NB: Materials shown in Monetary Terms will have to be viewed in the Resources Console For any clarifications, feel free to contact the undersigned Agent for assistance
DWG REF# - 3 Bed 3 Bedroomed House_Rev.0 Materials in Construction Stages Item
Description
Cement
¾ Stones
R/Sand
a) b) c) d) e) f)
Clearing & / Setting Out Trench Excavations Blinding Concrete Footing & Padded Foundations Substructure Brickwork Concrete Slab
15 bags 195 bags 28 bags 101 bags
2.5 m³ 23.0 m³
2.9 m³ 18.6 m³
g) h) i) j) k) l) m) n) o) p) q) r)
Doors with frame c/w hinges, screws & locksets Windows & Handles c/w nuts, bolts & washer Superstructure Brickwork, Window Level Superstructure Brickwork, Wall Plate Level Ring Beam Plaster External Plaster Internal Rhinoset Paint PVA High Gloss (Steel Frames) Sush Putty (N/A to Aluminium Frames) Wall Plate
s) t) u) v) w)
Roof Trusses (aggregates where gable ends exist) Purlins & Brandering Roof Covering Ceiling & Cornice Rainwater Goods
x) y)
Plumbing & Fittings Electricals & Fittings
z)
External Works Column Totals for Material Headings
74 32 63 17 40
bags bags bags bags bags
12 bags
Bricks
SUBSTRUCTURE (UP TO SLAB)
6.0 m³
6,301 bricks
16,841 bricks 7,217 bricks
ROOF (TRUSSES, COVERING & CEILING) 2,398 bricks
115 B/Force
230 DPC
115 DPC
5.1 m³
13.3 m³ 5.7 m³
6 rolls
16 rolls 7 rolls
4 rolls
4 rolls
2 rolls
bags 577 bags
LANDSCAPING & WASTE MANAGEMENT 0.0 m³ 0.0 m³ bricks 44.9 m³ 37.2 m³ 32,758 bricks
Page 1 of 5
others as described
14 rolls 6 rolls
rebar 427 kgs
3.1 m³ 7.3 m³
2.1 m³
rebar- kgs 300m 116 m² S.193- 8 sheets $ 716.52 $ 1,875.43
34 bags 97 ℓ 5ℓ kgs 56 m 3 rolls
$
3,661.81 811 m 78 sheets $ 826.30 $ 1,162.80
SERVICES (WATER & ELECTRICITY)
3 Bed - 3 Bedroomed House_Rev.0.xlsx Materials Procurement in Stages Created on 28/8/2019 @ 5:41 PM
230 B/Force
antkill- 2.5ℓ
11.9 m³ 9.6 m³ SUPER STRUCTURE (UP TO WALL PLATE)
7.4 m³
P/Sand
$ $ 0.0 m³ 36.4 m³
rolls 32 rolls
24 rolls
4 rolls
2 rolls
4,230.19 822.13
300m 12.5 m²
+263 77 192 7337 jeffstar@presageprojects.co.zw Presage Projects (Pvt) Ltd © 2019 All Rights Reserved
RICS NRM 2 Adoption 28/8/2019
PPHBQ2018_Rev.0
DWG REF# - 3 Bed 3 Bedroomed House_Rev.0 Elemental Bill of Quantities Item №
Pay Ref
$
Bill Description
Unit
Quantity
Rate (US$)
-
Amount (US$)
Quick Stats
building $/m² = $462.53/m²
Summary
1
building $/m³ = $154.18/m³ 0.00% $
Bill No. 1 Preliminaries (Main Contract)
18.50% $
Bill No. 2 Substructure
Bill No. 3 Superstructure
-
9,880.45
54.99% $
29,375.20
7.80% $
4,169.06
7.19% $
3,838.82
11.53% $
6,158.61
Subtotal
$
53,422.14
Plus 3.00% Contingency Sum
$
1,602.66
Subtotal
$
55,024.80
Add Vat @ 15%
$
8,253.72
Total Amount
$
63,278.52
Bill No. 4 Finishes
Bill No. 5 Fittings, Furnishings and Equipment Bill No. 6 Services
0.00% $
Bill No. 7 External Works
3 Bed - 3 Bedroomed House_Rev.0.xlsx Bill of Quantities|Interface Page 2 of 5
-
+263 77 192 7337 jeffstar@presageprojects.co.zw Presage Projects (Pvt) Ltd © 2019 All Rights Reserved
┌ Confidential Resource Usage
┐
DWG REF# - 3 Bed 3 Bedroomed House_Rev.0 Bill of Resources
1
2%
Cost Code
Resource Description
L L01 L03 L04 L05 L06 L07 L09 L14 L16 L17
Payroll Budget Information @ 9 Man-hours/Day General Hand Carpenter (C) Builder (B) Painter (T) Steel Fixer (X) Glazier (G) Electrician (E) Plumber (P) Light Plant/Equipment Operator (L) Heavy Plant Operator (H)
(All in Labour Rates) $ 2.35/hour $ 3.74/hour $ 3.74/hour $ 3.74/hour $ 3.74/hour $ 3.74/hour $ 3.74/hour $ 3.74/hour $ 4.26/hour $ 5.65/hour
P F01 P03 P04 P16 P17 P18 P19 M BM
Plant Hire Hours @ 8 Plant-hours/Day Diesel (Information only, already included in Plant Rates) 3CX TLB (c) Plate Compactor (d) 750/500 Concrete Mixer (n) Concrete Dumper (o) Concrete Vibrator Set (p) Power Trowel Machine (q) Bill of Materials (BoM) Procurement Building Materials Cements Tile Adhesive (20kg) Tile Grout (5kg) 22,5 (Masonry) Cement 32,5 (PC 15) Cement Aggregates 19mm Stone Washed Riversand (Cash - Pre-Payment at the Quarry) Pitsand Rhino Products Rhinoset Masonry Beta Common Bricks Cement air bricks/vents (pair) Window Cills Galvanised wall ties Reinforcement Deformed Reinforcement Bars (Cut & Bent) Tying Wire 1.6mm ø MeshRef S193 Brickforce 230 (@ every 4th course) Brickforce 115 (@ every 4th course) Shuttering Formwork for lintels Moisture Protection DPC 2 Ply 230 DPC 2 Ply 115 Polythene Sheets (2Ply) Paints & Products Dulux Universal Undercoat Dulux Int - Ext PVA White Dulux Ceiling White Dulux Steel Prime Dulux Gloss White Dulux Pink Wood Primer Dulux Tinters (Shelf price selling @ $5.00/50ml tube) Door Frames Standard 230 single door frame Standard 115 single door frame Aluminium Window Frames 1000×1500 500×1000 1800×1000 1500×1000 Doors Solid standard single door to suit frame Hollow standard single door to suit frame Steel Trusses Roof Trusses to detail Joinery 114mm × 38mm steel wall plate 38mm × 38mm steel purlins 38mm × 38mm sw brandering 9mm Plaster Board Ceiling (Supply Dimension - 2.4m × 1.2m) Rhinocove Cornice Iron Mongery Locksets 3 Lever Hinges c.w. screws for doors Window handle c/w nut, bolt & washer Rainwater Goods PVC Rainwater Gutters ½ round 125 × 87 Rainwater Downpipe 80mm Drip stones Chromadek Roof Sheets 25mm × 220mm sw Fascia Galvanised Roof Ridge
(Plant Charges) $ 1.12/ℓ $ 32.57/hour $ 7.89/hour $ 29.49/hour $ 23.64/hour $ 4.03/hour $ 18.70/hour (Material Costs)
CMT01 CMT02 CMT03 CMT04 BM003 BM004 BM005 RP01 MAS01 MAS06 MAS07 MAS08 RNF01 RNF02 RNF03 RNF06 RNF07 SH01 MP01 MP02 MP03 DP01 DP02 DP03 DP04 DP05 DP06 DP10 DF02 DF03 AWF01 AWF02 AWF03 AWF04 DR02 DR03 TT01 J01 J02 J03 J04 J07 IM01 IM05 IM06 RG03 RG07 RG10 RG11 RG12 RG13
Cost
3 Bed - 3 Bedroomed House_Rev.0.xlsx Resources|Console Created on 28/8/2019 @ 5:41 PM
Page 3 of 5
28.70% Bill Mark-Up @ 0.00% 2.10% 2.7 Month Timeline 69.20% US$ 53,422.14 69% 0 Excluding VAT Usage Amount (US$) $ 1.00 5,736.1 hours $ 15,332.28 4,412.4 hours $ 10,359.63 140.6 hours $ 525.78 865.7 hours $ 3,236.99 79.2 hours $ 296.32 03.5 hours $ 13.00 00.8 hours $ 2.80 62.8 hours $ 234.78 136.9 hours $ 511.74 30.4 hours $ 129.38 03.9 hours $ 21.86 29%
≡ ≡
49.3 hours $ 209.77 ℓ $ 3.4 hours $ 1.4 hours $ 23.0 hours $ 8.1 hours $ 8.1 hours $ 5.3 hours $ Order Quantity $ $
$5.22/sack $5.22/sack $8.26/sack $9.74/sack
12.14 4.32 15 564
bags bags bags bags
$34.78/m³ $21.74/m³ $17.39/m³
44.9 m³ 37.2 m³ 36.8 m³
$13.04/sack
34 bags
$0.16/brick $0.65 ea $0.87 ea $0.17 ea
33,245 bricks 18 no 112 cills 21 no
$3,478.26/ton $2.35/kg $5.22/m² $2.17/roll $1.74/roll
0.427 tons 0.58 kgs 116 m² 32 rolls 24 rolls
$3.91/m
21 m
$3.48/roll $1.74/roll $0.22/m²
4 rolls 2 rolls 231 m²
$5.65/ℓ $5.22/ℓ $2.61/ℓ $9.57/ℓ $10.43/ℓ $5.65/ℓ $86.96/ℓ $26.09 $14.78 1st Choice/Option $236.41 $78.80 $283.70 $236.41
ea ea ea ea ea ea
48 38 12 1.8 1.6 1.4 0.12
US$
ℓ ℓ ℓ ℓ ℓ ℓ ℓ
3 no 7 no 540.00 5 no 2 no 1 no 1 no
$86.96 ea $17.39 ea
3 no 7 no
$347.87 ea
11 no
$4.35/m $2.61/m $0.87/m $4.78/m² $1.30/m
56 m 591 m 220 m 115.5 m² 210 m
$13.91 ea $1.30 ea $1.74 ea
10 sets 10 no 9 no
$4.35/m $3.91/m $13.04 ea $10.96/sheet $10.43/m $5.22/m
63 m 12 m 4 no 78 sheets 63 m 15 m
$
$
$ $
$
$ $
$
$ $
$ $ $
$
$
$ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $
1,123.26 235.58 111.96 11.09 677.64 190.43 32.48 99.67 36,966.60 36,946.50 5,703.75 63.32 22.54 127.63 5,490.26 3,009.21 1,560.57 807.88 640.76 449.74 449.74 5,315.95 5,203.50 11.74 97.04 3.66 2,200.88 1,486.10 1.36 602.61 69.11 41.70 81.03 81.03 67.70 13.22 4.26 50.22 551.46 269.29 198.86 30.13 17.41 17.09 7.88 10.80 181.74 78.26 103.48 1,859.78 1,182.07 157.61 283.70 236.41 382.61 260.87 121.74 3,661.81 3,661.81 2,802.93 243.48 1,541.84 191.30 552.39 273.91 167.83 139.13 13.04 15.65 2,022.67 275.41 46.96 52.17 859.87 660.98 76.17
info@presageprojects.co.zw Presage Projects (Pvt) Ltd © 2019 All Rights Reserved
┌ Confidential Resource Usage
┐
DWG REF# - 3 Bed 3 Bedroomed House_Rev.0 Bill of Resources Cost Code RG14 KF01 KF03 KF04 HVAC02 BF01 BF02 BF03 BF09 BF10 TL01 TL02 PCI01 PCI02 PVCSP01 PVCSP02 GP01 CP01 GF01 GF02 GF03 GF04 GF05 CF01 CF02 CF03 PVCFT01 PVCFT02 PVCFT03 PVCFT04 PVCFT05 PVCFT06 PVCFT07 PVCFT08 PVCFT09 TM01 TM02 TM06 RF01 WMS01 CN01 CNF01 CNF02 CB02 CB05 SW01 SW04 ST01 ST02 ST03 ST04 ST05 ST07 B01 B02 EMS01 EMS02 EMS04 EMS05 ACC ACC01 ACC02 ACC03 ACC08 ACC11
1
Resource Description
69%
0
Cost
Galvanised Valley Kitchen Fittings Kitchen sink 1.2m drop in Cupboards under sink Cupboards on walls HVAC Ceiling fan Bathroom Fittings Wall mounted cabinet with mirror Towel rack Water Closet Ceramic wash basin & pedestal Shower Cubicle 950 × 950 × 2000mm corner type Tiles Floor tiles Wall tiles
$3.50/m $60.87 ea $1347.83 ea $1217.39 ea $56.52 ea $52.17 $22.61 $78.26 $34.78 $130.43
ea ea ea ea ea
$0.65 ea $0.54 ea
Pre-Cast Items Double Cam Concrete Sink Pre-cast lintels Plumbing PVC Sewer Pipes ø110mm sewer pipe ø60mm sewer pipe Galvanised Pipes ø20mm GI pipe Copper Pipes ø20mm copper pipe Galvanised Fittings ø20mm Gi elbow ø20mm Gi tee ø20mm Gi sleeve ø35mm brass p-trap for bath ø35mm Gate Valve Copper Fittings ø20mm copper elbow ø20mm copper tee ø20mm copper sleeve PVC Fittings ø160mm to ø110mm reducer ø110mm x 90° bend ø110mm x 45° bend ø110mm equal tees ø110mm end caps ø110mm p-trap ø110mm sieve ø110mm × 2m pvc vent pipe ø110mm fly trap over vent pipe Taps & Mixers ø15mm basin taps (Cobra) Sink Mixer ø35mm brass tap Rubber Fittings ø35mm rubber p-trap Water Main Supply ZINWA flow meter Electricals Conduits ø19mm pvc conduit Conduit Fittings ø20mm pvc sleeve Junction box (6 × 6) Cables 2.5mm² triple core copper conductors armoured cable Switches Single gang switch Cooker switch Sockets single electric socket double electric socket Cooker terminal Shaver socket Lamp holder (Brass) Fluorescent socket Bulbs/Lights Bulkhead c/w gland seal Osram 11watt fluorescent bulb Electrical Main Supply 3 Phase meter board Generator/Solar change over switch Distribution board 16 Way c/w Breakers ZETDC Prepaid meter Accessories Diesel (Information only, already included in Plant Rates) Petrol (Information only, already included in Plant Rates) 4" wire nails Termite Poison (app rate @ 5ℓ/m² of 5ℓ/95ℓ termicide/water mix) PVC Solvent Cement (100mℓ) 3 Bed - 3 Bedroomed House_Rev.0.xlsx Resources|Console
Created on 28/8/2019 @ 5:41 PM
29%
≡ ≡
Page 4 of 5
2%
Usage
28.70% Bill Mark-Up @ 0.00% 2.10% 2.7 Month Timeline 69.20% US$ 53,422.14 Excluding VAT Amount (US$) $ 1.00 15 m $ 51.10 $ 2,626.09 1 no $ 60.87 1 no $ 1,347.83 1 no $ 1,217.39 $ 113.04 2 no $ 113.04 $ 636.52 2 no $ 104.35 2 no $ 45.22 2 no $ 156.52 2 no $ 69.57 2 no $ 260.87 $ 59.47 36 no $ 23.42 66 no $ 36.04
$78.26 ea $1.74/m
1 no 21 m
$9.57/m $1.74/m
12 m 7 m
$21.74/m
42 m
$21.74/m $7.83 $14.78 $13.04 $3.48 $4.78
ea ea ea ea ea
$8.70 ea $16.52 ea $14.78 ea $31.30 $31.57 $34.78 $17.39 $4.35 $30.43 $5.22 $7.39 $2.17
ea ea ea ea ea ea ea ea ea
3 no
$33.04 ea
1 no
$1.74/m
63 m
$0.43 ea $0.87 ea
32 no 15 no
$0.26/m $3.48/m
189 m 30 m
$1.91 ea $8.70 ea
15 no 1 no
$34.78 $21.74 $213.04 $23.48
ea ea ea ea
$1.07/ℓ $1.17/ℓ $1.74/packet $0.61/ℓ $2.61 ea
$
$
15 5 1 2 15 3
$
no no no no no no no no no
$1.74 ea
$6.96 ea $3.04 ea
$
16 no 16 no 16 no 1 6 6 6 2 6 6 2 2
$
$ $ $
$ $ $
no no no no no no
no no no no
80.45 ℓ 129.32 ℓ 9 packets 2.53 ℓ .9 no
$ $
$
2 no 15 no 1 1 1 1
$ $
no no no no no
6 no 1 no 2 no
ea ea ea ea ea ea
$
42 m 16 16 16 2 7
$6.96 ea $47.83 ea $4.35 ea
$2.61 $5.22 $30.43 $3.04 $1.74 $4.78
$
$
$
$ $ $ $ $
$ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $
114.27 78.26 36.01 4,230.19 126.96 114.78 12.17 913.04 913.04 913.04 913.04 610.87 125.22 236.52 208.70 6.96 33.48 640.00 139.13 264.35 236.52 775.48 31.30 189.39 208.70 104.35 8.70 182.61 31.30 14.78 4.35 98.26 41.74 47.83 8.70 5.22 5.22 33.04 33.04 822.13 109.57 109.57 26.74 13.70 13.04 153.65 49.30 104.35 37.39 28.70 8.70 142.17 39.13 26.09 30.43 6.09 26.09 14.35 59.57 13.91 45.65 293.04 34.78 21.74 213.04 23.48 20.09 86.04 151.81 16.20 1.54 2.35 info@presageprojects.co.zw Presage Projects (Pvt) Ltd © 2019 All Rights Reserved
Conditions of Contract 3rd Edition 1977 (International) Clause 14.1 Program
WBS ID Operation % 1 3 Bedroomed House_Rev.0 2 Mobilisation/Procurement 2.1 Mobilise cabin and security fence c/w gate to site 2.2 Set-up temporary perimeter security 2.3 Set-up storeroom on site 2.4 Procure cement and aggregates 2.5 Mobilise tools and small equipment 3 Substructure 3.1 Earthworks 3.1.1 Clear site 3.1.2 Remove turf (nekusakura) 3.1.3 Excavate topsoil & cartaway 3.1.4 Excavate trenches 3.1.5 Compact trench bases 3.1.6 Termite treatment to surface of excavations 3.2 Strip Footing 3.2.1 Blinding to trench bases 3.2.2 Pour footing 3.3 Foundation Wall 3.3.1 Build external foundation wall 3.3.2 Build internal foundation walls 3.3.3 Backfill around external wall 3.3.4 Fill foundation with hardcore 3.4 Foundation Slab 3.4.1 Lay DPM 3.4.2 Prepare meshref S193 3.4.3 Pour slab
% Planned 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Start 2-Dec-19 2-Dec-19 2-Dec-19 4-Dec-19 4-Dec-19 4-Dec-19 6-Dec-19 4-Dec-19 4-Dec-19 4-Dec-19 11-Dec-19 17-Dec-19 21-Dec-19 23-Dec-19 25-Dec-19 27-Dec-19 27-Dec-19 28-Dec-19 31-Dec-19 31-Dec-19 2-Jan-20 2-Jan-20 4-Jan-20 7-Jan-20 7-Jan-20 8-Jan-20 9-Jan-20
Duration 79 Days 5 days 1 day 2 days 1 day 2 days 1 day 36 days 22 days 6 days 5 days 3 days 1 day 1 day 1 day 3 days 0 days 2 days 5 days 1 day 1 day 0 days 2 days 3 days 0.10 days 0 days 1 day
Finish 20-Feb-20 7-Dec-19 3-Dec-19 6-Dec-19 5-Dec-19 6-Dec-19 7-Dec-19 10-Jan-20 26-Dec-19 10-Dec-19 16-Dec-19 20-Dec-19 22-Dec-19 24-Dec-19 26-Dec-19 30-Dec-19 27-Dec-19 30-Dec-19 6-Jan-20 1-Jan-20 3-Jan-20 3-Jan-20 6-Jan-20 10-Jan-20 7-Jan-20 8-Jan-20 10-Jan-20
Superstructure 0.00% Masonry 0.00% Build external walls up to window level 0.00% 0.00% Build internal walls not exceeding 1.5m high Build-in door frames 0.00% Build-in window frames 0.00% Install lintels 0.00% Build internal walls up to wall plate 0.00% Build external walls up to wall plate with air bricks 0.00% 0.00% Build external walls at gable ends Plastering 0.00% Plaster walls internally 0.00% Plaster walls externally 0.00% Roof 0.00% Install wall plate 0.00% Supply and fix trusses by specialist 0.00% Fix purlins 0.00% Fix brandering 0.00% Install roof covering 0.00% Fix ridge on roof 0.00% Install ceiling 0.00% Install cornice 0.00% Fix fascia/barge board 0.00% Fix gutters 0.00% Install downpipes complete with shoes and dripstones 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
11-Jan-20 11-Jan-20 11-Jan-20 13-Jan-20 11-Jan-20 13-Jan-20 23-Jan-20 18-Jan-20 16-Jan-20 18-Jan-20 20-Jan-20 20-Jan-20 20-Jan-20 17-Jan-20 17-Jan-20 18-Jan-20 22-Jan-20 24-Jan-20 26-Jan-20 29-Jan-20 26-Jan-20 29-Jan-20 28-Jan-20 30-Jan-20 1-Feb-20
21 days 12 days 4 days 2 days 6 days 10 days 0 days 1 day 1 day 1 day 12 days 12 days 5 days 15 days 0 days 3 days 2 days 1 day 2 days 1 day 4 days 1 day 1 day 2 days 0 days
1-Feb-20 23-Jan-20 15-Jan-20 15-Jan-20 17-Jan-20 23-Jan-20 23-Jan-20 19-Jan-20 17-Jan-20 19-Jan-20 1-Feb-20 1-Feb-20 25-Jan-20 1-Feb-20 17-Jan-20 21-Jan-20 24-Jan-20 25-Jan-20 28-Jan-20 30-Jan-20 30-Jan-20 30-Jan-20 29-Jan-20 1-Feb-20 1-Feb-20
5 5.1 5.1.1 5.1.2 5.1.3 5.2 5.2.1 5.3 5.3.1 5.3.2 5.3.3 5.4 5.4.1 5.4.2
Finishes Wall & Floor Finishes Rhinoset finish on internal walls Rhinoset finish on ceiling Grano screed floor finish Glazing Glazing to all windows Painting Paint internal walls Paint ceiling High gloss paint steel to frames Tiling Wall tiles to bathroom and kitchen Floor tiles to bathroom and kitchen
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
25-Jan-20 28-Jan-20 2-Feb-20 5-Feb-20 28-Jan-20 25-Jan-20 25-Jan-20 25-Jan-20 1-Feb-20 11-Feb-20 25-Jan-20 7-Feb-20 7-Feb-20 9-Feb-20
24 days 21 days 16 days 6 days 0 days 0 days 0 days 19 days 6 days 2 days 0 days 3 days 2 days 1 day
18-Feb-20 18-Feb-20 18-Feb-20 11-Feb-20 28-Jan-20 25-Jan-20 25-Jan-20 13-Feb-20 7-Feb-20 13-Feb-20 25-Jan-20 10-Feb-20 9-Feb-20 10-Feb-20
6 7 8 9
Fittings and Equipment Services External Works Project Completion Furnish home and move in
0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00%
1-Feb-20 11-Jan-20 1-Feb-20 18-Feb-20 18-Feb-20
12 days 26 days 2 days 2 days 2 days
13-Feb-20 6-Feb-20 3-Feb-20 20-Feb-20 20-Feb-20
4 4.1 4.1.1 4.1.2 4.1.3 4.1.4 4.1.5 4.1.6 4.1.7 4.1.8 4.2 4.2.1 4.2.2 4.3 4.3.1 4.3.2 4.3.3 4.3.4 4.3.5 4.3.6 4.3.7 4.3.8 4.3.9 4.3.10 4.3.11
Created on 28/8/2019 @ 5:41 PM
9.1
Complete 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
29-Oct-19
28-Nov-19
3 Bed - 3 Bedroomed House_Rev.0.xlsx Construction Schedule|Baseline
28-Dec-19
2-Dec-19
79 Days
2-Dec-19
1 days
2-Dec-19
27-Jan-20
26-Feb-20
5 days
Duration
4-Dec-19
2 days
4-Dec-19
2 days
4-Dec-19
6-Dec-19
4-Dec-19
% Complete
1 days 1 days
6 days
11-Dec-19
5 days
17-Dec-19
3 days
21-Dec-19
1 days
23-Dec-19
1 days
25-Dec-19
1 days
27-Dec-19
0 days
28-Dec-19
2 days
31-Dec-19
1 days
2-Jan-20 2-Jan-20
1 days 0 days
4-Jan-20
2 days
7-Jan-20
8-Jan-20
0.10 days
9-Jan-20
0 days
1 days
11-Jan-20
21 days
11-Jan-20
4 days
11-Jan-20
12 days
13-Jan-20
11-Jan-20
2 days
6 days
13-Jan-20
10 days
18-Jan-20
16-Jan-20
23-Jan-20
0 days
1 days
1 days
18-Jan-20
1 days
20-Jan-20
12 days
20-Jan-20
5 days
20-Jan-20 17-Jan-20 17-Jan-20
12 days
15 days
18-Jan-20
0 days
3 days
22-Jan-20
2 days
24-Jan-20
1 days
26-Jan-20
2 days
26-Jan-20
4 days
29-Jan-20 29-Jan-20
28-Jan-20
1 days 1 days
1 days
30-Jan-20
2 days
1-Feb-20
25-Jan-20
28-Jan-20
21 days
2-Feb-20
28-Jan-20
0 days
25-Jan-20
19 days
25-Jan-20
16 days
5-Feb-20
0 days
25-Jan-20 25-Jan-20
0 days
24 days
6 days
0 days
1-Feb-20
0 days
6 days
11-Feb-20
7-Feb-20 7-Feb-20
2 days
9-Feb-20
11-Jan-20
26 days
1-Feb-20
12 days
1-Feb-20
2 days
2 days
3 days 1 days
18-Feb-20 18-Feb-20
Page 5 of 5
2 days 2 days
+263 77 192 7337 info@presageprojects.co.zw Presage Projects (Pvt) Ltd Š 2019 All Rights Reserved