Trenchless September 2021

Page 38

TUNNELLING & MICROTUNNELLING

Bohrtec machine guides sewer works with Pilot tube and FrontSteer method A vital sewer main installation in New South Wales was made possible through the technical superiority of Bohrtec’s guided auger boring machines.

I

n 2019, Downer Pipetech was engaged by Sydney Water to install 870 m of 226 mm uPVC sewer main for the future developments in the Spring Farm residential area of NSW. With the project requiring the completion of 10 under bore sections, Downer engaged auger boring specialist Bortec Laser Bore from Narellan NSW, which uses machines from expert German supplier Bohrtec. During consultations with experts from Germany, it was noted that geotechnical reports indicated displaceable soft sand, non-displaceable stiff clays and soft sandstone would be encountered. These ground

Pits 10 and 11 – shoring boxes 6 m x 3 m; FrontSteer method.

38 TRENCHLESS AUSTRALASIA SEPTEMBER 2021

conditions suited either the Bohrtec pilot tube system for the displaceable soil, or the Bohrtec 406 mm FrontSteer system for the non-displaceable ground. Although Bortec Laser Bore possessed both a Bohrtec BM 400 LSC and a Bohrtec 400 LS, it was decided the LSC machine would be better suited to the launch shafts due to its more compact design. Challenges While the project proponents had top-quality Bohrtec machinery at their disposal, the works were not without their challenges and a range of equipment was required. The required bore lengths ranged from 69 to 111 m and encompassed a total of approximately 830 m of boring across the project, while the launch shafts ranged from 6 to 13 m in depth. Due to changing ground conditions, the pilot tube method was used in the softer displaceable soil, and the FrontSteer method was used in the harder non-displaceable clay and soft sandstone areas. This method has both vertical and horizontal steering capabilities with an accuracy of up to ± 25 mm for drive of a length up to 100 m. The connection point for the sewer was into an existing sewer access chamber 13 m deep in the middle of a roadway. Bortec and Downer discussed the possibility of directly boring into the existing manhole and eliminating the excavation of the roadway to a connection, and Downer agreed to set up a platform in the existing access chamber in the roadway and internally core out a 600 mm core hole where the bore was to come out. Bortec was able to use the pilot system to move through the soft sand and, with the use of the optical guidance system, could come out directly in the centre of this core hole. Afterwards, the hole could be upsized and bored in the 406 mm steel pipes. Manholes up to 13 m deep were constructed with tight access,


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

ASTT Corporate Members

1min
pages 72-73

Breakthrough technology for drain blockages

3min
pages 70-71

Destigmatising poor mental health in construction

4min
pages 68-69

No-dig innovator takes service to new heights

5min
pages 66-67

Australia’s first online drain cleaning refresher

4min
pages 64-65

ImpulseRadar offers a different view

5min
pages 62-63

Hydro excavation in Brisbane’s Southbank

4min
pages 50-51

The future in pipeline rehabilitation

3min
pages 58-59

Ahead of the curve

3min
pages 56-57

KAISER forges new partnerships

3min
pages 54-55

The superior alternative in SMS rehab

2min
pages 60-61

SECA unveils eCityJet

2min
pages 52-53

The most powerful truck-mounted vacuum excavator yet

2min
pages 48-49

Boretech leading WA’s HDD utility installations

4min
pages 46-47

Getting the edge over the competition

4min
pages 40-41

Bohrtec machine guides sewer works

3min
pages 38-39

Good practices for HDD project management

5min
pages 42-43

Rob Carr in the driver’s seat in WA

4min
pages 36-37

HDI Lucas stays tuned in on Channel Island

3min
pages 32-33

Zipping past the competition

2min
pages 34-35

NSW rolls on through COVID storm

6min
pages 28-31

What to expect at No-Dig

0
pages 24-25

From the President

2min
pages 10-11

No-Dig Down Under postponed

1min
pages 20-21

News in brief

7min
pages 16-19

Councillor’s reports

3min
pages 14-15

Editor’s letter

4min
pages 8-9

From the ASTT Secretary

3min
pages 12-13

Herrenknecht becomes No-Dig Gold Sponsor

2min
pages 22-23
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.