WASTE MANAGEMENT IN ACTION - BUILDING GREENER ROADS
A new milestone ALEX FRASER’S LAVERTON ASPHALT PLANT IN MELBOURNE HAS PRODUCED ITS ONE MILLIONTH TONNE OF ASPHALT. WMR FINDS OUT MORE ABOUT THE FACILITY AND THE MILESTONE. Alex Fraser’s Asphalt production team.
O
n May 31, 2019, following a 16-month build, Alex Fraser unveiled its high recycled technology asphalt plant, along with an innovative glass recycling plant at its Sustainable Supply Hub in Laverton North. Lily D’Ambrosio, Victorian Minister for Energy, Environment and Climate Change officially opened the $20 million plant which creates sustainable asphalt to build greener roads and rail projects across Victoria. With the capability to produce asphalt mixes incorporating recycled glass, plastic and reclaimed asphalt pavement, the facility has been heralded as one of Australia’s greenest asphalt production plants. After just two years, Alex Fraser’ Laverton Asphalt team are celebrating their first million tonne production milestone. Recycled content accounted for more than 30 per cent 60 / WMR / May 2022
of the total production tonnes. Brendan Camilleri, Asphalt General Manager, says the achievement is a reflection of the hard work and dedication of the Laverton Asphalt team. “It was a very proud moment for the team,” he says. “As the millionth tonne was loaded, we rang a traditional cow bell which was presented to us by the Ammann Group, on the day the plant was commissioned.” Brendan says he is particularly proud of the team effort behind the milestone. “It was a big and ongoing effort. The first year was especially challenging, as we were learning to use the new facility to its optimum, while servicing several major projects that demanded high volumes of material,” he says. “It was all hands on deck, and a great team effort. I’m extremely proud of how our people came together.”
MAJOR PROJECTS Asphalt produced by the Laverton plant has been supplied to major projects throughout Victoria, including the Western Roads Upgrade. Alex Fraser supplied more than 170,000 tonnes of road base and 200,000 tonnes of asphalt for the project. In total, the recycled glass equivalent of 190 million bottles was used. The use of Alex Fraser’s sustainable construction materials on the Western Roads Upgrade helped to divert 264,800 tonnes of material from landfill and reduce carbon emissions by 1729 tonnes. “The Western Roads Upgrade projects were the first major projects supplied by this plant,” Brendan says. “They called for high volumes every day, so we worked closely with the Department of Transport and our clients to provide green roads asphalt with the