
1
CTX CH= ±5400MM
2 2 1
SECURITY ALARM
2
SMOKE DETECTOR
3
COMBINED HEAT DETECTOR AND FIRE ALARM SOUNDER
3 16
WIFI ROUTER
4
DESCRIPTION
NOS.
ADJUSTABLE 12W DOWN LIGHT
30
NEW PENDANT LIGHTING
19
NOTE: ALL LIGHTING POSITION AND HT FROM FLOOR LEVEL TO BE ADVISED BY LIGHTING SPECIALIST
DL1
DL1
1430
DL1
DL1
1430
5430
DL1
AC CONTROL SENSOR
SYM.
150MM(D)X110MM(H) ROUND LED DOWNLIGHT
DL1
1430 DL1
DL1
CT2 1
D
1430
DL1
UP
1
DL1
UP
1
EVERY STEP! 10 m²
5430
4
DL1
R610
3660
1
5430 UP
MEET-UP 6 m²
A 410 3660
1
DL1
AC A
DL1
R610
3660
H
R800
1430
1
ALL-EVENT 18 m²
W-F
DL1
1380
DL1
W-F
CH= ±4800MM CT1
880
A
MEETING AREA 16 m²
R610
2000
DL1
DL1
FEMALE TOILET 12 m² 350
C
DL1
1290
DL1
DL1
1510
1290
DL1
H DL1
1
AV SPEAKER RECESSED
LIGHTING
1070
1510
DL1
EMERGENCY EXIT SIGN
FIRE SPRINKLER HEAD
CH= ±2400MM CTX DL1
990
1920
DL1
R610
R800
800
H
SA
R800
CO-WORKING AREA #SWING 14 m²
2900
800
UP
NOS.
EXIT LIGHT (CEILING MOUNTED) EMERGENCY LIGHT RECESSED
1
1
DESCRIPTION
1
1000
BROADCAST STUDIO 10 m² 1510
DL1
4000
A AC
R610
2
DL1
RCP L2
R800
R610
3660
1
1510
6
1000
DL1
DL1
A
490
R800
4
12
9
DL1
5200
620
5
11
990
R800
DL1
1430 DL1
A
1430 DL1
DL1
SA
17MM(THK) TIMBER BATTEN CEILING
TOWER A- 2ND FLOOR LEVEL : REFLECTED CEILING PLAN SCALE 1:100
NOTE: THIS DRAWING IS COPYRIGHTED. THE AUTHORIZED USER IS TO CHECK ALL DIMENSIONS ON SITE. ONLY FIGURED DIMENSIONS ARE TO BE WORKED ON. DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO PARTNERSHIP BEFORE PROCEEDING.
DESCRIPTION
6
10
5430
10
3 4
W-F
15200
7 8 9
13
AC COACH LINKER 20 m²
NO.
R610 1
GAMIFY TRAINING AREA 68 m² 5430
1510
4000
1 2
3660
1
DL1
1
B
R610
3660
2970
840
1510
R800
R610
2460
DOWN
SYM.
SA
A
1130
A
1680
W-F
CT1 CH= ±4800MM
CLIENT : SPORTSWORK GROUP SDN. BHD.
ARCHITECT :
NRY ARCHITECTS SDN. BHD.
INTERIOR DESIGN CONSULTANT : NINEPLUS INTERIOR DESIGN (M) SDN BHD
QUANTITY SURVEYOR : SANG QS CONSULT
DATE B1-2-9, BLOCK B1,SOLARIS 15TH FLOOR, MENARA TEO CHEW, DUTAMAS,NO.1, JALAN DUTAMAS NO. 1, JALAN LUMUT 50400 KUALA 1,KUALA LUMPUR,50480 ,MALAYSIA. LUMPUR, MALAYSIA. 03-6411 6411 03-4043 1348 info@sportswork.net nry.com.my
C-11-4, Level 4, Jalan 3/144a, Medan Connaught, 56000 Kuala Lumpur, Wilayah Persekutuan Kuala Lumpur. +6012-323 3282 info@9plusinterior.com
22C, Jalan SS 19/1d, Ss 19, 47500 Subang Jaya, Selangor. 03-5613 5796 sang@sangqs.com
PROJECT TITLE :
DRAWING TITLE : REFLECTED CEILING PLAN 2ND FLOOR OFFICE LEVEL
PROPOSE INTERIOR DESIGN AT NO.1, JALAN TAYLORS, 47500 ,SUBANG JAYA, SELANGOR. FOR SPORTSWORK
SCALE :
DATE :
1:100
2 NOVEMBER 2021
CHECKED BY :
DRAWN BY :
MS. NORJI
IVAN KHOO YUN FAN
DRAWING NO :
REV NO :
SW_DWD_IK_RCP_06
01
LEGEND:
1
2
4
3
5
6
SYM.
QTY.
DESCRIPTION
POWER & DATA
29600 5500
5500
5500
5500
H1
H1
S1 S2 410
3400
DOWN
S1
S1
3860
7
1
4200
4000
B
DL1
SB1
12
8 6
7
1
DL1
DL1 DL1
DL1
DL1
DL1
DL1
4790
5200
15200
DL1
DL1
DL1
DL1 H1
DL1
DL1
DL1
4000
SB1
DL1
A
1
1
DL1
17
DOUBLE GANG WALL SOCKET @ 1200MM ABOVE FLOOR LEVEL
2
DATA POINT OUTLET @ 300MM HT. UNLESS OTHERWISE SPECIFIED.
4
AV CABLE ( HDML / VGA / AUDIO PORT) @ 300MM HT. UNLESS OTHERWISE SPECIFIED.
1
TELEPHONE POINT OUTLET @ 300 HT.UNLESS OTHERWISE SPECIFIED.
1
NEW SERVICE/FLOOR BOX CONSIST OF: - 2 POWER OUTLETS -1 DATA OUTLETS
12
DL1
ALL-EVENT 18 m²
1
SB1
1
SB1
SB1
DL1
DL1
CO-WORKING AREA #RIDE 28 m² DL1
DL1
7
DISTRIBUTION BOARD
1
OUTLET TO BE MOUNTED ON WALL @ 1200MM HT OUTLET TO BE MOUNTED ON WORKSTATION / TABLE
ADJUSTABLE 12W DOWN LIGHT
30
NEW PENDANT LIGHTING
19
150MM(D)X110MM(H) ROUND LED DOWNLIGHT
W DL1
DL1
W 1
LIGHTING POINT FOR JOINERY
NOTE: ALL LIGHTING POSITION AND HT FROM FLOOR LEVEL TO BE ADVISED BY LIGHTING SPECIALIST
DL1
W
UP
1
SINGLE GANG WALL SOCKET @ 1200MM ABOVE FLOOR LEVEL
DL1
S1
3610
EVERY STEP! 10 m²
SB1
1
CEILING / LIGHTING
W
S1
S1
UP
MEET-UP 6 m²
DL1
H1
CLUB GATHER 15 m²
3 GANG 1 WAY LIGHT SWITCH
H1
5380 1
1
A
1
DL1
DL1
DL1
DL1
550
DL1
S1
S1 H1
OUTLET TO BE MOUNTED ON WORKSTATION / TABLE
H1
TOWER A- 2ND FLOOR LEVEL : LIGHTING & ELECTRICAL LAYOUT PLAN SCALE 1:100
NOTE: THIS DRAWING IS COPYRIGHTED. THE AUTHORIZED USER IS TO CHECK ALL DIMENSIONS ON SITE. ONLY FIGURED DIMENSIONS ARE TO BE WORKED ON. DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO PARTNERSHIP BEFORE PROCEEDING.
DESCRIPTION
MEETING AREA 16 m²
H1
SB1
W H1
UP
DL1
H1
S1
5
DL1
LIFT LOBBY 11 m²
DL1
DL1
NO.
S1 S2 1
FEMALE TOILET 12 m²
S1 DL1
DL1
DL1
H1
UP
DL1
LEP L2
1
DL1
DL1
2 GANG 1 WAY LIGHT SWITCH
SOCKET HEIGHT
DL1
ELECTRICAL RISE 4 m²
OKU 4 m²
DL1
DL1
SB1
SB1
DL1
D
CO-WORKING AREA #SWING 14 m²
H1
DL1
SB1
1
1
S1
H1
C
1
MALE TOILET 12 m²
DL1
W
1 13
SB1
GAMIFY TRAINING AREA 68 m²
9 5
3 2
11
10
4
DL1
BROADCAST STUDIO 10 m²
UP S1 S2
11
3
COACH LINKER 20 m²
4
10
12
2
SB1
5
9
1 1
1
6
8
1
DL1
8
5790
4210
A
550
1720
5500
3250
550
1 GANG 1 WAY LIGHT SWITCH
CLIENT : SPORTSWORK GROUP SDN. BHD.
ARCHITECT :
NRY ARCHITECTS SDN. BHD.
INTERIOR DESIGN CONSULTANT : NINEPLUS INTERIOR DESIGN (M) SDN BHD
QUANTITY SURVEYOR : SANG QS CONSULT
PROJECT TITLE :
PROPOSE INTERIOR DESIGN AT NO.1, JALAN TAYLORS, 47500 ,SUBANG JAYA, SELANGOR. FOR SPORTSWORK
DATE B1-2-9, BLOCK B1,SOLARIS 15TH FLOOR, MENARA TEO CHEW, DUTAMAS,NO.1, JALAN DUTAMAS NO. 1, JALAN LUMUT 50400 KUALA 1,KUALA LUMPUR,50480 ,MALAYSIA. LUMPUR, MALAYSIA. 03-6411 6411 03-4043 1348 info@sportswork.net nry.com.my
C-11-4, Level 4, Jalan 3/144a, Medan Connaught, 56000 Kuala Lumpur, Wilayah Persekutuan Kuala Lumpur. +6012-323 3282 info@9plusinterior.com
22C, Jalan SS 19/1d, Ss 19, 47500 Subang Jaya, Selangor. 03-5613 5796 sang@sangqs.com
DRAWING TITLE : LIGHTING & ELECTRICAL PLAN 2ND FLOOR OFFICE LEVEL SCALE :
DATE :
1:100
2 NOVEMBER 2021
CHECKED BY :
DRAWN BY :
MS. NORJI
IVAN KHOO YUN FAN
DRAWING NO :
REV NO :
SW_DWD_IK_LEP_07
01
550
3
2
1 5500
5500
28600 5500
4
5 5500
NOTE:
6 5500
THIS DRAWING IS COPYRIGHTED. THE AUTHORIZED USER IS TO CHECK ALL DIMENSIONS ON SITE. ONLY FIGURED DIMENSIONS ARE TO BE WORKED ON. DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO PARTNERSHIP BEFORE PROCEEDING.
550
5500
ROOF LEVEL
NO.
DATE
DESCRIPTION
1000MM(H) STAINLESS STEEL SAFETY RAILING W/ 12MM(THK) TEMPERED GLASS PANEL
4TH FLOOR
5500
CLIENT :
SPORTSWORK GROUP SDN. BHD. B1-2-9, BLOCK B1,SOLARIS DUTAMAS,NO.1, JALAN DUTAMAS 1,KUALA LUMPUR,50480 ,MALAYSIA.
(TEL) 03-6411 6411 info@sportswork.net 2100MM(H) X 1800MM(W) DOUBLE SWING DOOR
ARCHITECT :
15TH FLOOR, MENARA TEO CHEW, NO. 1, JALAN LUMUT 50400 KUALA LUMPUR, MALAYSIA.
500
3RD FLOOR CEILING LEVEL FCL 31.70 EXPOSED CEILING 800MM(D) ALUMINUM LED PENDANT LIGHT 2400
NRY ARCHITECTS SDN. BHD.
(TEL) 03-4043 1348 nry.com.my
CURVY PERFORATED MESH PARTITION WALL
200
5500
100MM(D) COPPER TUBE WALL DESIGN MEZZANINE FLOOR 300MM(THK.) STEEL BEAM
FFL 29.70
28000
2400MM(H)X1200(W) CURTAIN WALL
INTERIOR NINEPLUS INTERIOR CONSULTANT : DESIGN (M) SDN BHD
C-11-4, LEVEL 4, JALAN 3/144A, MEDAN CONNAUGHT, 56000 KUALA LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR.
2400
2300MM(H)X30MM(THK) SLIDING ACOUSTIC SCREEN 350MM(W) X 750MM(H) BIKE STOOL 2160MM(L) X 2160MM(W) X400MM(H) PLUSH FABRIC PEBBLE MODULAR SOFA
2ND FLOOR FFL 25.60
(TEL) +6012-323 3282 info@9plusinterior.com
6MM(THK) POLYPROPYLENE PATTERNED CARPET
QUANTITY SURVEYOR : SANG QS CONSULT
5500
22C, JALAN SS 19/1D, SS 19, 47500 SUBANG JAYA, SELANGOR. (TEL) 03-5613 5796
sang@sangqs.com 5000MM(H)X1200(W) CURTAIN WALL
PROJECT TITLE : 1ST FLOOR
PROPOSE INTERIOR DESIGN AT NO.1, JALAN TAYLORS, 47500 ,SUBANG JAYA, SELANGOR. FOR SPORTSWORK
6000
DRAWING TITLE : TOWER A SECTION A-A 2ND FLOOR OFFICE LEVEL
SCALE :
DATE :
1:75
9 NOVEMBER 2021
CHECKED BY :
DRAWN BY :
MS. NORJI
IVAN KHOO YUN FAN
GROUND FLOOR
SC L2
TOWER A-SECTION A-A SCALE 1:75
DRAWING NO :
REV NO :
SW_DWD_IK_SC_08
01
1320
1200
1370
X
870
1
3630
450MM(L) X 500MM(W) YELLOW ABS PLASTIC OFFICE SWING
1400
1000MM(D) X 50MM(THK.) ROUND MESH PANEL C/W LIGHTING FIXTURES
900MM(L) WOOL CYLINDER EXERCISE SOFA
860
50MM THK. STEEL SUPPOPTING FRAME W/ EPOXY COATING
X PL WS NOTE: THIS DRAWING IS COPYRIGHTED. THE AUTHORIZED USER IS TO CHECK ALL DIMENSIONS ON SITE. ONLY FIGURED DIMENSIONS ARE TO BE WORKED ON. DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO PARTNERSHIP BEFORE PROCEEDING. NO.
DESCRIPTION
NOTE: FIVE STAFFS WORKSTATION AT CO-WORKING ZONE. WORKSTATION IS DESIGNED TO BE EXTENDABLE DEPENDS ON THE DEMANDS OF THE OFFICE USERS.
WORKSTATION LAYOUT PLAN SCALE 1:20
CLIENT : SPORTSWORK GROUP SDN. BHD.
ARCHITECT :
NRY ARCHITECTS SDN. BHD.
INTERIOR DESIGN CONSULTANT : NINEPLUS INTERIOR DESIGN (M) SDN BHD
QUANTITY SURVEYOR : SANG QS CONSULT
PROJECT TITLE :
PROPOSE INTERIOR DESIGN AT NO.1, JALAN TAYLORS, 47500 ,SUBANG JAYA, SELANGOR. FOR SPORTSWORK
DATE B1-2-9, BLOCK B1,SOLARIS 15TH FLOOR, MENARA TEO CHEW, DUTAMAS,NO.1, JALAN DUTAMAS NO. 1, JALAN LUMUT 50400 KUALA 1,KUALA LUMPUR,50480 ,MALAYSIA. LUMPUR, MALAYSIA. 03-6411 6411 03-4043 1348 info@sportswork.net nry.com.my
C-11-4, Level 4, Jalan 3/144a, Medan Connaught, 56000 Kuala Lumpur, Wilayah Persekutuan Kuala Lumpur. +6012-323 3282 info@9plusinterior.com
22C, Jalan SS 19/1d, Ss 19, 47500 Subang Jaya, Selangor. 03-5613 5796 sang@sangqs.com
DRAWING TITLE : WORKSTATION LAYOUT PLAN 2ND FLOOR OFFICE LEVEL SCALE :
DATE :
1:20
9 NOVEMBER 2021
CHECKED BY :
DRAWN BY :
MS. NORJI
IVAN KHOO YUN FAN
DRAWING NO :
REV NO :
SW_DWD_IK_DT_9a
01
CL 5500MM
3950
270
1350
1000MM(D) X 50MM(THK.) ROUND MESH PANEL C/W LIGHTING FIXTURES
1110
3640
2300MM(H) X 850MM(W) ACOUSTIC SCREEN C/W THERMOSETTING RESIN
390
50MM(D) STAINLESS STEEL SUPPOPTING FRAME W/ EPOXY COATING FINISHES
520
900MM(L) WOOL CYLINDER EXERCISE SOFA
FL EL 1 NOTE: THIS DRAWING IS COPYRIGHTED. THE AUTHORIZED USER IS TO CHECK ALL DIMENSIONS ON SITE. ONLY FIGURED DIMENSIONS ARE TO BE WORKED ON. DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO PARTNERSHIP BEFORE PROCEEDING. NO.
DESCRIPTION
ELEVATION 1 SCALE 1:20 CLIENT : SPORTSWORK GROUP SDN. BHD.
ARCHITECT :
NRY ARCHITECTS SDN. BHD.
INTERIOR DESIGN CONSULTANT : NINEPLUS INTERIOR DESIGN (M) SDN BHD
QUANTITY SURVEYOR : SANG QS CONSULT
PROJECT TITLE :
PROPOSE INTERIOR DESIGN AT NO.1, JALAN TAYLORS, 47500 ,SUBANG JAYA, SELANGOR. FOR SPORTSWORK
DATE B1-2-9, BLOCK B1,SOLARIS 15TH FLOOR, MENARA TEO CHEW, DUTAMAS,NO.1, JALAN DUTAMAS NO. 1, JALAN LUMUT 50400 KUALA 1,KUALA LUMPUR,50480 ,MALAYSIA. LUMPUR, MALAYSIA. 03-6411 6411 03-4043 1348 info@sportswork.net nry.com.my
C-11-4, Level 4, Jalan 3/144a, Medan Connaught, 56000 Kuala Lumpur, Wilayah Persekutuan Kuala Lumpur. +6012-323 3282 info@9plusinterior.com
22C, Jalan SS 19/1d, Ss 19, 47500 Subang Jaya, Selangor. 03-5613 5796 sang@sangqs.com
DRAWING TITLE : WORKSTATION ELEVATION 2ND FLOOR OFFICE LEVEL SCALE :
DATE :
1:20
15 NOVEMBER 2021
CHECKED BY :
DRAWN BY :
MS. NORJI
IVAN KHOO YUN FAN
DRAWING NO :
REV NO :
SW_DWD_IK_DT_9b
01
CL 5500MM
3670 1410
2260
1160
1000MM(D) X 50MM(THK.) ROUND MESH PANEL C/W LIGHTING FIXTURES
270
2300MM(H) X 850MM(W) ACOUSTIC SCREEN C/W THERMOSETTING RESIN
990
3700
DET. 2'
770
260
50MM (D) STAINLESS STEEL SUPPOPTING FRAME W/ EPOXY COATING
3500MM(L) X 3000MM(W) X 50MM(H) GALVANIZED STEEL GRATING IN BRIGHT FINISH DET. 1'
FL SC X NOTE: THIS DRAWING IS COPYRIGHTED. THE AUTHORIZED USER IS TO CHECK ALL DIMENSIONS ON SITE. ONLY FIGURED DIMENSIONS ARE TO BE WORKED ON. DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO PARTNERSHIP BEFORE PROCEEDING. NO.
DESCRIPTION
CLIENT : SPORTSWORK GROUP SDN. BHD.
SECTION X-X SCALE 1:20 ARCHITECT :
NRY ARCHITECTS SDN. BHD.
INTERIOR DESIGN CONSULTANT : NINEPLUS INTERIOR DESIGN (M) SDN BHD
QUANTITY SURVEYOR : SANG QS CONSULT
PROJECT TITLE :
PROPOSE INTERIOR DESIGN AT NO.1, JALAN TAYLORS, 47500 ,SUBANG JAYA, SELANGOR. FOR SPORTSWORK
DATE B1-2-9, BLOCK B1,SOLARIS 15TH FLOOR, MENARA TEO CHEW, DUTAMAS,NO.1, JALAN DUTAMAS NO. 1, JALAN LUMUT 50400 KUALA 1,KUALA LUMPUR,50480 ,MALAYSIA. LUMPUR, MALAYSIA. 03-6411 6411 03-4043 1348 info@sportswork.net nry.com.my
C-11-4, Level 4, Jalan 3/144a, Medan Connaught, 56000 Kuala Lumpur, Wilayah Persekutuan Kuala Lumpur. +6012-323 3282 info@9plusinterior.com
22C, Jalan SS 19/1d, Ss 19, 47500 Subang Jaya, Selangor. 03-5613 5796 sang@sangqs.com
DRAWING TITLE : WORKSTATION SECTION 2ND FLOOR OFFICE LEVEL SCALE :
DATE :
1:20
9 NOVEMBER 2021
CHECKED BY :
DRAWN BY :
MS. NORJI
IVAN KHOO YUN FAN
DRAWING NO :
REV NO :
SW_DWD_IK_DT_9c
01
30
140 70
150 10
40
70
70
70MM(D) STAINLESS STEEL HOLLOW TUBE
70MM(D) STAINLESS STEEL HOLLOW TUBE
30
85MM(D) CUSTOMIZED ALUMINUM TEE JOINT TUBE CONNECTOR
3500MM(L) X 3000MM(W) X 50MM(H) GALVANIZED STEEL GRATING WITH BRIGHT FINISH
DT 1
THIS DRAWING IS COPYRIGHTED. THE AUTHORIZED USER IS TO CHECK ALL DIMENSIONS ON SITE. ONLY FIGURED DIMENSIONS ARE TO BE WORKED ON. DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO PARTNERSHIP BEFORE PROCEEDING.
DESCRIPTION
DT 2
DETAIL : 1' SCALE 1:2
NOTE:
NO.
110MM(L) FLAT HEAD COUNTERSUNK BOLTS MACHINE SCREWS
50
20
5MM(D) ALUMINUM BLIND RIVET WITH 14MM(D) STAINLESS STEEL MANDRILL ATTACHMENT HEAD
50
140
70
140MM(L) ZINC PLATED STEEL HEX SCREW
130
50
5MM(THK.) GALVANIZED THREADED INSTALLATION PLATE
CLIENT : SPORTSWORK GROUP SDN. BHD.
ARCHITECT :
NRY ARCHITECTS SDN. BHD.
INTERIOR DESIGN CONSULTANT : NINEPLUS INTERIOR DESIGN (M) SDN BHD
QUANTITY SURVEYOR : SANG QS CONSULT
DETAIL : 2' SCALE 1:2
PROJECT TITLE :
PROPOSE INTERIOR DESIGN AT NO.1, JALAN TAYLORS, 47500 ,SUBANG JAYA, SELANGOR. FOR SPORTSWORK
DATE B1-2-9, BLOCK B1,SOLARIS 15TH FLOOR, MENARA TEO CHEW, DUTAMAS,NO.1, JALAN DUTAMAS NO. 1, JALAN LUMUT 50400 KUALA 1,KUALA LUMPUR,50480 ,MALAYSIA. LUMPUR, MALAYSIA. 03-6411 6411 03-4043 1348 info@sportswork.net nry.com.my
C-11-4, Level 4, Jalan 3/144a, Medan Connaught, 56000 Kuala Lumpur, Wilayah Persekutuan Kuala Lumpur. +6012-323 3282 info@9plusinterior.com
22C, Jalan SS 19/1d, Ss 19, 47500 Subang Jaya, Selangor. 03-5613 5796 sang@sangqs.com
DRAWING TITLE : WORKSTATION BLOW-UP DETAILS 2ND FLOOR OFFICE LEVEL SCALE :
DATE :
1:2
15 NOVEMBER 2021
CHECKED BY :
DRAWN BY :
MS. NORJI
IVAN KHOO YUN FAN
DRAWING NO :
REV NO :
SW_DWD_IK_DT_9d
01
LT-01
BF-02 CP-01
WP-01 BF-04
BF-01 FF-02 LF-01
BF-03
FF-01
ST-01
800MM(D)X50MM(THK) ALUMINUM ROUND LED PENDANT LIGHT W/ STEEL MESH
2300MM(H) X 30MM(THK) FIXED ACOUSTIC SCREEN W/ STEEL FRAME
4800MM(L) X 100MM(W) X 50MM(H) TIMBER BATTEN CEILING
2300MM(H) X 30MM(THK) SLIDING ACOUSTIC SCREEN W/ ALUMINUM TRACK 2 COATS YELLOW SEMI GLOSSY 900MM(L) DESIGNER CYLINDER EXERCISE SOFA IN WOOL FINISH
200MM(W) X 200MM(L) X 30MM(THK) SEQUOIA WOOD LOOK TILES 450MM(L) X 450MM(W) X 550MM(H) BIKE STOOL
1800MM(H) OFFICE SWING W/ STEEL SWING SET BRACKET
500MM(L) X 500MM(W) X 6MM (H) POLYPROPYLENE PATTERNED CARPET
50MM DIAMETER HOLLOW STEEL TUBE
SPORTSWORK GROUP SDN. BHD.
SPORTSWORK GROUP SDN. BHD.
TERMS & CONDITIONS
BILL OF QUANTITIES
SPORTSWORK GROUP SDN. BHD.
QUOTATION DATE :19TH NOVEMBER 2021 QUOTE NO :MDT_DWD_IK_BQ_10 TERMS :CHEQUE/CASH
B1-2-9, BLOCK B1,SOLARIS DUTAMAS,NO.1, JALAN DUTAMAS 1,KUALA LUMPUR,50480 ,MALAYSIA.
1. 2. 3. 4. 5.
ATTENTION : RENOVATION WORKS FOR SPORTSWORK GROUP SDN. BHD. BILL OF QUANTITIES QTY.
UNIT
TILING WORK FLOOR a to supply material & labour to lay 500MM(L) X 500MM(W) X 6MM (THK) POLYPROPYLENE PATTERNED CARPET TILE @Co-working zone Code: FF-01 , Area:62m²
26
PCS
b to supply material & labour to 200MM(L) X 200MM(W) X 30MM(THK) SEQUOIA
18
PCS
NO. 1.
DESCRIPTION
WOOD LOOK TILES @meeting area Code: FF-02, Area:15m² 2.
RATE (RM)
TOTAL (RM)
6.
PAINTING WORK
a to supply material & labour to paint 2 COATS YELLOW SEMI GLOSSY @Internal side of corrugated metal partition wall Code: WP-01 3.
4.
METAL WORK 3.1 SUPPORTING FRAME a to supply material & labour to install 2500MM(L) X 50MM (D) HOLLOW STEEL TUBE @Co-working zone Code: ST-01 , Area:14m²
2
LITRE
16
BAR
18
NOS
7.
8.
CEILING WORK
a to supply material & labour to install 4800MM(L) X 100MM(W) X 50MM(H) TIMBER BATTEN CEILING @Co-working zone Code: CP-01 , Area: Approx.20m²
9. 5.
BUILT-IN FURNITURE a to supply and install 2300MM(H) X 30MM(THK) SLIDING ACOUSTIC SCREEN W/ ALUMINUM TRACK @meeting zone Code: BF-01, Area: Approx.8m²
b to supply and install 2300MM(H) X 30MM(THK) FIXED ACOUSTIC SCREEN W/
12
NOS
2
NOS
STEEL FRAME @Co-working zone Code: BF-02, Area: Approx.6m²
c to supply and install 1800MM(H) OFFICE SWING W/ STEEL SWING SET
10.
3
SET
2
NOS
BRACKET @Co-working zone Code: BF-03, Area: Approx.14m²
d to supply and install 900MM(L) DESIGNER CYLINDER EXERCISE SOFA IN
11.
Validity: 14 days Period of completed : 60 days (refer of down payment upon comfirmation of order) All Dimension subject to Final site measurement. Variation Order : Any alteration not specified in the quotation will be issued under variation order follow with an invoice Variation order ( VO ). Payment Terms:-THE CONTRACT SUM RM Percentage 30% = RM Stage I Upon confirmation of project/service 20% = RM Stage I Progress Claim (Installation of fixtures & fittings) 20% = RM Stage III Progress Claim (Completion of fixtures & fittings) - 11001 10% = RM Stage V final payment full completion of all works) -Services/warks shall commence upon receipt of payment of each phase except for final phase.Time frame of work that has been agreed by both. -All outstanding amounts must be paid within ten (10) working days after the handover of site (exclude V.O. period). Shall there be any delay of the handover site, payment must still be made within (10) working days of the originally contemplated handover date confirmed by the Client & NINEPLUS Interior Company. -NINEPLUS Interior Company do not hold any responsibilities in delay of work from the agreed Time frame that is resulted by payment issues. -Payment not made within above mentioned period will carry interest at the rate of 2% per month (30 days) until full payment is made. -Cheque should be crossed A/C Payee & Made Payable to NINEPLUS Interior Company. -NINEPLUS Interior Company shall not in any circumstances or for any reason whatsoever be liable for any losses, damages, cost, expenses including, without limitation, direct, indirect,special or consequential damages or economic losses arising from any such failure to perform. Design/Works/Service Disclaimer NINEPLUS Interior Company cannot be held responsible for designs/works/service that may later be undesirable or cause inconvenience. The Client understands that all designer/contractor interprets the Client's requirements and wishes. however, any design/works that are not done according to agreed as per quoted shall be rectified accordingly by NINEPLUS Interior Company. Project Access -Client will provide NINEPLUS Interior Company with access to the project and all information that may be required to complete the project. -Failure to do so by the Client provides NINEPLUS Interior Company the right to terminate service ( with a written notice ) and collect outstanding balances. Termination of Service NINEPLUS Interior Company has the right to terminate or suspend All works/Services, upon written notice, if the Client falls to make payments/default in accordance with the mentioned terms and conditions. -Termination shall be without prejudice to any and all other rights and remedies of NINEPLUS Interior Company and Client shall remain liable for all. -Within five (5) working days of termination of our service for any reason, NINEPLUS Interior Company shall submit to Client an itemized invoice for any fees or expenses accrued under this quotation. The client, upon payment of accrued amounts so invoiced, shall thereafter have no further liability or obligations to NINEPLUS Interior Company whatsoever for any further fees or expenses arising hereunder. Project Time Frame & Fees for extra service Reasonable time frame for drawings are to be discussed & agreed by both party NINEPLUS Interior Company. Estimated time frame for entire project's frame inclusive of revision period will be a maximum of TWO (2) MONTHS starts from date of appointment. If project exceed estimated time frame, an additional minimum fee of RM150 per month will be charge, as consultation fees only, excluded reimbursement claim &site visit charges. Subject to the project & remaining job-scope. Site Visit. Inspection & Travelling -Site visit or inspection services that requires NINEPLUS Interior Company to travel by air (overseas, Sabah & Sarawak) are subject to claim all. Acknowledgement of Quoted Fees, Terms & Conditions -Upon receiving payment according to the percentage stated above will acknowledge that you have read & agreed on our scope of design/works/services,fees,terms & conditions. This quotation shall be treated as a contract legally binding once being signed. -English language/wordings shall prevail and be used as contract terms shall any discrepancies arise due to translations.
WOOL FINISH @Co-working zone Code: BF-04 , Area: Approx.5m² Issue By 6.
7.
LOOSE FURNITURE a 450MM(L) X 450MM(W) X 550MM(H) BIKE STOOL (adjustable seat height) @meeting zone & coach linker Code: LF-01 LIGHTING a 800MM(D)X50MM(THK) ALUMINUM ROUND LED PENDANT LIGHT Code: LT-01
10
NOS COMPANY NAME
20
NOS
NINEPLUS Interior Company DIRECTOR
Acknowledge & Agreed by, ___________________________ Signature with I.C number
REFLECTION The
interior
spaces
of
my
designed
level
comply
with
the
UBBL
1984.
The
UBBL
pertaining to fire safety requirements, such as By-Law 172 (emergency exit signs), ByLaw
228
(sprinker
communication
valves),
system),
By-Law
have
been
237
(fire
alarms),
implemented
in
the
and
By-Law
office
239
(Voice
space.Besides,
my
designed level also complied with By-Law 39 (natural lighting and ventilation) that is under Part III of the UBBL. It required every room designed, adapted, or used for business to be provided with natural lighting and natural ventilation.
The
materials
that
are
used
in
the
space
are
concrete,
brick,
metal,
copper,
aluminum, and timber-look tiles. These materials are the material that represents the concept of industrial style interior design. Timber look tiles are mostly used for the platform and flooring in the office area.
Furthermore, greenery plants are vital to have in the office area as they create a pleasant environment and add a harmonious feel to the workspace. Interior plants
03
provide client with a natural and beautiful addition to their interior while also helping employees'
general
well-being.
In
my
research,
our
cities
and
workplaces
are
frequently structured in a way that isolates us from nature. Incorporating plants into the design of our offices may boost pleasure, creativity, and productivity. It also refreshes the office's air conditioning and creates a sustainable office atmosphere.
INTRODUCTION In this project, I am required to do my research on existing
precedent
design/coworking extract
the
studies
space,
precedent
related
recognise
the
study's
to
office
layout,
and
Schedule
of
Accommodation (SOA) and FF&E. It also introduces students
to
the
UBBL
and/or
fire
regulations,
which
must be considered while planning the area. The aim is of this project is to understand layout design in relation to UBBL and/or Fire requirements. Based on the chosen
Assignment
precedent study, I will create a set of as-built drawings that includes a plan, internal elevation, section, SOA, FF&E,
and
an
analysis
of
UBBL
application.
PRECEDENT STUDIES : A BUREAU
and
material
Bachelor of Art (HONS) in Interior Architecture DETAILING AND WORKING DRAWINGS [IDS60804]
Assignment 2 :
Precedent studies – A Bureau Lecturer: Ms. Aziah Hassan
Name : Ivan Khoo Yun Fan Student ID : 0344608
REVISION TRACKING DRAWING NO.
SHEET NAME
CURRENT REVISION
DATE
DESCRIPTION
ISSUED
1 -
PRECEDENT STUDIES - INDIVIDUAL
1
11/10/2021
ISSUED FOR CONSTRUCTION
NO
-
PRECEDENT STUDIES - GROUP
1
11/10/2021
ISSUED FOR CONSTRUCTION
NO
CS_DWD_IK_FLP_01
FURNITURE LAYOUT PLAN
3
11/10/2021
ISSUED FOR CONSTRUCTION
NO
CS_DWD_IK_SOA_02
SCHEDULE OF ACCOMODATION
3
11/10/2021
ISSUED FOR CONSTRUCTION
NO
CS_DWD_IK_S01_03
OVERALL SECTION
3
11/10/2021
ISSUED FOR CONSTRUCTION
NO
CS_DWD_IK_S02_04
PARTIAL SECTION A
2
11/10/2021
ISSUED FOR CONSTRUCTION
NO
CS_DWD_IK_S03_05
PARTIAL SECTION B
2
11/10/2021
ISSUED FOR CONSTRUCTION
NO
CS_DWD_IK_B01_06
BESPOKE TABLE PLAN & FRONT ELEVATION
2
11/10/2021
ISSUED FOR CONSTRUCTION
NO
CS_DWD_IK_B02_07
BESPOKE TABLE RIGHT & LEFT ELEVATION
2
11/10/2021
ISSUED FOR CONSTRUCTION
NO
CS_DWD_IK_B03_08
BESPOKE TABLE DETAIL A & B
2
11/10/2021
ISSUED FOR CONSTRUCTION
NO
CS_DWD_IK_DWS_09 DOORS & WINDOWS SCHEDULE
3
11/10/2021
ISSUED FOR CONSTRUCTION
NO
CS_DWD_IK_SOF_10
3
11/10/2021
ISSUED FOR CONSTRUCTION
NO
CS_DWD_IK_UBBL_11a UBBL 1
2
11/10/2021
ISSUED FOR CONSTRUCTION
NO
CS_DWD_IK_UBBL_11b UBBL 2
2
11/10/2021
ISSUED FOR CONSTRUCTION
NO
CS_DWD_IK_UBBL_11c UBBL 3
2
11/10/2021
ISSUED FOR CONSTRUCTION
NO
CS_DWD_IK_UBBL_11d UBBL ANALYSIS REPORT
1
11/10/2021
ISSUED FOR CONSTRUCTION
NO
2
3
4
SCHEDULE OF FINISHES
5
CHANGES
1
2
4
3
5
6
40900
6850
17600
8600
7850
A SCREENING ROOM CONCRETE FLOORING 77m2
B MEETING ROOM #1 CONCRETE FLOORING 17m2
MEETING ROOM #2 CONCRETE FLOORING 17m2
PANTRY CONCRETE FLOORING 12m2
REGISTER AREA CONCRETE FLOORING 36m2
12450
17100
D2
D1
F1 CO-WORKING SPACE CONCRETE FLOORING 12m2
C W1
MAKER SPACE CONCRETE FLOORING 30m2
4650
PHOTOGRAPHY DARK ROOM CERAMIC TILES 32m2
VOID
CS_DWD_IK_BD_02 TEXTILE STUDIO CONCRETE FLOORING 60m2
Y
F2 PAINTING STUDIO
Y
UP
CONCRETE FLOORING 24m2 CERAMIC STUDIO CONCRETE FLOORING
W2
D3
43m2
D WOOD WORKSHOP CONCRETE FLOORING 12m2
KILN ROOM CONCRETE FLOORING 11m2
01 FURNITURE LAYOUT PLAN LP01
SCALE 1:125
DRAWING TITLE
NOTE
CLIENT
ARCHITECT
HUBBA-TO SUPERMACHINE STUDIO No .
Description
INTERIOR DESIGN CONSULTANT SUPERMACHINE STUDIO
QUANTITY SURVEYOR
PROJECT TITLE
SUPERMACHINE STUDIO
HUBBA-TO CO WORKING SPACE FURNITURE LAYOUT PLAN
Date
SCALE
PROPOSE RENOVATION FOR HUBBA-TO CO WORKING SPACE
CHECKED BY
3RD FL, HABITO MALL, SOI ON NUT 1/1, SUKHUMVIT 77 ROAD, ON NUT, PHRA KHANONG NUEA, WATTHANA, BANGKOK 10250, THAILAND . 3RD FL, HABITO MALL, SOI ON NUT 1/1 SUKHUMVIT 77 ROAD, ON NUT, PHRA KHANONG NUEA, WATTHANA, BANGKOK 10250, THAILAND
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
DATE
11 OCTOBER 2021
1:125 MS AZIAH
DRAWN BY
IVAN KHOO YUN FAN DRAWING NO
CS_DWD_IK_FLP_01
REV NO
03
5
6
4
3
2
1
40900 8000
7850 1450
1530
4870
1650
2030
2400 1760
1760
800 150
2100
15500 150
3850
4050
7150 450
3000
4150
450
1350
1150
1200
1200
1350
450
+ 56.00
1000
FFL
C1 EXPOSED CEILING
C1
PP03
B2
PP04
B2
PP04 B2
650
B2
B2 150MM (THK.) BRICK WALL W/ WHITE PAINT
1890
B2
12MM (THK.) DOUBLE GLAZING GLASS W/ ALUMINUM CURTAIN WALL FRAME
4000
B2
F2 20MM (THK.) CEMENT SCREED FINISHES
460
+ 56.00
F2
F2
F1
FFL
REFER TO CS_DWD_IK_S02_03
03
OVERALL SECTION
S01
SCALE 1:125
NOTE
CLIENT
REFER TO CS_DWD_IK_S03_04
ARCHITECT
HUBBA-TO No .
Description
SUPERMACHINE STUDIO
Date
INTERIOR DESIGN CONSULTANT SUPERMACHINE STUDIO
QUANTITY SURVEYOR
PROJECT TITLE
HUBBA-TO CO WORKING SPACE OVERALL SECTION
SUPERMACHINE STUDIO
SCALE
PROPOSE RENOVATION FOR HUBBA-TO CO WORKING SPACE
PHRA KHANONG NUEA, WATTHANA, BANGKOK 10250, THAILAND .
BANGKOK 10250, THAILAND
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
DATE
11 OCTOBER 2021
1:125 CHECKED BY
3RD FL, HABITO MALL, SOI ON NUT 1/1, SUKHUMVIT 77 ROAD, ON NUT,
3RD FL, HABITO MALL, SOI ON NUT 1/1 SUKHUMVIT 77 ROAD, ON NUT, PHRA KHANONG NUEA, WATTHANA,
DRAWING TITLE
MS AZIAH
DRAWN BY
IVAN KHOO YUN FAN DRAWING NO
CS_DWD_IK_S01_03
REV NO
03
5
6
4 22100
7850 1450
14250
1530
4870
1650
2030
1760
1760
800
2400
3850
+ 56.00
1000
FFL C1
B2
C1 EXPOSED CEILING
PP04
PP03 B2
+ 56.00 FFL
1890
F2 12MM (THK.) DOUBLE GLAZING GLASS W/ ALUMINUM CURTAIN WALL FRAME
460
4000
650
B2 150MM (THK.) BRICK WALL W/ WHITE PAINT
F2 20MM (THK.) CEMENT SCREED FINISHES
F1
04
PARTIAL SECTION A
S02
SCALE 1:75
DRAWING TITLE
NOTE
CLIENT
ARCHITECT
HUBBA-TO SUPERMACHINE STUDIO No .
Description
INTERIOR DESIGN CONSULTANT SUPERMACHINE STUDIO
QUANTITY SURVEYOR
PROJECT TITLE
SUPERMACHINE STUDIO
HUBBA-TO CO WORKING SPACE PARTIAL SECTION A
Date
SCALE
PROPOSE RENOVATION FOR HUBBA-TO CO WORKING SPACE
PHRA KHANONG NUEA, WATTHANA, BANGKOK 10250, THAILAND . 3RD FL, HABITO MALL, SOI ON NUT 1/1 SUKHUMVIT 77 ROAD, ON NUT, PHRA KHANONG NUEA, WATTHANA, BANGKOK 10250, THAILAND
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
11 OCTOBER 2021
1:75
3RD FL, HABITO MALL, SOI ON NUT 1/1, SUKHUMVIT 77 ROAD, ON NUT,
DATE
CHECKED BY
MS AZIAH
DRAWN BY
IVAN KHOO YUN FAN DRAWING NO
CS_DWD_IK_S02_04
REV NO
03
3
2
1
18800 11650 4050
+ 56.00
450
3000
4150
450 1350
1150
7150 1200
1200
1350
450
FFL
C1 EXPOSED CEILING PP04
B2 B2
B2
B2 150MM (THK.) BRICK WALL W/ WHITE PAINT
B2
F2 12MM (THK.) DOUBLE GLAZING GLASS W/ ALUMINUM CURTAIN WALL FRAME F2 20MM (THK.) CEMENT SCREED FINISHES
+ 56.00
F2
FFL
05
PARTIAL SECTION B
S03
SCALE 1:75
DRAWING TITLE
NOTE
CLIENT
ARCHITECT
HUBBA-TO SUPERMACHINE STUDIO No .
Description
INTERIOR DESIGN CONSULTANT SUPERMACHINE STUDIO
QUANTITY SURVEYOR
PROJECT TITLE
SUPERMACHINE STUDIO
HUBBA-TO CO WORKING SPACE PARTIAL SECTION B
Date
SCALE
PROPOSE RENOVATION FOR HUBBA-TO CO WORKING SPACE
1:75
3RD FL, HABITO MALL, SOI ON NUT 1/1, SUKHUMVIT 77 ROAD, ON NUT, PHRA KHANONG NUEA, WATTHANA, BANGKOK 10250, THAILAND . 3RD FL, HABITO MALL, SOI ON NUT 1/1 SUKHUMVIT 77 ROAD, ON NUT, PHRA KHANONG NUEA, WATTHANA, BANGKOK 10250, THAILAND
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
DATE
11 OCTOBER 2021 CHECKED BY
MS AZIAH
DRAWN BY
IVAN KHOO YUN FAN DRAWING NO
CS_DWD_IK_S03_05
REV NO
03
1200
2460
06
BESPOKE TABLE PLAN
B01
SCALE 1:20
2460 640
730
OPEN
OPEN
OPEN
OPEN
360
30
840
310
80
1090
60
OPEN
DET. B 06
BESPOKE TABLE FRONT ELEVATION
B01
SCALE 1:10 DRAWING TITLE
NOTE
CLIENT
ARCHITECT
HUBBA-TO No .
Description
SUPERMACHINE STUDIO
Date
INTERIOR DESIGN CONSULTANT SUPERMACHINE STUDIO
QUANTITY SURVEYOR
PROJECT TITLE
HUBBA-TO CO WORKING SPACE BESPOKE TABLE PLAN & FRONT ELEVATION
SUPERMACHINE STUDIO
SCALE
PROPOSE RENOVATION FOR HUBBA-TO CO WORKING SPACE
REFER TO DRAWINGS
3RD FL, HABITO MALL, SOI ON NUT 1/1, SUKHUMVIT 77 ROAD, ON NUT,
MS AZIAH
BANGKOK 10250, THAILAND
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
11 OCTOBER 2021
CHECKED BY
PHRA KHANONG NUEA, WATTHANA, BANGKOK 10250, THAILAND . 3RD FL, HABITO MALL, SOI ON NUT 1/1 SUKHUMVIT 77 ROAD, ON NUT, PHRA KHANONG NUEA, WATTHANA,
DATE
DRAWN BY
IVAN KHOO YUN FAN DRAWING NO
CS_DWD_IK_B01_06
REV NO
03
760
760
2460MM (L) x 1200MM(W)x 50MM (THK) PLYWOOD TABLE TOP
80
40MM (THK) STAINLESS STEEL TABLE FRAME
30 140 30 150
4MM(THK) STAINLESS STEEL HANDLE W/ BLACK EPOXY FINISH
6MM (THK) STAINLESS STEEL SLIDING TRACK
360
840
30 360
840
310
80
DET. A
40MM(THK) STAINLESS STEEL LEG W/ POWDER COATING
60
60
650MM(W) X 330MM(H) BLACK WIRE MESH
07
BESPOKE TABLE RIGHT ELEVATION
07
BESPOKE TABLE LEFT ELEVATION
B02
SCALE 1:10
B02
SCALE 1:10
DRAWING TITLE
NOTE
CLIENT
ARCHITECT
HUBBA-TO No .
Description
SUPERMACHINE STUDIO
Date
INTERIOR DESIGN CONSULTANT SUPERMACHINE STUDIO
QUANTITY SURVEYOR
PROJECT TITLE
HUBBA-TO CO WORKING SPACE BESPOKE TABLE RIGHT & LEFT ELEVATION
SUPERMACHINE STUDIO
SCALE
PROPOSE RENOVATION FOR HUBBA-TO CO WORKING SPACE 3RD FL, HABITO MALL, SOI ON NUT 1/1, SUKHUMVIT 77 ROAD, ON NUT, PHRA KHANONG NUEA, WATTHANA, BANGKOK 10250, THAILAND . 3RD FL, HABITO MALL, SOI ON NUT 1/1 SUKHUMVIT 77 ROAD, ON NUT, PHRA KHANONG NUEA, WATTHANA, BANGKOK 10250, THAILAND
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
DATE
11 OCTOBER 2021
1:10 CHECKED BY
MS AZIAH
DRAWN BY
IVAN KHOO YUN FAN DRAWING NO
CS_DWD_IK_B02_07
REV NO
03
30
40
40
30
4MM (THK) LACQUER FINISH ON THE TOP OF PLYWOOD
50
760MM (HT) X 400MM(D) STAINLESS STEEL TABLE LEG W/ POWDER COATING
10 40
2460MM (L) X 1200MM(W)x 50MM (THK) PLYWOOD TABLE TOP
20MM (THK) X 1000MM (L) X 640MM (W) PLYWOOD PANEL
6MM (THK) X 35MM (L) SWG SPAX SCREW POZIDRIV STEEL ZINC PLATED
08
BESPOKE TABLE DETAIL A
08
BESPOKE TABLE DETAIL B
SCALE 1:5
B03
SCALE 1:5
CLIENT
ARCHITECT
HUBBA-TO Description
6MM (THK) STAINLESS STEEL L-SHAPE BRACKET
B03
NOTE
No .
40 760MM (HT) X 400MM(D) STAINLESS STEEL TABLE LEG W/ POWDER COATING
6MM (THK) X 30MM (L) SWG SPAX SCREW POZIDRIV STEEL ZINC PLATED
60
60
6MM (THK) X 70MM (L) SWG SPAX SCREW POZIDRIV STEEL ZINC PLATED
SUPERMACHINE STUDIO
Date
INTERIOR DESIGN CONSULTANT SUPERMACHINE STUDIO
QUANTITY SURVEYOR
PROJECT TITLE
HUBBA-TO CO WORKING SPACE BESPOKE TABLE DETAIL A & B
SUPERMACHINE STUDIO
DRAWING TITLE
SCALE
PROPOSE RENOVATION FOR HUBBA-TO CO WORKING SPACE
DATE
11 OCTOBER 2021
1:5 3RD FL, HABITO MALL, SOI ON NUT 1/1, SUKHUMVIT 77 ROAD, ON NUT, CHECKED BY
PHRA KHANONG NUEA, WATTHANA, BANGKOK 10250, THAILAND .
MS AZIAH 3RD FL, HABITO MALL, SOI ON NUT 1/1 SUKHUMVIT 77 ROAD, ON NUT, PHRA KHANONG NUEA, WATTHANA, BANGKOK 10250, THAILAND
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
DRAWN BY
IVAN KHOO YUN FAN DRAWING NO
CS_DWD_IK_B03_08
REV NO
03
D1
D2
D3
2150 1045
1045
1800 900
900
FFL
FFL
75
FFL
2250
2100
2400
2400
75
900
D3
DOOR.NO LOCATION
MEETING ROOM TYPE
SINGLE SWING FIBERGLASS DOOR
FRAME
900MM (W)X 2100MM (H) X 50MM THK ALUMINIUM FRAME IN POWDER COATED FINISH
DESCRIPTION
IRONMONGERY
DOOR.NO
D2
DOOR.NO
LOCATION
KILN ROOM
LOCATION
TYPE
GLASS SLIDING DOOR WITH ALUMINIUM FRAME 2150MM (W)X 2400MM (H)ALUMINIUM WINDOW FRAME WITH POWDER COATED FINISH
DESCRIPTION FRAME
DOOR LEAF
50MM THK CLEAR GLASS PANEL
DOOR LEAF
HINGES
STAINLESS STEEL BUTT HINGES
HINGES
STAINLESS STEEL SLIDING HINGE
LOCK/BOLTS
STAINLESS STEEL HANDLE
STOP/PULLS
ALUMINIUM
LOCK/BOLTS
1 POINT LOCK
STOP/PULLS
STAINLESS STEEL ROD DOOR HANDLE
IRONMONGERY
D1 MAINENTRANCE TYPE
SWING DOUBLE DOOR W / FIXED GLASS PANEL
FRAME
8.0MM THK. BLACK POWDER COATED ALUMINIUM FRAME
DESCRIPTION
15MM THK TEMPERED GLASS
12MM TEMPERED GLASS FIXED PANEL
DOOR LEAF
2.0MM THK.STAINLESS STEEL BUTT HINGES
HINGES IRONMONGERY
LOCK/BOLTS
STAINLESS STEEL ROD DOOR HANDLE
STOP/PULLS
HYDRAULIC DOOR CLOSER W/ ALUMINIUM FINISH
W1
W2
4900 1225
1225
1225
1400
50
600
1225
2000
1300
3400
1300
850 FFL
50
FFL
WINDOW.NO LOCATION TYPE
DOOR.NO LOCATION TYPE
CURTAIN WALL
DESCRIPTION
1300 (W) X 1300 (H) BLACKNED STEEL
FRAME
4900MM (L) X 3400MM (H) ALUMINIUM FRAME
DOOR LEAF
FIXED STEEL GRILLE
DOOR LEAF
POWDER COATING FINISH
HINGES
N/A
HINGES
N/A
LOCK/BOLTS
N/A
LOCK/BOLTS
N/A
STOP/PULLS
N/A
STOP/PULLS
N/A
FRAME
CLIENT
NOTE
IRONMONGERY
ARCHITECT
HUBBA-TO SUPERMACHINE STUDIO No .
W2 PHOTOGRAPHY DARK ROOM
SINGLE PANEL FIXED GRILLE
DESCRIPTION
IRONMONGERY
W1 CO WORKING AREA
Description
INTERIOR DESIGN CONSULTANT SUPERMACHINE STUDIO
QUANTITY SURVEYOR
PROJECT TITLE
SUPERMACHINE STUDIO
DRAWING TITLE
HUBBA-TO CO WORKING SPACE DOORS & WINDOWS SCHEDULE
Date
SCALE
PROPOSE RENOVATION FOR HUBBA-TO CO WORKING SPACE 3RD FL, HABITO MALL, SOI ON NUT 1/1, SUKHUMVIT 77 ROAD, ON NUT, PHRA KHANONG NUEA, WATTHANA, BANGKOK 10250, THAILAND . 3RD FL, HABITO MALL, SOI ON NUT 1/1 SUKHUMVIT 77 ROAD, ON NUT, PHRA KHANONG NUEA, WATTHANA, BANGKOK 10250, THAILAND
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
DATE
11 OCTOBER 2021
NTS CHECKED BY
MS AZIAH
DRAWN BY
IVAN KHOO YUN FAN DRAWING NO
CS_DWD_IK_DWS_09
REV NO
03
UBBL ANALYSIS REPORT UBBL 165 Measurement of travel distance to exits. In this level of the building, it included one exit door and it is the only exit door that reach to the ground floor. By studying UBBL law 165, the travel distance shall be measured from the doors of such rooms in the case of individual rooms which are subject to occupancy of not more than six persons, .Based on the table of 7th schedule (table 1.1), it is an office area and it has provided that the travel distance from any point in the room to the room door does not exceed 15 metres. The travel distance of the nearest room from exit is 14 meters , it has applied the UBBL 165 ,but the other rooms have exceed 15 meters and they do not applied the UBBL 165. Furthermore, because the real direction of travel at the screening room area cannot be determinded in an open layout, the direct distance can be estimated as a straight line from the entrance to the exit. The allowed travel distance is therefore decreased by 2/3. Following the UBBL 165 (B) , if individual rooms which are subject to occupancy of not more than six persons ,the final exits to comply with dead end and travel distance Max distance is 15 m within room plus max allowable travel distance From door of room to final exit.But in this case, the room that not more than six persons also exceed the maximum distance. (figure 1.2) Refer to UBBL law 165, this issue can be avoid from not applied the UBBL law by adding adding more exit doors in the building and make sure the travel distance from a room to the exit is not exceed 15 meters. It is to ensure the users safety but also to follow the law of UBBL.
figure 1.2 Diagram of Travel distance
table 1.1 7th Schedule
UBBL 222 Fire Resistance Wall There are a lot of compartment wall or separating wall in this level of Hubba-To.The walls of this building mostly are build by brick and curtain wall. But some of the compartment wall are applied with the particle board on the wall surface.The walls applied at leather studio are fire resistance wall (figure 1.3). By studying UBBL law 222, if each side of the wall is separately exposed to test by fire, the wall should have fire resistance for not less than fifteen minutes as the minimum period required by this law. To clarify that this requirement is applicable to any structural wall, external wall and compartment wall or separating wall. Another statement from this law is any part of an exterior wall that is 0.92 metre or more from the relevant boundary and is required by these By-laws to be fire resistant must be fire resistant for at least fifteen minutes if the inside of the wall is exposed to fire. Aside from that, the wall must be capable of meeting the criteria of clause 11c of section 3 of BS 476: Part 1: related to insulation for a duration of not less than fifteen minutes for the purposes of these by-laws.
figure 1.4 Fire resistance wall
figure 1.3 Fire resistance walls on Leather Studio
CLIENT
NOTE
ARCHITECT
HUBBA-TO No .
Description
Referring to UBBL law 222, there are some areas in this building that could be improved. Areas such as dark rooms and wood workshops should also have fire resistance walls installed as these areas have a high risk of causing fire accidents. The purpose of applying the fire resistance wall in the building is to reduce the possibility of a fire accident and reduce the wide spread of fire in the building when one happens.
SUPERMACHINE STUDIO
Date
INTERIOR DESIGN CONSULTANT SUPERMACHINE STUDIO
QUANTITY SURVEYOR
PROJECT TITLE
HUBBA-TO CO WORKING SPACE UBBL ANALYSIS REPORT
SUPERMACHINE STUDIO
DRAWING TITLE
SCALE
PROPOSE RENOVATION FOR HUBBA-TO CO WORKING SPACE
DATE
11 OCTOBER 2021
NTS 3RD FL, HABITO MALL, SOI ON NUT 1/1, SUKHUMVIT 77 ROAD, ON NUT, CHECKED BY
PHRA KHANONG NUEA, WATTHANA, BANGKOK 10250, THAILAND .
MS AZIAH 3RD FL, HABITO MALL, SOI ON NUT 1/1 SUKHUMVIT 77 ROAD, ON NUT, PHRA KHANONG NUEA, WATTHANA, BANGKOK 10250, THAILAND
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
CHOM PHON, CHATUCHAK, BANGKOK 10900, THAILAND +66-2-276-6279
DRAWN BY
IVAN KHOO YUN FAN DRAWING NO
CS_DWD_IK_UBBL_11d
REV NO
01
REFLECTION
This assignment includes group tasks and individual tasks. Furthermore, the study of UBBL and building fire safety is the assignment's main learning outcome. As a member of my group, I think collaboration in a team is important, and fortunately, we have solved many problems together and ended the group tasking with a happy ending.
There are a few challenges that I faced in the individual tasks, especially the UBBL. I went to research the UBBL regulations and identify the UBBL that apply to the buildings. I think the hardest part is to remember the various details of each bylaw. In addition, I was also able to identify the missing fire safety requirements in the building. I think UBBL is a necessary condition for designing interior space, and it is also necessary knowledge as a designer. This is our professional skill, but also our responsibility as an interior designer. I think I need to continue to accumulate experience at work and have
02
a deeper understanding of the usefulness of UBBL in practice.
INTRODUCTION In this project, I am required place'
within
the
complex,
to
such
choose as
a
a
'working
study
area,
bedroom, or working location with an opening, such as a
door
or
a
window,
within
the
perimeter.
I
must
measure the actual size of the room and the openings, then
convert
the
measurements
to
2D
drawings
complete with specifications, a schedule of finishes for the area including the floor, walls, and ceiling, as well as a door or window schedule that can be seen in the
Assignment
area. The aim of this project is to be able convert the drawing convention into 2D drawings and capture the level
of
detailing,
such
as
opening
widths,
frames
installed on the walls, framing profiles and construction, materials used, and other finishes considerations.
WORK FROM HOME : DOORS & WINDOWS
Bachelor of Art (HONS) in Interior Architecture DETAILING AND WORKING DRAWINGS [IDS60804]
Assignment 1 : WORK FROM HOME + DOOR OR WINDOW
Lecturer: Ms.Norji Nasir
Name : Ivan Khoo Yun Fan Student ID : 0344608
NOTE :
Y
4480
THIS DRAWING IS COPYRIGHTED. THE AUTHORIZED USER IS TO CHECK ALL DIMENSIONS ON SITE. ONLY FIGURED DIMENSIONS ARE TO BE WORKED ON. DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO PARTNERSHIP BEFORE PROCEEDING.
700
2200
1090
105
105 490
NO.
PH_DWD_IK_DD_03
DATE
DESCRIPTION
CLIENT : HILTON HOTEL KUCHING Jalan Tunku Abdul Rahman, 93100 Kuching, Sarawak.
1350MM(L) x 760MM(W) x 750MM(H) MAPLE TIMBER STUDY TABLE
(TEL) 082-223 888
ARCHITECT :
4230
LIVING AREA WOOL CARPET 20 sq. mtr.
3440
IDC ARCHITECTS Level 2, Lot 157, 158, Jalan Chan Chin Ann, 93100 Kuching, Sarawak. (TEL) 082-240 406 INTERIOR DESIGN CONSULTANT : EA ALAM REKA GROUP A-05-01, Jalan Zuhal U5/178, Pusat Komersial Arena Bintang, Subang Bestari, 40150 Shah Alam, Selangor. (TEL) 082-240 406 KPK QUANTITY SURVEYORS QUANTITY SURVEYOR : (SARAWAK) SDN. BHD. Jalan Tan Sri Ong Kee Hui, Gan Swee Cho Garden, 93200 Kuching, Sarawak
3000MM(W) x 6MM(THK) WOOL CARPET FLOORING
(TEL) 082-241 244
790
PROJECT NAME : PROPOSE REPUBLISHMENT WORK FOR HILTON HOTEL
DRAWING TITLE :
COUNTER BAR
LIVING ROOM FURNITURE LAYOUT PLAN
SCALE: REFER TO DRAWING
FLP LIVING ROOM LAYOUT PLAN LR SCALE 1:25
Y
CHECKED BY: NORJI NASIR
DRAWING NO:
PH_DWD_IK_FLP_01
DATE: 12 SEPTEMBER 2021 DRAWN BY: IVAN KHOO YUN FAN
REV. NO: 01
NOTE : THIS DRAWING IS COPYRIGHTED. THE AUTHORIZED USER IS TO CHECK ALL DIMENSIONS ON SITE. ONLY FIGURED DIMENSIONS ARE TO BE WORKED ON. DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO PARTNERSHIP BEFORE PROCEEDING.
4130
NO.
+ 56.00
DATE
DESCRIPTION
CLIENT :
SSL
600
HILTON HOTEL KUCHING Jalan Tunku Abdul Rahman, 93100 Kuching, Sarawak.
CP1
CONCRETE WALL WITH WALDEN WHITE LATEX PAINT
(TEL) 082-223 888
ARCHITECT : IDC ARCHITECTS Level 2, Lot 157, 158, Jalan Chan Chin Ann, 93100 Kuching, Sarawak. (TEL) 082-240 406
WP1
INTERIOR DESIGN CONSULTANT : EA ALAM REKA GROUP
2050
2850
W1
A-05-01, Jalan Zuhal U5/178, Pusat Komersial Arena Bintang, Subang Bestari, 40150 Shah Alam, Selangor.
WP1
(TEL) 082-240 406 KPK QUANTITY SURVEYORS QUANTITY SURVEYOR : (SARAWAK) SDN. BHD.
2100MM(H) x 850MM(W) x 350MM(THK) SOLID NYATOH TIMBER DOOR
PH_DWD_IK_DOS_03
200
OPEN
Jalan Tan Sri Ong Kee Hui, Gan Swee Cho Garden, 93200 Kuching, Sarawak (TEL) 082-241 244 PROJECT NAME : PROPOSE REPUBLISHMENT WORK FOR HILTON HOTEL
F1 FFL
OPEN
DRAWING TITLE : LIVING ROOM ROOM SECTION
SECTION Y-Y
SC Y SCALE 1:20
SCALE: REFER TO DRAWING CHECKED BY: NORJI NASIR
DRAWING NO:
PH_DWD_IK_SC_02
DATE: 12 SEPTEMBER 2021 DRAWN BY: IVAN KHOO YUN FAN
REV. NO: 02
NOTE : THIS DRAWING IS COPYRIGHTED. THE AUTHORIZED USER IS TO CHECK ALL DIMENSIONS ON SITE. ONLY FIGURED DIMENSIONS ARE TO BE WORKED ON. DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO PARTNERSHIP BEFORE PROCEEDING.
NO.
DATE
DESCRIPTION
CLIENT : HILTON HOTEL KUCHING Jalan Tunku Abdul Rahman, 93100 Kuching, Sarawak.
2940
(TEL) 082-223 888
830
1410
700 ARCHITECT : IDC ARCHITECTS Level 2, Lot 157, 158, Jalan Chan Chin Ann, 93100 Kuching, Sarawak. (TEL) 082-240 406 INTERIOR DESIGN CONSULTANT : EA ALAM REKA GROUP
18
105 60
EXTERIOR
A-05-01, Jalan Zuhal U5/178, Pusat Komersial Arena Bintang, Subang Bestari, 40150 Shah Alam, Selangor. (TEL) 082-240 406
INTERIOR
8MM (THK.) ALUMINUM WINDOW FRAME W/ THERMAL BREAK
KPK QUANTITY SURVEYORS QUANTITY SURVEYOR : (SARAWAK) SDN. BHD. Jalan Tan Sri Ong Kee Hui, Gan Swee Cho Garden, 93200 Kuching, Sarawak
18MM (THK.) DOUBLE GLAZING GLASS
PL PLAN OF WINDOWS W SCALE 1:10
ALUMINUM CASEMENT WINDOW RIGHT-HANDLE
(TEL) 082-241 244 PROJECT NAME : PROPOSE REPUBLISHMENT WORK FOR HILTON HOTEL
DRAWING TITLE :
DETAILED PLAN OF WINDOWS
SCALE: REFER TO DRAWING CHECKED BY: NORJI NASIR
DATE: 12 SEPTEMBER 2021 DRAWN BY:
DRAWING NO:
PH_DWD_IK_DOP_03
IVAN KHOO YUN FAN
REV. NO: 03
105
NOTE :
'D1'
THIS DRAWING IS COPYRIGHTED. THE AUTHORIZED USER IS TO CHECK ALL
60
DIMENSIONS ON SITE. ONLY FIGURED DIMENSIONS ARE TO BE WORKED ON. DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO PARTNERSHIP BEFORE PROCEEDING.
18
60 18
60
CONCRETE BLOCK C/W PLASTER FINISHING SILICONE SEALING
DATE
DESCRIPTION
60
NO.
8MM (THK.) ALUMINUM WINDOW FRAME W/ THERMAL BREAK
CLIENT :
RUBBER SEALS
HILTON HOTEL KUCHING Jalan Tunku Abdul Rahman, 93100 Kuching, Sarawak.
18MM (THK.) DOUBLE GLAZING GLASS
(TEL) 082-223 888
ARCHITECT :
INTERIOR
EXTERIOR
IDC ARCHITECTS Level 2, Lot 157, 158, Jalan Chan Chin Ann, 93100 Kuching, Sarawak. (TEL) 082-240 406
BLOW UP D1
D1 W
SCALE 1:2
60
1750
1870
INTERIOR DESIGN CONSULTANT : EA ALAM REKA GROUP A-05-01, Jalan Zuhal U5/178, Pusat Komersial Arena Bintang, Subang Bestari, 40150 Shah Alam, Selangor.
18
(TEL) 082-240 406 KPK QUANTITY SURVEYORS QUANTITY SURVEYOR : (SARAWAK) SDN. BHD. Jalan Tan Sri Ong Kee Hui, Gan Swee Cho Garden, 93200 Kuching, Sarawak (TEL) 082-241 244
20
8MM (THK.) ALUMINUM WINDOW FRAME W/ THERMAL BREAK
60
40
RUBBER SEALS
PROJECT NAME : PROPOSE REPUBLISHMENT WORK FOR HILTON HOTEL
WOOD BLOCK SKIRTING BOARD
'D2' CONCRETE BLOCK C/W PLASTER FINISHING
DRAWING TITLE :
60
DETAILED SECTION OF WINDOWS &TWO BLOW-UP DETAILS
SC SECTION OF WINDOWS W SCALE 1:5
D2 W
BLOW UP D2 SCALE 1:2
SCALE: REFER TO DRAWING CHECKED BY: NORJI NASIR
DATE: 12 SEPTEMBER 2021 DRAWN BY:
DRAWING NO:
PH_DWD_IK_DOS_04
IVAN KHOO YUN FAN
REV. NO: 04
NOTE : THIS DRAWING IS COPYRIGHTED. THE AUTHORIZED USER IS TO CHECK ALL DIMENSIONS ON SITE. ONLY FIGURED DIMENSIONS ARE TO BE WORKED ON. DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO PARTNERSHIP BEFORE PROCEEDING.
SCHEDULE OF WINDOWS
2940 NO.
1410
700
90
830
DATE
DESCRIPTION
CLIENT : HILTON HOTEL KUCHING Jalan Tunku Abdul Rahman, 93100 Kuching, Sarawak. (TEL) 082-223 888
IDC ARCHITECTS Level 2, Lot 157, 158, Jalan Chan Chin Ann, 93100 Kuching, Sarawak. (TEL) 082-240 406
1870
2050
ARCHITECT :
INTERIOR DESIGN CONSULTANT : EA ALAM REKA GROUP A-05-01, Jalan Zuhal U5/178, Pusat Komersial Arena Bintang, Subang Bestari, 40150 Shah Alam, Selangor. (TEL) 082-240 406
90
KPK QUANTITY SURVEYORS QUANTITY SURVEYOR : (SARAWAK) SDN. BHD. Jalan Tan Sri Ong Kee Hui, Gan Swee Cho Garden, 93200 Kuching, Sarawak
+ 56.00 FFL
(TEL) 082-241 244
WINDOW NO. DESCRIPTION
W1 TYPE FRAME DOOR LEAF
DOUBLE GLAZED UNIT 2 PANEL ALUMINUM CASEMENT WINDOW W/ FIXED GLASS PANEL
PROJECT NAME : PROPOSE REPUBLISHMENT WORK FOR HILTON HOTEL
8.0MM THK. BLACK POWDER COATED ALUMINUM FRAME 18MM CLEAR DOUBLE GLAZING GLASS (EXTERNAL : LAMINATED ; INTERNAL : LAMINATED & TEMPERED) DRAWING TITLE :
IRONMONGERY
HINGES LOCK , BOLTS STOP , PULLS
LOCATION
2.0MM THK. STAINLESS STEEL CASEMENT WINDOW 4 BAR HINGES
SCHEDULE OF WINDOWS
STAINLESS STEEL LOCKING CASEMENT WINDOW HANDLE / FASTENER N/A LIVING AREA
SCALE: REFER TO DRAWING CHECKED BY: NORJI NASIR
DRAWING NO:
PH_DWD_IK_SW_05
DATE: 12 SEPTEMBER 2021 DRAWN BY: IVAN KHOO YUN FAN
REV. NO: 05
NOTE : THIS DRAWING IS COPYRIGHTED. THE AUTHORIZED USER IS TO CHECK ALL DIMENSIONS ON SITE. ONLY FIGURED DIMENSIONS ARE TO BE WORKED ON. DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO PARTNERSHIP BEFORE PROCEEDING.
NO.
DATE
DESCRIPTION
CLIENT : HILTON HOTEL KUCHING Jalan Tunku Abdul Rahman, 93100 Kuching, Sarawak.
SCHEDULE OF FINISHES
(TEL) 082-223 888
AREA LIVING ROOM
FLOOR CODE : F1 SIZE : 3000MM(W) x 60MM(THK) MATERIALS:WOOL CARPET FLOORING BRAND : UDANI CARPETS SDN BHD
WALL
CEILING
CODE : CP1 CODE : WP1 MATERIALS: PLASTER MATERIALS: PLASTER AND LATEX PAINT AND LATEX PAINT BRAND : NIPPON BRAND : NIPPON PAINT (M) SDN. BHD. PAINT (M) SDN. BHD.
DOOR CODE : D1 FIRE RATED SINGLE FLUSH DOOR SIZE : 2100MM(H) X 850MM(W) X350MM(THK) MATERIALS: NYATOH TIMBER BRAND : COMEDGE BMT SDN. BHD.
WINDOW CODE : W1 DOUBLE GLAZING GLASS WINDOW SIZE : 2940MM(L)X 2050MM(W)X 18MM(THK) MATERIALS: ALUMINUM WINDOW FRAME BRAND : ECOGLASS GALAXY SDN. BHD.
ARCHITECT : IDC ARCHITECTS Level 2, Lot 157, 158, Jalan Chan Chin Ann, 93100 Kuching, Sarawak. (TEL) 082-240 406 INTERIOR DESIGN CONSULTANT : EA ALAM REKA GROUP A-05-01, Jalan Zuhal U5/178, Pusat Komersial Arena Bintang, Subang Bestari, 40150 Shah Alam, Selangor. (TEL) 082-240 406 KPK QUANTITY SURVEYORS QUANTITY SURVEYOR : (SARAWAK) SDN. BHD. Jalan Tan Sri Ong Kee Hui, Gan Swee Cho Garden, 93200 Kuching, Sarawak (TEL) 082-241 244 PROJECT NAME : PROPOSE REPUBLISHMENT WORK FOR HILTON HOTEL
DRAWING TITLE :
SCHEDULE OF FINISHES
SCALE: REFER TO DRAWING CHECKED BY: NORJI NASIR
DRAWING NO:
PH_DWD_IK_SF_06
DATE: 12 SEPTEMBER 2021 DRAWN BY: IVAN KHOO YUN FAN
REV. NO: 06
REFLECTION This assignment gave me a preliminary understanding of detailing and working drawings. It enhances my design knowledge and technical competencies of interior detailing.
In addition, by observing the types of windows and doors in the room of our working
space,
I
enhanced
my
knowledge
of
the
constituent
hardware
and
joinery parts of the windows and doors. Converting my observations from reality into
technical
construction
drawings
is
one
of
the
skills
I
learned
from
this
assignment. After doing a lot of research on the materials for this assignment, I was also able to identify the types of materials.
01