PROPOSED FY 2023 - 2027 Capital Improvement Program

Creed Fields Park Total Project Cost: $3.8M Project Status:

Continuing

PROJECT DESCRIPTION The Creed Fields Park is approximately 15 acres located at 4390 Riffe Street Elliston, VA. This park will have many features including: • • • • • • • •

Three Baseball/ Softball Fields One Multi-Purpose Fields Lighting for Fields Restroom Facility – water, sewer, and power Parking lot – 200 spaces with lighting Picnic Shelter Playground Extensive Walking Trails

FUNDING SOURCES • • •

Lease Revenue Bonds – $.4M Cash-to-Capital - $3.4M Annual maintenance costs will be supported by the general fund.

Project - Creed Fields Park Planning Design

Prior Years thru FY 22

FY 23

$1,260

FY 24

FY 25

FY 26

FY 27

$0

$0

$0

$0

$0

Total FY 23-27 $0

Grand Total $1,260

$109,065

$0

$0

$0

$0

$0

$0

$109,065

Construction

$2,598,732

$1,000,000

$0

$0

$0

$0

$1,000,000

$3,598,732

Construction Contingency

$0 $2,709,057

$100,000 $1,100,000

$0 $0

$0 $0

$0 $0

$0 $0

$100,000 $1,100,000

$3,809,057

Prior Years thru FY 22

FY 23

Total Project Costs

Funding Proceeds to Date Bond Funds

$0

FY 24

FY 25

FY 26

FY 27

$425,000

$0

$0

$0

$0

Total FY 23-27

$100,000

$425,000

Grand Total $425,000

County Cash to Capital - Transfer from GF

$2,709,057

$0

$0

$0

$0

$0

$0

$2,709,057

Additional County Cash to Capital

$0 $2,709,057

$675,000 $1,100,000

$0 $0

$0 $0

$0 $0

$0 $0

$675,000 $1,100,000

$3,809,057

Total Funding Sources

14

$675,000