May 2013 | www.rtands.com
NRC Annual
Membership Directory
Inside
Contractors strengthen
state of NRC plus
Ditching and drainage NRC Project of the Year And also
AREMA News p. 43
Contents May 2013
News
5
RAILWAY TRACK AND STRUCTURES
Features
16
Industry Today 5 Supplier News 9 People
NRC Project of the Year UTA’s FrontRunner South commuter rail line was successfully constructed due to good planning and a focus on safety.
Columns
24
24
Ditching and drainage Mud and water can ruin a perfectly good railroad. Today’s equipment taps into advances to help keep water at bay.
35
Strength of the NRC rooted in membership As the association continues its growth, NRC’s leadership reveals their thoughts on where the organization is headed.
35 Departments 12 TTCI R&D 43 Arema News 48 Products 49 Advertisers Index 49 Sales Representatives
Photo courtesy R.J. Corman Railroad Group.
3
On Track A safety reminder for summer
10
50 Calendar 51 Classified Advertising 52 Professional Directory
NRC Chairman’s Column Biggest and the best auction yet
FOLLOW US on Twitter LIKE US on Facebook
www.rtands.com
16
Railway Track & Structures
May 2013 1
On Track
RAILWAY TRACK AND STRUCTURES
Vol. 109, No. 5 Print ISSN # 0033-9016, Digital ISSN # 2160-2514 EDITORIAL OFFICES 20 South Clark Street, Suite 1910 Chicago, Ill. 60603 Telephone (312) 683-0130 Fax (312) 683-0131 Website www.rtands.com Mischa Wanek-Libman/Editor, mischa@sbpub.com Jennifer Nunez/Assistant Editor, jnunez@sbpub.com CORPORATE OFFICES 55 Broad Street, 26th Floor New York, N.Y. 10004 Telephone (212) 620-7200 Fax (212) 633-1165 Arthur J. McGinnis, Jr./ President and Chairman Jonathan Chalon/Publisher George S. Sokulski/Associate Publisher Emeritus Mary Conyers/Production Director Maureen Cooney/Circulation Director Jane Poterala/Conference Director
Railway Track & Structures (Print ISSN 0033-9016, Digital ISSN 2160-2514), (USPS 860-560), (Canada Post Cust. #7204654), (Bluechip Int’l, Po Box 25542, London, ON N6C 6B2, Agreement # 41094515) is published monthly by Simmons-Boardman Publ. Corp, 55 Broad Street, 26th Floor, New York, N.Y. 10004. Printed in the U.S.A. Periodicals postage paid at New York, NY and Additional mailing offices. Pricing, Qualified individual in the railroad employees may request a free subscription. Non-qualified subscriptions printed or digital version: 1 year Railroad Employees (US/ Canada/Mexico) $16.00; all others $46.00; foreign $80.00; foreign, air mail $180.00. 2 years Railroad Employees US/Canada/Mexico $30.00; all others $85.00; foreign $140.00; foreign, air mail $340.00. BOTH Print & Digital Versions: 1 year Railroad Employees US/Canada/Mexico $24.00; all others $69.00; foreign $120.00; foreign, air mail $220.00. 2 years Railroad Employees US/Canada/Mexico $45.00; all others $128.00; foreign $209.00; foreign, air mail $409.00. Single Copies are $10.00 ea. Subscriptions must be paid for in U.S. funds only. COPYRIGHT © Simmons-Boardman Publishing Corporation 2013. All rights reserved. Contents may not be reproduced without permission. For reprint information contact: PARS International Corp., 102 W 38th St., 6th Floor, New York, N.Y. 10018 Phone (212) 221-9595 Fax (212) 221-9195. For Subscriptions & address changes, Please call (800) 895-4389, (402) 346-4740, Fax (402) 346-3670, e-mail circulation@sbpub.com or write to: Railway Track & Structures, Simmons-Boardman Publ. Corp, PO Box 10, Omaha, NE 68101-0010.POSTMASTER: Send address changes to Railway Track & Structures, PO Box 10, Omaha, NE 68101-0010.
www.rtands.com
A safety reminder for summer
A
s a Chicagoan for the past 12 years, I, along with the rest of the metropolitan area, look forward to this time of year when we can take our oversized puffy coats and shove them in the back of our closets; confident that we will not need to call on them again until October. The weather is warming up and while our winter apparel gets to hibernate the summer away, the maintenance and construction forces in the rail industry are doing the opposite and starting to ramp up activity. The RT&S breaking news section on our website has been packed with stories about groundbreaking ceremonies for transit projects, Class 1s scheduling regular infrastructure maintenance and large capacity expansion projects progressing. With all this activity going on along our railroads, now is a good time to remind ourselves to be safe. Generally speaking, the industry is in a pretty good place as it pertains to safety. The Federal Railroad Administration (FRA) called 2012 the safest year on record. It was the fifth fiscal year in a row that the industry improved on all six of the FRA’s official safety performance measures, including the rate of grade-crossing incidents, human factor-caused train accidents, track-caused accidents, equipment-caused accidents, signal and miscellaneous train accidents and non-accidental rail hazmat releases. However, there is always room for improvement when it comes to safety. Railroads, municipalities and Operation Lifesaver continue to team up in public outreach efforts to educate communities about safety around railroads and the hazards associated with driving around gates and trespassing. Industry-focused outreach efforts encompass FRA’s risk reduction programs and system safety programs including the current collaborative effort with the railroads to educate
and raise awareness among industry employees of the dangers of using electronic devices on the job. Additionally, all of the major rail organizations and associations have their own safety efforts to benefit their members. There are many elements to the safety equation. Not only is there a commitment needed from every individual to keeping yourself and those around you safe, but there is also leadership’s role in safety and ensuring a good safety example is given all the way up the managerial ladder. The railroad, while an industry full of opportunity, can be an unforgiving environment. And as traffic increases and networks expand, a focus on safety will continue to play a prominent role in all of our day-to-day work. Beginning in June, RT&S will feature a series of guest editors over the next three months whose thoughts on the industry will be appearing on this page. We have three experts who will be tackling subject matter from various corners of the industry starting with Dr. Allan Zarembski in June, who will discuss railway engineering education. In July, Transportation Technology Center’s Semih Kalay will write about technology’s role in developing solutions to improve safety and efficiency. In August, Canadian Pacific’s Brent Laing, vice president of engineering, will provide a railroader’s perspective. We are very excited to have these three distinguished men on board as guest editors. Be safe this summer and I’ll see you in September.
Mischa Wanek-Libman, Editor
Railway Track & Structures
May 2013 3
INDUSTRY TODAY Supplier News Amsted RPS and Switzerland-based Schwihag AG formed a joint venture to manufacture and supply skl style rail fastening systems to the global heavy-haul freight market. Bombardier Transportation signed a contract worth approximately $195 million with the Florida Department of Transportation to provide operations and maintenance services for Central Florida’s SunRail commuter rail project. J.L. Patterson & Associates, Inc. (JLP), has been awarded a three-year, $6 million contract to provide supplemental engineering services for rail facilities and third-party coordination by the Los Angles County Metropolitan Transportation Authority Board of Directors.
www.rtands.com
TIGER’s fifth round will make $474 million available There will be a fifth round of Transportation Investment Generating Economic Recovery (TIGER) grants that will provide $474 million in funds to surface transportation projects, the U.S. Department of Transportation (USDOT) said. The Fiscal Year 2013 Appropriations Act requires that TIGER funds be obligated before October 1, 2014, which means USDOT will give priority to projects that are ready to proceed quickly. In addition to project readiness, primary selection criteria include improving the condition of existing transportation facilities and systems; contributing to the economic competitiveness of the United States and creating and preserving jobs; increasing transportation choices and access to transportation services for people in communities across the U.S.; improving energy efficiency, reducing dependence on oil and reducing greenhouse gas emissions and improving safety. “We’re taking the next step to keep moving our transportation infrastructure into the 21st century with a fifth round of TIGER funding. And, as excited as we are about TIGER 2013 here at DOT, I know that communities across the country are even more thrilled over this latest version of DOT’s favorite cat,” U.S. Transportation Secretary Ray LaHood wrote in his FastLane blog. The four previous rounds of the TIGER program provided $3.1 billion to support 218 projects in all 50 states, the District of Columbia and Puerto Rico. Congress dedicated $1.5 billion for TIGER I that funded 51 projects, $600 million for TIGER II that funded 42 projects, $526.944 million for TIGER III that funded 46 projects and $500 million for TIGER IV that funded 47 projects. Demand for the program has been overwhelming, with more than 4,050 applicants requesting more than $105.2 billion during the previous rounds. According to the USDOT website, the TIGER program “provides a unique opportunity for the U.S. Department of Transportation to invest in road, rail, transit and port projects that promise to achieve critical national objectives...Each project is multimodal, multi-jurisdictional or otherwise challenging to fund through existing programs. The TIGER program enables USDOT to use a rigorous process to select projects with exceptional benefits, explore ways to deliver projects faster and save on construction costs and make investments in our nation’s infrastructure that make communities more livable and sustainable.” In addition to multiple port and transit projects with rail elements benefitting from the program, several major freight rail-related projects have progressed with TIGER funds including Norfolk Southern’s Crescent Corridor, CSX’s National Gateway and the Chicago Region Environmental and Transportation Efficiency Program.
Railway Track & Structures
May 2013 5
INDUSTRY TODAY Supplier News Lilee Systems and Alstom are introducing a new suite of interoperable Positive Train Control products for rail lines; Lilee also partnered up with Cisco to define, design and implement an end-toend communication architecture for PTC systems. RailComm is providing its Domain Operations Controller system, as well as remote control blue flag protection with its RADiANT data radios, universal
6 Railway Track & Structures
Union Pacific plans to perform $38 million in trackwork in three states Union Pacific plans to invest $38 million in various infrastructure upgrades in Kansas, Wyoming and Nebraska. The railroad’s Kansas infrastructure will see $19 million in improvements along the line that runs between Salina and near Oakley. UP will install more than 133,000 crossties and more than 63,700 tons of ballast, replace more than a quarter mile of rail in various curves and renew the surfaces at 174 grade crossings. The project began in April and is scheduled to be completed by the end of July. The rail line between Granite and Rawlins, Wyo., will receive $12 million in infrastructure investment. The project, which is currently underway and will be completed by the end of July, will replace close to 69,000 crossties, install more than 27,000 tons of ballast, replace more then five miles of rail in various curves and renew the surfaces at 26 grade crossings. The UP line between Grand Island and
May 2013
North Bend, Neb., will see $7 million in trackwork performed. The work planned includes replacing 33,500 concrete crossties and replacing one switch. All three projects are part of the nearly 1,500 that Union Pacific will complete across its 32,000-mile network this year to help improve train operating efficiency, reduce motorist wait times at crossings and enhance safety. The railroad will spend an estimated $3.6 billion in 2013 on capital expenditures. “Union Pacific helps link businesses with consumers, suppliers and markets across the nation and around the world,” said Donna Kush, Union Pacific vice president - Public Affairs, Northern Region. “In addition to helping move customers’ goods more safely and efficiently, our investments support communities by reducing traffic congestion, facilitating industrial development and promoting economic expansion.”
www.rtands.com
INDUSTRY TODAY Detroit, Tempe streetcar projects advance with FTA approvals The Federal Transit Administration (FTA) gave the green light to the Detroit, Mich., Woodward Avenue Streetcar Project. With FTA’s environmental clearance, the project can now proceed to the next phases of design, right-of-way acquisition and construction. The project is a 3.3-mile, fixed-rail, atgrade streetcar system located entirely within the right-of-way of Woodward Avenue. It would operate in mixed traffic and run from Larned Street in downtown Detroit north to Chandler Street/Delaware Street, north of Grand Boulevard, in the New Center district. Twelve stations are proposed along Woodward Avenue, 11 with project implementation and a potential 12th station in the future. M-1 Rail, which will operate the streetcar service, expects to begin construction of the system south of Adams Street in 2013. Construction north of Adams Street will begin in 2014, which will include Michigan Depart-
www.rtands.com
Supplier News
ment of Transportation’s planned reconstruction of 2.5 miles of Woodward Avenue from Sibley Street to Chandler Street. M-1 Rail plans to complete the entire system and begin operations in late 2015. In other approval news, the FTA also approved Phoenix Valley Metro Rail’s request to enter project development for the Tempe Streetcar, a 2.6-mile extension of the Valley Metro system. Valley Metro said the approval marks the first step in receiving federal project approval and ultimately federal funds to build the extension. The approval allows for completing the environmental study and initiating the engineering phase. The project cost is estimated at $130 million. At this time, more than half of the funding has been identified through Proposition 400 regional transit tax and federal air quality dollars. The city of Tempe’s local transit tax funds all operations costs with a portion of the cost offset by passenger fare revenue.
switch machine/blue flag controller and blue flag indicators to a yard in Alliance, Neb. Tutor Perini/Zachry/ Parsons, a Joint Venture, has been identified as the best scoring team for the California High-Speed Rail Authority design-build contract for construction of the Madera to Fresno segment. Vanasse Hangen Brustlin, Inc., acquired Martin/Alexiou/Bryson, P.C., a Raleigh, N. C. transportation planning and design firm.
Railway Track & Structures
May 2013 7
INDUSTRY TODAY
U.S. Department of Transportation/Fast Lane
President’s proposed FY 14 budget includes $77 million for transportation
The proposed FY 14 budget includes $675 million for the Northeast Corridor. Both passenger and freight rail would benefit from the administration’s proposed budget.
President Obama released his fiscal year 2014 budget on April 10 and included $77 million for the U.S. Department of Transportation. The figure is six percent above the FY 2012 enacted levels and the administration says the budget provides immediate transportation investment in key areas. “A well-functioning transportation system is critical to America’s economic future. Whether it is by road, transit, air, rail, pipeline or waterway, Americans rely on our transportation system to move people and goods safely, facilitate commerce, attract and retain businesses and support jobs,” the administration wrote in the budget. Rail, both freight and passenger, has been placed in the budget spotlight with the president requesting $6.6 billion for the Federal Railroad Administration (FRA), up $5 billion from actual 2012 numbers, and $10.9 billion for the Federal Transit Administration (FTA), a slight increase from the $10.6 billion spent in 2012. The requested $6.6 billion for the FRA includes a
8 Railway Track & Structures
May 2013
multi-year high-speed and intercity passenger rail program that would establish a National High Performance Rail System (NHPRS) program. According to the administration, the NHPRS would use an integrated approach to improve rail safety, promote economic competitiveness, ensure cost-effective rail investments and support domestic manufacturing and jobs. Among the specific requests of the NHPRS, the Northeast Corridor would receive $675 million; state corridors would receive $300 million; long-distance routes would receive $800 million and national assets, those rail facilities that form Amtrak’s “backbone,” would receive $925 million. Also included in the FRA budget numbers: $3.7 billion for a rail service improvement program; $54.7 million to stimulate research, development and technology; $184.5 million for FRA’s safety and development programs and $35.3 million for safety-related research and development activities. FTA’s requested budget is meant “to strengthen transit safety oversight, bring bus and rail transit infrastructure into a state of good repair and provide new and expanded transit systems in communities nationwide.” Among the highlights of the proposed FTA budget is an additional $195 million in New Starts funding that would go toward two Los Angeles County Metropolitan Transportation Authority projects, the Regional Connector Transit Corridor and the Purple Line Extension, as well as Washington state’s Columbia River Crossing project, which includes a light-rail extension. In reaction to the proposed budget, U.S. Transportation Secretary Ray LaHood took to his FastLane blog and wrote, “This country needs–and its people deserve–a modern transportation network that helps create jobs, encourages businesses to expand and helps us compete in a global economy. That’s exactly the transportation system that the President’s 2014 budget for DOT seeks to build.”
www.rtands.com
PEOPLE A&K RAILROAD MATERIALS promoted Jeff Galyean to chief financial officer after Ray Yamasaki retired. California High-Speed Rail Authority hired Scott Jarvis as assistant chief program manager. Gannett Fleming hired Keyvan Pirbazari, PE, as senior program manager for its Transit and Rail Practice. Harsco Corporation appointed F. Nicholas Grasberger to senior vice president and chief financial officer. Iowa Mold Tooling Co. Inc. promoted Laurie Johnson to customer support manager. L.B. Foster Company promoted Bill Zimmer to director, Class 1 rail sales; hired David Sprinkle as regional Class 1 sales manager, handling CSX and Norfolk Southern; promoted Rick Steininger to director, technical rail sales; promoted Mark Hammons to general manager, rail sales West; promoted Joe Mahoney to director of rail sales; promoted Chuck Parks to regional sales manager, Southeast Sales District; promoted Jay Roach to regional sales manager, Midwest Sales District; named James Irr-Barr as sales representative in the Midwest Sales District; promoted Hector Herrera to regional sales manager, Latin America; promoted Victor Gonzalez to sales manager, Mexico; promoted Michelle Chapin to director of inside rail sales; hired Roger Babusci as an inside sales representative; named Hannah Posner as an inside sales representative and hired Nancy Spirko as rail inside sales coordinator. Metropolitan Transportation Authority will be served by Thomas Prendergast as chairman and chief executive officer and Carmen Bianco as New York City Transit acting president. Norfolk Southern promoted Tom Schnautz to assistant vice president of research and advanced technology; Gerhard Thelen retired March 31 as vice president operations planning and support. North Carolina Department of Transportation named Paul Worley director of the Rail Division. Stanec hired Thomas Westerman, PE, as railway bridge lead for its Heavy Rail Sector. STV named Richard Amodei as head of the firm’s Transportation and Infrastructure Division’s Northeast Region. T.Y. Lin International named Eric Winters, PE, to Rail Group manager for Southern California and Nevada. URS Corporation named Richard Reis vice president and northwest regional manager for its Infrastructure & Environment Division. www.rtands.com
Railway Track & Structures
May 2013 9
NRC CHAIRMAN’S COLUMN
Biggest and the best auction yet
The National Railroad Construction & Maintenance Association, Inc. 500 New Jersey Ave., N. W. Suite 400 Washington D. C. 20009 Tel: 202-715-2920 Fax: 202-318-0867 www.nrcma.org info@nrcma.org
10 Railway Track & Structures
The NRC’s 2013 Rail Construction and Maintenance Equipment Auction was Tuesday, April 16, at the Blackmon Auctions Yard in Little Rock, Ark., and it was our biggest one ever. I would like to thank Thomas Blackmon, Jr., for doing an outstanding job once again as host and auctioneer. The auction committee deserves a big “thank you,” as well, which was led by Danny Brown of RailWorks Corporation, Mark Gaffney of Stacy & Witbeck, Paul Laurello of Delta Railroad Construction, Inc., Greg Spilker of Progress Rail Equipment Leasing and Dan Samford of Herzog Contracting Corp. For the first time this year, we did the auction in conjunction with Union Pacific’s annual spring auction that it does with Blackmon and we believe this worked out well. In total, there were more than 300 pieces of equipment bought and sold for approximately $1.5 million. In addition to the dozens of contractors and railroads that consigned equipment to the auction, Balfour Beatty Rail, Inc., Railway Equipment Services, Delta Railroad Construction, Inc., and Cahaba Truck and Equipment all donated equipment to the NRC Auction this year. One hundred percent of the proceeds from the sale of that donated equipment goes into the NRC Safety, Training and Education Fund, which is used to fund all of the NRC’s safety activities, including the Safety Training DVDs, the pocket safety manual, tool box talks, RWP training materials and the safety award contest. To Mark Snailham and R.T. Swindall at Balfour Beatty Rail, Inc., Eddie and Barbara Stokes at Railway Equipment Services, Paul and Larry Laurello at Delta Railroad Construction, Inc., Paxton Estes and Kevin Barber at Cahaba and all of the other good people working behind the scenes at those companies, your donations to the auction and support of the NRC and the rail industry are truly appreciated. The Safety Training DVDs and other May 2013
safety materials are just the tip of the iceberg when it comes to benefits of membership in the NRC. Our website, www.nrcma.org, houses multiple resources to benefit members, including a “Bid Notifications” page with various links and information on new projects, a membership directory, legislative information and an industry c a l e n d a r. M e m b e r s h i p a l s o i n c l u d e s inclusion on the NRC bulletin distribution list, access to the NRC library of safety reference material and other industry resources and, of course, a discount for registration to the annual NRC conference held every January in either southern California or south Florida. Another resource to NRC members is Tabitha Layman. Tabitha is our grassroots coordinator and is available to help NRC members coordinate visits from congressmen, governors and other elected officials to members’ headquarters, construction sites and manufacturing facilities to demonstrate the importance of rail construction to the national economy. I encourage you to get in touch with Tabitha in the NRC office by calling 202-7151245 or e-mailing tlayman@nrcma.org. In addition to getting on the NRC e-mail list and reading about the NRC right here in RT&S, you can also follow the NRC on Twitter (“@theNRC”) and join our group on LinkedIn. Finally, don’t forget to save the date: The 2014 NRC Conference will be held at J.W. Marriott in Palm Desert, Calif., from Sunday, January 5, 2014, through Wednesday, January 8, 2014. Updated information will be posted on www.nrcma.org/go/conference. 2012 was the safest year in railroad history. Let’s make 2013 a better year yet. Work safe and keep those around you working safe. by Terry Benton, NRC Chairman www.rtands.com
TTCI R&D Recent developments in:
Alternative bridge ties for open deck steel bridges by Duane Otter, Ph. D., PE and Richard Joy, PE, principal engineers, TTCI.
TTCI researchers investigate lower life-cycle cost crosstie options for open deck bridges.
A
s railroad traffic increases, railroads are looking for longer lasting ties for their bridge decks. Railroad bridge engineers have noted increasing expenses and decreasing life of traditional solid sawn timber bridge decks in revenue service. This has prompted interest in alternatives that might provide lower life-cycle costs and has led Transportation Technology Center, Inc., to investigate alternatives to solid sawn timber ties for open deck bridges. For open deck bridge applications, ties in many cases serve as structural members, in addition to performing the functions of a conventional track tie. Such ties are sometimes referred to as span ties. For ties to perform adequately as structural members on open deck bridges, additional bending strength, shear strength and limited deflection are Figure 1: FFU bridge ties installed on a Class 1 railroad.
12 Railway Track & Structures
May 2013
required. Until recently, lack of design guidelines hindered development of alternative ties for open deck bridge applications. Under the direction of bridge engineers from Class 1 railroads, TTCI has been working in three areas to encourage development of improved bridge ties: (1) in-track testing of ties at the Facility for Accellerated Service Testing (FAST) and in revenue service, (2) laboratory testing of ties to determine suitability and (3) development of recommended practice for bridge ties in conjunction with committees of the American Railway Engineering and Maintenance of Way Association (AREMA).
Revenue service installations
Based on acceptable performance in laboratory testing by a Class 1 railroad and TTCI, one railroad made a pilot installation of fiber-reinforced foamed urethane (FFU) ties on an open deck steel bridge in December 2011 (see Figure 1). FFU is essentially a fiberglass material and ties made of this material have been used in Japan for a number of years. For this installation, the ties were dapped. However, no provision was made to provide relief for the protruding rivet heads on the top flange of the span. Instead, the ties were allowed to settle onto the steel under the weight of passing trains. The ties were installed using the railroad’s standard bridge tie insertion machinery. They are similar in weight and size to timber ties that have traditionally been used in this application. Girder spacing on this bridge is 6.5 feet center-to-center. For the girder spacing, the ties function as span ties, but the bending moments are much smaller than on spans with wider girder spacings, commonly up to approximately nine feet. TTCI is monitoring performance of the ties on this bridge. Periodic measurements include tie www.rtands.com
deflections and track gauge restraint. The installation is on a track that carries primarily empty coal trains and mixed freight traffic. Maximum normal car weight is 286,000 pounds gross rail load. Annual tonnage over this bridge is about 26 million gross tons (mgt) per year.
Tie installations on steel bridge at FAST
TTCI has installed two types of donated alternative ties and various solid sawn timber bridge ties on the steel bridge at FAST for testing.1 Douglas fir glulam (glued laminated timber) ties and solid sawn timber ties (white oak, Douglas fir and southern yellow pine) were installed on the 55.5-foot riveted steel span in late 2009. The solid sawn timber ties are serving as benchmarks for comparison. In early 2011, FFU ties were installed on the span. These ties are similar to those that were later installed on a Class 1 railroad. This span is much like many of the open deck steel spans still in revenue service in North America today. It has eight-foot girder spacing, making it an excellent test bed for structural bridge ties. The test span is subjected to 100-150 mgt per year of heavy-axle-load traffic. Figure 2 shows the tie layout for the FFU ties. Note that there is one long Douglas fir walkway support tie separating two adjacent five-tie panels. The bottoms of the FFU ties were milled so they would fit over the protruding rivet heads on the top surface of the steel girder on the bridge at FAST. The ties at FAST were not dapped. Note the difference in these details compared to the revenue service installation of FFU ties. There are two lines of rivets on each of the top flanges at FAST. The milling pattern allows the ties to move longitudinally along the top flange. During installation at FAST, the milling facilitated quick and accurate lateral location of the ties on the girders. The milling of the FFU ties to clear the rivets was performed based on the vendor’s recommendation. None of the timber or glulam ties installed on the span were milled or dapped. The timber ties were set directly on top of the rivets and allowed to seat under train traffic, as were the FFU ties in the revenue service installation. The Douglas fir glulam ties are installed in two similar panels at the east end of the span. Nominal tie size for both the glulam and FFU ties is 10 inches wide by 12 inches deep by 12 feet long. TTCI fastened the ties to the steel girder using hook bolts every fourth tie. Rail and tie plates were fastened using cut spikes. All ties were fastened to an outside spacer timber with lag screws. Note that this installation is typical of North American bridge installation practice; in this case, closely following plans used by the Class 1 railroad that donated the steel span.
Testing at FAST
Thus far at FAST, the ties have been subjected to 315,000-pound gross rail load traffic at 40 mph. The test train at FAST operates in both directions over these ties. Accumulated tonnage on the solid sawn timber and glulam timber ties is 448 mgt. Accumulated tonnage on the FFU ties is 268 mgt. To date, none of the ties has required any maintenance or replacement. Various species of solid sawn www.rtands.com
timber bridge ties installed at the same time have not required any maintenance or replacement. A rail change has resulted in the need to insert plugs into spike holes. Standard wood plugs were used for all ties, including the FFU ties. Measurements of tie deflections were taken at mid-tie and at each rail seat. Figure 3 shows the average deflection values at center of tie and beneath the rail seats for two different ties of five various types: (1) southern yellow pine, (2) Douglas fir (solid sawn), (3) white oak, (4) Douglas fir glulam and (5) FFU. These deflections are all within the recommended range of values for alternative bridge ties.2 As expected, the tie center deflections are greater than those under the rail seats for all tie types. The deflection values measured at FAST for the various tie types reflect the same relative deflection trends as measured in laboratory tests. 3 This trend provides additional support for the recently-recommended laboratory guidelines.2, 4
Laboratory experiments
A Class 1 railroad and TTCI have performed laboratory tests to evaluate the performance of various ties in terms of the following tie properties: • Spike insertion force • Spike pullout resistance • Tie plate cutting • Lateral gauge restraint • Bending The bending test provides an indication of the performance of the tie as a structural member. The other tests quantify aspects of the ability of a tie to hold gauge, surface and alignment. Selected ties that pass laboratory tests have been installed on a trial basis on open-deck steel bridges, both at FAST and in revenue service. Some previous experimental ties that passed the laboratory tests were installed on selected bridges on one railroad. One early experiment with a steel-reinforced plastic composite tie was initially successful. But issues, such as the inability to consistently meet design specifications and inadequate fire resistance led to discontinuance of use of that particular tie design.
Bending test
When a bridge tie must also function as a structural member (span tie), it is essential that it pass a bending test. The test rig simulates the girder spacing of the span and load points of the rail. Spacing of the reaction points was set up to replicate center-to-center girder spacing (eight feet). Spacing of the load points was 60 inches for standard gauge track. For both the Douglas fir glulam ties and the FFU ties, two randomly chosen ties were tested in the laboratory. These ties were checked for defects before testing. A deflection test and a design load test were performed in the laboratory. The deflection test measured minimum and maximum tie center deflection under loads of 27,000 pounds (live load before factor of safety) at each rail seat. Under the live load of 27,000 pounds, all ties stayed below the recommended maximum deflection of 0.38-inch for tie center deflection for an eight-foot Railway Track & Structures
May 2013 13
TTCI R&D Figure 2, Top: FFU bridge deck ties being installed on the steel span at FAST.
girder spacing. All ties provided tie center deflections greater than the 0.11-inch recommended minimum for an eightfoot girder spacing. Values compared favorably to previously-defined minimum and maximum deflection values.4 A design load test was also performed. For this test, a load of 53,000 pounds per rail (live load including factor of safety) was applied. A visual inspection was made to the tie after this test to check for any damage. All ties performed well under the 53,000-pound load. No damage was observed. The maximum bending moment under this loading condition is about 106,000 foot-pounds.
Other laboratory tests
Figure 3: Illustrates the average deflection of various solid sawn timber and alternative ties under the test train at FAST.
14 Railway Track & Structures
May 2013
Testing by the Class 1 railroad included compression tests to determine the ability of the FFU material to resist deformation and cutting under compressive loads (tie plate cutting). Deformation of tie samples was barely discernible after the test. These results are much better than for any previously tested materials. In tests for spike insertion force and spike pullout resistance, the FFU ties performed favorably compared with many of the timber species.5 Testing was also perfor med by applying a cyclic lateral load to a cut spike dr iven into the tie to quantify lateral gauge restraint. The maximum lateral deflection
www.rtands.com
per cycle was monitored. The total lateral movement under load was also monitored. More than five million cycles were applied. Based on past experience, sufficient cycles were accumulated to indicate that the FFU material performs better in this lateral gauge restraint test than any other timber or plastic composite tie materials previously tested.5
Recommended practice
There were no industry guidelines for railroad open deck bridge ties before publication of the 2012 edition of the AREMA Manual for Railway Engineering, other than the guidance for timber ties provided in Chapter 7. In order to develop guidelines, railroad bridge engineers worked with AREMA Committees 30 and 7 and TTCI researchers on the development of recommended practices for alternative bridge deck ties as new AREMA recommended practices. The new recommended practices for “Engineered Composite Ties for Open Deck Bridges” are now found in Chapter 30, Part 5.6 of the Manual for Railway Engineering. The new practice references existing AREMArecommended practices for performance as a track tie, with additional recommendations for structural bending ties, as are common on steel deck plate girder spans. The new provisions are based on performance testing independent of material properties. The primary design load is based on the Cooper E-80 wheel load of 40,000 pounds with 100-percent impact, distributed evenly over three ties, per AREMA Chapter 15. 2 Note that at FAST, the nominal wheel loads are 39,375 pounds, nearly the same as the design load. Other provisions address workability and fire resistance, for example. Many of these issues are handled by reference to material in Chapter 30 that applies to conventional track ties.
Acknowledgements
The authors are grateful for the assistance an d c ontr ibu tion s of Class 1 railroad bridge engineers for donations of both solid sawn and glued-laminated timber bridge ties for this study and also for the donation of the FFU ties from Sekisui Chemical Co. Ltd., represented in Nor th America by Sumitomo Corporation of America. Thanks are also g iven to the AREMA Committe e 3 0 - Ties, subcommittee on engineered composite ties, chaired by Richard L a m p e a u , f o r i t s wo r k o n t h e development of the new AREMA recommended practices for engineered composite br idge ties. AREMA Committee 7 - Timber Structures, ch aired by D r. Gar y Fr y, also provided valuable input and assistance in developing the new AREMA recommended practices. This study was funded in par t through the Association of American
Railroads’ Strategic Research Initiatives Program.
References 1. Otter, D. and Tunna, L. April 2012. “Evaluation of Alternative Open Deck Bridge Ties at FAST.” Technology Digest TD-12-008. Association of American Railroads Transportation Technology Center, Inc., Pueblo, Colo. 2. American Railway Engineering and Maintenance of Way Association. 2012. Manual for Railway Engineering, Lanham, Md. 3. Joy, R., Ninness, K. and Duane Otter. October 2011. “Benchmark Testing of Timber Open Deck Bridge Ties.” Technology Digest TD-11-036. Association of American Railroads, Transportation Technology Center, Inc., Pueblo, Colo. 4. Joy, R. and Otter, D. October 2011. “Alternative Material Ties for Open Deck Bridges.” Technology Digest TD-11-035. Association of American Railroads, Transportation Technology Center, Inc., Pueblo, Colo. 5. Otter, D., Patton, R. and Joy, R. September 2012. “Developments in Alternative Bridge Ties for Open Deck Steel Bridges.” Proceedings, AREMA Annual Conference, Chicago, Ill.
Future testing
The perfor mance of the test ties will be monitored in revenue ser vice and at FAST for a period to be determined. Inspectors will visually inspect the condition of the ties and observe them under traffic on a regular basis for any signs of degradation or loss of performance. www.rtands.com
Railway Track & Structures
May 2013 15
NRC Rail Construction Project of the Year:
Utah Transit Authority FrontRunner South by Mischa Wanek-Libman, editor
The joint venture of Stacy and Witbeck, Inc., and Herzog Contracting Corp. utilize innovation and fluid communication to safely construct a 45mile commuter rail line.
J
uggling the var ious elements of a 45-mile, $525-million commuter rail project is challenging enough in railroad construction. Add to it the need to closely work with local communities, transit agencies and a freight railroad to make sure safety is observed and communication remains open and it becomes clear why Stacy and Witbeck, Inc./Herzog Contracting Corp., a Joint Venture, was awarded the National Railroad Construction a n d M a i n t e n a n c e A s s o c i a t i o n ’s 2 0 1 2 R a i l r o a d Construction Project of the Year, which was presented at the association’s annual conference in January 2013. “The safety record, scope of the project and the cost containment measures utilized in this multiyear project are what made the Stacy and Witbeck/Herzog Contracting Corp. project stand out. With more than million man hours worked in challenging situations without a single lost time accident, the companies have demonstrated that safety was the absolute top priority. The coordination and interface with major project stakeholders, such as Union Pacific, 14 cities, two counties and the Utah Department of Transportation (UDOT) was impressive and displayed a commitment to quality work in a partnership environment,” the NRC said of the project. The FrontRunner South project is par t of Utah Transit Authority’s (UTA) FrontLines 2015 program, 16 Railway Track & Structures
May 2013
which is composed of five UTA rail projects that will be in operation by 2015 and will expand the existing rail network by 70 miles. The FrontRunner South project scope of work included 30 bridges, two million cubic yards of earthwork, 50 miles of roadbed preparation and trackwork, 40 joint (with UP) at-grade crossings, signaling work and station construction. The project began construction in August 2008 and began carrying commuter s between Salt Lake City and Provo in December 2012.
Challenges known and unknown
The project construction contract utilized a modified design-build process known as Contract Manager/General Contractor (CMGC). According to Clayton Gilliland, project manager with Stacy and Witbeck, the CMGC format helped the joint venture become familiar with the scope of work because the companies were able to Above: Bridge construction within the Jordan Narrows area. The UP work train is involved in FrontRunner South project-related work and is traveling to an adjacent project site that required mainline renewal by the railroad. The train is towing UP’s track laying machine and related track materials. www.rtands.com
UTA FrontRunner south
work closely with the project designer and provide input throughout most of the design process, which allowed for accurate pricing of materials and work prioritization. The CMGC format also allowed the companies to tackle the known challenges of the project, such as fitting the commuter rail corridor inside Union Pacific’s existing right-of-way. Gilliland notes that several industries are served off of the UP mainline. If the commuter rail project utilized the same side of the track as the various industries, the services would frequently intersect. “The alignment itself was an engineering challenge because you’re trying to fit it in between the existing mainline and fit it on the right-of-way. UTA and UP made a decision that we would [build the commuter route] on the east side of the UP for the northern third of the job and on the west side of the UP for the southern two-thirds of the job and that fit better with industries and properties,” said Gilliland. The joint venture constructed a flyover where the project crosses over the UP from east to west, in south Jordan. This flyover consisted of a 1,000-foot bridge constructed in the middle of a curve to carry the UTA commuter traffic over UP’s freight traffic. Gilliland also said a five-mile stretch, known as the Jordan Narrows, right in the middle of the project presented another
www.rtands.com
engineering challenge. “There’s a section where we parallel the Jordan River and it’s very remote, so there’s no access to the work except for a cut out at each end of the five-mile stretch,” said Gilliland. He says that in addition to the multiple irrigation canal crossings, which could only be worked on during the winter so farmers were not affected during the summer season, the project needed to cross the Jordan River at two locations and a portion of UP’s line needed to be relocated in order to make room for the FrontRunner project. “Sequencing the work, accessing the work and optimizing the alignment through the Jordan Narrows was a
“The safety record, scope of the project and the cost containment measures utilized in this multiyear project are what made the Stacy and Witbeck/Herzog Contracting Corp. project stand out.”
Railway Track & Structures
May 2013 17
uta frontrunner south
big known engineering challenge,” said Gilliland. While the known engineering challenges allowed for proper planning of solutions, there were a few situations that cropped up during the course of the project, which required innovative thinking on the part of the joint venture. An example of this was making sure the FrontRunner South construction fit into the various project stakeholders’ requirements. UP requested the project be constructed 40 feet from its mainline instead of 25 feet, which pushed the project into private property requiring additional property acquisitions that needed to be prioritized to keep work progressing. Additionally, the project included building several grade separations over UDOT roads. During FrontRunner South construction, Gilliland says UDOT was in the middle of an accelerated bridge construction campaign that severely limited roadway outages and required close to zero impact to the traveling public. “We had to change our means of bridge construction,” said Gilliland. The bridge designs were standardized and included precast elements that were a complete assembly, including deck, girders, ballast, retaining walls, walkway and handrail. Not only did this reduce traffic impacts during construction, but helped as a cost containment measure, as well. “We also would work around the clock on the weekends to drill shafts so we could get out of the way by Monday morning and have the road completely opened,” said Gilliland. While the project’s var ious challenges kept all stakeholders on their toes, the common theme with every solution seemed to be rooted to good communication. Gilliland says Stacy and Witbeck was part of the FrontRunner North construction and the relationship with UP was a continuation for FrontRunner South. “We had quite a bit of momentum with UP, but they would send a representative into our weekly planning sessions so we would describe to them in detail the work we had planned for the following week. They had representatives on the ground with our crews and during job briefings, where work being done that day would be described, the UP rep. could weigh in,” said Gilliland. “With UDOT, we met with them bi-weekly to talk about upcoming work and we met regardless if there were any issues. We just met to keep the dialogue open and I think that was effective. The rest of the municipalities, we provided them updates, such as stakeholder luncheons, to let them know where the work was and what was coming up.”
Safety factor
As with any project this size, safety is a top priority. The project expended more than two million man hours and averaged more than 325 persons engaged on site every day with zero lost time accidents. In the NRC Project of the Year application, the joint venture noted several contributing factors to its safety success, including: • Unwavering support of the safety program from UTA and the 18 Railway Track & Structures
May 2013
www.rtands.com
uta frontrunner south
The relocated UP mainline and new FrontRunner South line in the Jordan Narrows area.
joint venture’s corporate leadership. • The joint venture felt strongly that self-performed work (60 percent) gave it an extraordinary platform to set the
20 Railway Track & Structures
May 2013
pace for safety performance in a very tangible way and earn the respect of the project’s subcontractors. • Continually working to convince the
project’s individual craft employees that the joint venture cared for their individual wellness. • Each day began with a START card, enhancing hazard awareness and each week began with an all hands safety meeting that included a var iety of training topics, recognition and awareness. A d d i t i o n a l l y, e ve r y c r e w wa s encouraged to “Take 30” minutes ever y week for safety to review the site conditions, discuss the operational risks and generally recharge the safety focus. • A “PPE Quick Reference Guide” was issued that visually identified the personal protective equipment recommended for all common power tools. • The joint venture held a belief
www.rtands.com
UTA FrontRunner south
The integration team, which includes test engineers, contractors, designers and operations personnel, escorting the first test train set along the alignment. Testing in the first zone began in June 2012. There were five test zones, each near 10 miles in length.
that planned work decreases the risk of incidents. Another safety element was the “Pinch Point Protection” system the team developed with UP. Gilliland says there were areas along the project that did not have adequate right-ofway to allow normal track clearance between FrontRunner and UP. The “Pinch Point Protection” system was designed to shut down both railroads in the event any equipment encroaches into the adjacent railroad’s operating envelope. According to Gilliland, the system consists of steel posts with an electrical circuit that were installed between FrontRunner
www.rtands.com
and UP tracks every 100 feet. If the post is knocked over by a derailed train, the circuit would be interrupted and it would shutdown both tracks.
Measure of success
In addition to being awarded NRC’s Project of the Year, the project won the Utah AGC “Par tner ing
Railway Track & Structures
May 2013 21
uta frontrunner south The joint venture and UP coordinated work along the 40 grade crossing locations to minimize traffic impact and work more efficiently. During one stretch, the team executed roadway and track improvements at 23 locations in 26 weeks.
Project of the Year” in 2011; Keith Tarkalson, general superintendent and construction manager, was awarded Utah AGC “Superintendent of the
22 Railway Track & Structures
May 2013
Year” in 2011 and the project won Stacy and Witbeck’s “Safest Project of the Year” in 2011. While the recognition is certainly
nice, for Gilliland, being able to provide a transportation alternative to the region was also a great accomplishment. “There is no other paralleling freeway or reasonable paralleling surface street, there is only one other option and that’s I-15. If there is a weather day or a traffic accident, the commute is just impossible,” said Gilliland. “Providing that option and seeing the excitement from everyone on opening day and knowing the commuters are adding two hours of useful time to their day because they’re on the train, not whiteknuckled, stressful driving, is what I think is pretty cool.”
www.rtands.com
Ditching and drainage efforts that
go with the flow Suppliers provide resources to keep roadbeds clear of water. The ends of Snap-Tite pipe are designed to snap together in the field during the relining process. by Jennifer Nunez, assistant editor
W
ater seepage can be a real hazard to the railroads, causing track damage and emergency situations when flooding occurs. Proper drainage along the lines ensures a healthy operation and suppliers are on top of the latest technology and innovations to help railroads achieve just that.
BTE
Ballast Tools Equipment Company has been building and upgrading equipment that includes both hi-rail and off-track options this past year. The company focuses on fast, effective and efficient use of track time and resultsoriented production. BTE has various sized excavator options and new large capacity back-hoes with hi-rail for multiple situations. “Customers want the ability to perform on-track, as well as off-track,” noted Matt Weyand, sales engineer. “As a result, our hi-rail systems are becoming increasingly popular. These come in a variety of different shapes and sizes, depending on the customer applications and requirements. Most recently, we have ranged from smaller CAT 312 excavators, up to larger CAT 450 backhoes with a full range of hi-rail capabilities and attachment options.” For larger projects, the BTE Beast Undercutter is offered. For tight applications, with off-track maintenance, positioning a ditching bucket can be difficult, he says. “That’s where a combination of a hi-rail system and Rototilt attachment manipulation comes in handy; because you can match the angle of the track without making a ton 24 Railway Track & Structures
May 2013
of adjustments,” said Weyand. “It’s a super time saver and with shortened work windows, that’s a way big deal.” While BTE does not perform drainage jobs, the company has seen some additional challenges with fouled track and turnouts serviced by its equipment customers. This track fouling has been with a variety of materials, including coal, iron ore, fine powders and dust, as well as good, oldfashioned mud. “We have found that our aggressive digging chains and attachments have the durability and performance life to work in these difficult situations ever y day,” explained Weyand.
GREX
Georgetown Rail Equipment Company’s (GREX) Self Powered Slot (SPS) machine is a train that consists of gondola cars stretching up to 430 feet in length. With an on-board excavator, an experienced GREX operator and remote-controlled power, the SPS is offered to customers as a ditching solution. Additionally, GREX has recently implemented a new operator training program occurring on a bi-annual basis. The SPS of today has morphed from the original SlotTrain design, which required a work train for power. The SPS was conceived after demand for self-powered equipment; however, GREX still offers the traditional SlotTrain for those customers who may not need an SPS. With all of the capabilities of an SPS, other than being self-powered, the original SlotTrain still offers customers a ditching solution. www.rtands.com
www.rtands.com
Railway Track & Structures
May 2013 25
Ditching and Drainage
into the adjacent track’s territory, which means work can continue, even in high-traffic areas. We’ve also added rototilts to each excavator, which allows the operator to maneuver the bucket 360 degrees and tilt up to +/- 40 degrees. This gives our operator increased flexibility with the bucket, allowing them to more precisely form the drainage area. This feature, along with varying bucket sizes depending on the particular job, allows us to enact extreme precision when ditching.” GREX takes pride in operator expertise. The average GREX SPS operator holds eight years of experience working on the railroad. In that time, these operators have performed work across all regions of the United States and are regularly asked to make recommendations based on their proficiency for ditching. “With a bucket reach of 34 feet and 400 tons of capacity, our operators can handle just about any ditching scenario possible,” stated Turner.
Herzog
Top, the Herzog MPM digging a ditch to help keep muddy waters off the tracks. 450 Hi-Rail Backhoe with ditching bucket from Ballast Tools Equipment.
“In our continuous effort to increase production and improve safety, all SPS trains are now equipped with zero-turn radius excavators,” noted Lynn Turner, vice president of marketing and sales. “This feature allows for work to be performed when working on double main territory without fouling the adjacent track. Special lockouts prevent the excavator from physically moving 26 Railway Track & Structures
May 2013
Herzog Railroad Services, Inc. (HRSI), placed the first Multi-Purpose Machine (MPM) into service in 1999. The machine was designed to provide railroads with a piece of work equipment that could execute numerous tasks utilizing various attachments within a minimal amount of time. “The MPM is a one-of-a-kind piece of work equipment,” noted Tim Francis, vice president of marketing. “It is operated by remote control with just one qualified HRSI operator. The MPM’s excavator rides a bogey that sits atop a gantry system that traverses the HRSI manufactured well cars. This allows us to have virtually unrestricted access to the material in all of the cars at all times. The MPM’s 27-foot reach makes it perfect for any task within its radius.” A standard MPM is outfitted with a bucket, grapples and magnet, but upon request, a tree shear, brushcutter or auger can be added. The MPM is capable of traveling under its own power at up to 50 mph or it can be moved in train service at the rear of the consist. The zero-turn radius track hoe allows it to work on multiple track mainlines or in yards. The MPM has the ability to load up to 240 cubic yards per hour and the entire machine can transport almost 480 cubic yards of material. HRSI is currently using its Light Detection and Ranging (LIDAR) truck technology to develop a program, which will allow the company to survey ditch lines, which the railroad has identified as an area of concern. “The human subjectivity is removed from the equation and the MPM operator will be able to cut an even more accurate grade than without the assistance of the LIDAR scan,” Francis noted. “The MPM track hoe will be set up with a computer that will aid the operator by providing them with a 3D view of the track and ditch lines. The computer screen will identify areas where the grade is correct, where backfilling of material is needed or anywhere material needs to be removed.” The company notes that the biggest advantage of the MPM is the final product it leaves behind. The newly cut ditch lines allow for unrestricted water flow and railroad subgrades can properly shed water, which will help reduce www.rtands.com
new fouled ballast locations and subgrade failures.
Loram
“Customers continue to reinforce that drainage is of utmost importance for providing a sound track structure,” explained Scott Diercks, product development manager for Loram Maintenance of Way, Inc. “The success of any ballasted track design is directly related to the ability of the track bed to drain and the proper maintenance of the overall drainage system. An effective drainage system handles the rapid runoff of storm water from the ballast, across the subballast surface and into a properly designed parallel drainage system.” Loram’s drainage products include shoulder ballast cleaning, ditching, specialty excavation, undercutting and track lifting. Inspection technologies, such as ground penetrating radar and LIDAR, continue to evolve and become standard tools for assessing and planning work needs. Loram says it has experienced an increasing demand for ditching and drainage services from transit and freight railroads domestically and internationally. Benefits of a well-drained roadbed include less geometry degradation and increased component life. Loram says that by coupling a ditching program with a ballast-cleaning program, railroads are able to create a free-flowing track structure that provides a dependable infrastructure and better service. As for the Loram Track Lifter Undercutter, it can lift track up 12 inches in one pass up to four miles per hour. The track lifting process creates a new subballast layer, establishing more permeable ballast and an overall stronger structure, Diercks notes. Additionally, Loram offers its fleet of Railvacs and Badger Ditchers to its customers. Loram says customers utilize the equipment to address unique maintenance needs, such as ditching, cribbing/undercutting mainline mud spots, installation of drain tiles and culverts and undercutting switches and diamonds. The Badger Ditcher is designed to provide economical, high-production solutions to drainage problems, such as overgrown and ballast-filled ditches and slope erosion. The machine is capable of moving more than 800 tons of material www.rtands.com
Railway Track & Structures
May 2013 27
Ditching and Drainage hard-to-reach areas.
NMC
NMC Railway Systems currently offers the Grip N Ditch bucket with 360-degree rotation in its attachment product line. The bucket, with the purpose build gearbox drive systems, is said to work effectively on stabilizing areas for flood control and other clean-up projects. The Grip N Ditch is best utilized on CAT backhoes and excavators. NMC Railway Systems can accommodate ditching and drainage projects with a full line of Cat Work Tool ditching buckets with drainage systems. Cat skid steers also have trenching attachments. One of the latest features for its ditching and drainage projects is the addition of the tilt function on Grip N Ditch buckets larger than 54 inches. Featured exclusively on the 324 HighRail Excavator, the bucket includes a side tilt option up to 20 degrees. “Utilizing a Grip N Ditch bucket on our line of hi-rail excavators allows operators to work and trench in remote areas of track line,” said Chuck Haskell, sales manager. “At NMC Railway Systems, we continually look for ways to improve track travel and track safety.”
Plasser American
Top, Loram’s Railvac excavating ballast. NMC Railway Systems’ 312 High-Rail Excavator with ditching bucket.
every hour at depths up to six feet and dumps waste up to 35 feet from the center of the track. Loram’s Railvac is designed for specialty ballast excavation in areas of tight clearances, such as ballast deck bridges, switch winterization, tunnels, culverts and hard-to-reach drains. “The Railvac is a robust machine 28 Railway Track & Structures
May 2013
designed to work on tough Class 1 railroad conditions, but flexible enough to accommodate transit and commuter railroads,” explained Diercks. The Railvac applies 5,000 pounds of force and is coupled with a rotating nozzle to break up tough material. The machine also features remote joystick controls and nozzle flexibility to reach
Clean ballast is extremely important to maintain track geometry, notes Plasser American Corp. and scheduled ballast undercutting/cleaning to create proper drainage and removing fouled material from the track is the first step to long-lasting track. Plasser supplies machines, such as the RM-80, which can undercut and clean plain track, as well as switches from either side, eliminating the need to turn the machine around; high-capacity double screening unit machines, such as the RM-2003 Dual Shaker UndercutterCleaner and the RM-802 High-Speed Undercutter-Cleaner, which works with pre-dumped ballast and the FRM802 Shoulder Cleaner. “In instances where the track quality cannot be maintained due to weak subgrade or continuous fouling from the subgrade, a subgrade renewal machine may be used to correct the problem,” explained Plasser. www.rtands.com
Ditching and Drainage
“Subgrade renewal machines remove the ballast layer, as well as the subballast layer and replace it with a formation protection layer and a layer of ballast. The formation protection layer prevents material from coming up and fouling the ballast, prevents water from seeping down into the subgrade and distributes the load on the track over a larger area, reducing the stress on the subgrade by increasing the bearing surface.” Plasser’s PM 200-2 R Formation Rehabilitation Machine, according to the company, can remove the ballast and subballast, recycle the removed material and then install a compacted formation protection layer and a ballast layer all in one pass. All work is performed without physically removing the track, allowing for shorter track outages. Plasser recently developed the URM-700 High-Capacity Switch Undercutting/Cleaning Machine. The URM-700 is equipped with two shoulder cleaning chains and an undercutting chain that is capable of undercutting both tracks of a switch or crossover in one pass. The machine can also be utilized for spot undercutting/cleaning work. Initially, the URM-700 removes the shoulder on the side of the switch or crossover where the undercutter chain will be inserted. Then, the undercutting chain is inserted into the track, which can be done on either side of the machine and
30 Railway Track & Structures
May 2013
the machine undercuts the switch or crossover by rotating the undercutter chain under the track until the entire switch or crossover has been cleaned. “The greatest advantage of the URM-700 over conventional switch undercutters is that all excavated material is conveyed to a shaker car, cleaned by the vibratory shaker unit and the reusable ballast is inserted back into the track behind the undercutter chain and fouled ballast is discharged to the side of the track,” noted Plasser. “The geometry of the switch or crossover is maintained to a high level by roller clamps that hold the track during undercutting operations. Tamping and dynamic track stabilization can be performed immediately following undercutting. The URM-700 will be debuted at the 26th International Exhibition for Track Technology (iaf) from May 28 – 30, 2013, in Münster, Germany.”
RCE
“With the erratic weather so far this spring, ditching and maintaining proper drainage is a huge issue this year for railroads,” explained Dennis Hanke, sales manager of Rail Construction Equipment Co. “We’re seeing a higher demand for equipment to address these issues.” According to Hanke, ditching from on-track using
www.rtands.com
Ditching and Drainage
hi-rail excavators and dump car ts has been in high demand this year and for that, RCE offers its customers the 225D Hi-Rail Excavator, along with its hydraulic side dump cart. The 225D Hi-Rail Excavator is equipped with a hydraulic tilting ditching bucket, which is said to improve the ability to maintain proper drainage. This product provides the ability to clean up drainage issues form on- or off-track. When combined with the RCE Hydraulic Dump Cart, the customer has the ability to also remove unwanted material from the ditched areas.
Snap Tite
Plasser’s URM-700 High-Capacity Switch Undercutting/ Cleaning Machine.
32 Railway Track & Structures
May 2013
Snap-Tite is proud to say that culvert rehabilitation is becoming more widely accepted in the industry and AREMA has recognized it as a recommended practice for fixing drainage issues. “Railroads are looking for ways to reduce bridge inventory,” explained Mitch Goss, railroad project manager. “One way is to convert bridges into culverts using large diameter high-density polyethylene pipe (HDPE).” One trend Goss has noticed this year is the increased use of a bullet nose on one end of a pipe used for sliplining. The
www.rtands.com
Ditching and Drainage
The RCE 225D High-Rail Excavator ditching and cleaning up rock slides on the Union Pacific.
bullet nose allows for the liner pipe to push through ballast that has fallen through separated joints. Snap-Tite is a no-dig lining method of drainage culverts. The Snap-Tite culvert lining pipe system is available for
34 Railway Track & Structures
May 2013
use in drainage culvert repair/reline projects. Its patented male/female machining ends of the HDPE allows it to be “snapped” together, piece-by-piece and pushed into the full length of the existing pipe. It is available in lengths from two to 50 feet long and is available for culverts up to 84 inches in diameter. However, larger diameters are available upon request. Snap-Tite focuses on both culvert rehabilitation and bridge replacement. Specific challenges for culvert rehabs are recognizing the problem and forming a plan before it’s too late, Goss says. “In many cases, the culvert collapses and rehabilitation is no longer an option,” he explained. “Snap-Tite wants to work with the railroads to generate a maintenance plan for fixing culverts. The specific challenges for bridge replacement are addressing the loading and hydraulic concerns of creating a new structure. When you tear down an old bridge and replace it with a culvert made of HDPE, structural and hydraulic analysis must be done.” Snap-Tite currently works with Class 1 railroads Union Pacific, CSX, BNSF and Canadian Pacific; passenger railroads Amtrak and Pan Am; regional railroads Florida East Coast Railway and Montana Rail Link and shortlines Iowa Interstate and Wisconsin & Southern.
www.rtands.com
The National Railroad Construction and Maintenance Association has experienced healthy growth by keeping the needs of its members in the forefront. Attendees view equipment at the NRC’s 2013 Railroad Construction and Maintenance Equipment Auction, which was held April 16, 2013, and benefits the NRC Safety, Training and Education Fund.
NRC is stronger than ever
R
ailway Track & Structures asked National Railroad Construction and Maintenance Association (NRC) Chairman Terry Benton of Colo Railroad Builders, NRC President Chuck Baker and NRC Operations Manager Ashley Bosch about the past year and what they believe is in the future for the NRC.
RT&S: Terry, you are in your second year as NRC Chairman. What goals have you established for the NRC to be accomplished during your tenure and are you making progress towards those goals? Terry Benton: My goals for the organization are to continue promoting the importance of the NRC organization to the membership by: • Listening to our members and helping determine where the NRC can assist in meeting their needs, whether in construction and maintenance of track, structures, communication and signals or any of the other disciplines that the NRC represents; • Continuing to maintain the momentum of the NRC’s current legislative and safety initiatives and • Promoting the NRC to non-members and customers to expand the membership of the NRC in order to build a stronger voice in Washington and to more fully represent the entire industry. The NRC will continue to provide support, leadership and advocacy for the industry in the safety and legislative/regulatory areas. I have been building on the legacy of leadership left by Past Chairmen Jim Perkins of Loram, Jon McGrath of McGrath LLC, Manny Ramirez of Mass Electric, Rick Ebersold of Herzog Services, Larry Laurello of Delta Railroad Construction and Scott Brace of RailWorks and will www.rtands.com
continue to grow the organization as my predecessors have. NRC membership has grown more than 75 percent in the past six years, from 184 Member Companies in 2006 to 326 members in 2012. We have been joined by 65 new members in the past 12 months alone. Our Membership Committee, chaired by Stephanie Freeman of Coleman Industrial Construction, is doing a great job. Stephanie is joined on the committee by David Armstrong of Commercial Insurance Associates, Steve Bolte of Progressive Railroading, Danny Brown and Jim Hansen of RailWorks, Mike Choat of Railroad Controls Limited, Bob Hirte of Hamilton Construction, Phil McDonald of Koppers, Jody Sims of Kiewit Infrastructure West, George Sokulski of RT&S and Dave Stein of Holland Company. RT&S: You mention expanding the membership. What benefits does the NRC offer to its current members and potential new ones? Benton: The Membership Committee and our Washington D.C. staff, including NRC President Chuck Baker, Director of Operations Matt Ginsberg, Operations Manager Ashley Bosch and Grassroots Coordinator Tabitha Layman, have done an excellent job of identifying and recruiting companies in our industry who will benefit from being NRC members. The NRC exists to support rail contractors and suppliers, expand their business opportunities and protect them from harmful laws and regulations. We are the only organization entirely dedicated to this purpose. We keep a close eye on all issues that could affect our membership positively or negatively and we vigorously defend our position in front of legislative and regulatory bodies. Bosch: We have a long list of specific benefits we provide to our Railway Track & Structures
May 2013 35
state of the nrc David Armstrong, far right, is shown with representatives of the four category winners of the 2012 NRC/RT&S/Commercial Insurance Associates Safety Awards, which were presented at the NRC conference this past January.
members, which are detailed on our website at www.nrcma.org. Membership includes discounted registration at the annual NRC conference and exhibition and a full company listing in both the printed and online versions of the NRC membership directory, which is distributed to Class 1, shortline and regional railroads, as well as executives at rail transit and commuter rail agencies throughout the country. Membership also includes access to the Contractor Safety Award contest, the Annual Railroad Construction and Maintenance Equipment Auction and inclusion on the NRC’s bulletin distribution list, which is full of useful information for rail contractors and suppliers. At the moment, well over 350 rail construction, supply and professional service companies are members of the NRC, which as Terry said, is up more than 75 percent in the past six years. We attribute most of that growth to word of mouth, the NRC Membership Committee and our board members who have been the NRC’s best evangelists. We have an impressive group on the board and they have the credibility with their colleagues to convince them to join the NRC and support our industry. Baker: I’d like to specifically thank each of our board members. Other than Terry, they are David Armstrong of Commercial Insurance Associates, Danny Brown of RailWorks, Mike Choat of Railroad Controls Limited, Chris Daloisio of Railroad Constructors (NRC Secretary/Treasurer), Joe Daloisio of Railroad Construction Co., Bill Dorris of RailWorks (NRC Vice Chairman), Stephanie Freeman of Coleman Industrial Construction, Clayton Gilliland of Stacy & Witbeck, Scott Goehri of HDR Engineering, 36 Railway Track & Structures
May 2013
Jim Hansen of RailWorks, Norm Jester of Herzog Contracting Corp., Larry Laurello of Delta Railroad Construction, Greg Lippard of L. B. Foster, Dave Minor of A&K Railroad Materials, Scott Norman of Herzog Contracting Corp, Jim Perkins of Loram, Jody Sims of Kiewit, Mark Snailham of Balfour Beatty Rail and Daniel Stout of STX Railroad Construction Services. These ladies and gentlemen do an extraordinary amount of work to support the NRC and the rail construction industry. Benton: The NRC is using a variety of methods to stay in touch with our members and get our message out to the world. In addition to constantly updating our website at www.nrcma.org and communicating via e-mail bulletins, the NRC has begun tweeting. I recommend following the NRC on Twitter. Just go to www.twitter.com, set up a quick, free account and follow “@theNRC” or just go to www.twitter.com/thenrc. RT&S: What is the NRC doing to promote safety? Benton: We have a very active Safety Committee. Tammy Mathews of RailWorks is our current Safety Committee Chairwoman and follows Ernesto Scarpitti of Delta Railroad Construction. Tammy is an excellent representative of RailWorks, the NRC and the industry as a whole. The Safety Committee oversees the Safety Training DVD program, the NRC’s participation in the Federal Railroad Administration’s (FRA) Railroad Safety Advisory Committee (RSAC) process, the Contractor Safety Award contest, the NRC’s Roadway Worker Protection training materials, the Pocket Safety Manual, our “Tool Box Talks”
and all of the NRC’s other safety programs. The continuing series of safety training DVDs is led by Safety Committee member and former Board Director John Zuspan of Track Guy Consultants. The two most recent DVDs in this series, Safety Around Flash Butt Welding and Fall Protection in the Rail Industry, were unveiled at the conference in January 2013 and are now available to all NRC members. The entire series has received excellent reviews and is available at no cost to NRC members. The previous 12 DVDs, which are still available, are: Safety with Railroad Hand Tools, Safety with Railroad Power Tools, Safety on Freight and Industrial Track, Safety Around Railway Maintenance Equipment (Parts 1 and 2), Safety Around Transit Track, Safety While Unloading and Handling Material, Safety with Hot Work, Safety Around Thermal Adjusting of CWR, Safety Around Field Welds, Safety on a Rail Gang and Safety on a Tie Gang. Safety Committee members, along with NRC staff, represent the NRC’s interests on FRA’s RSAC. RSAC membership and participation enables the NRC to provide input to the FRA as they create regulations dealing with such key issues as minimum training standards for railroads and contractors performing maintenance-of-way work, drug and alcohol testing policies, medical standards for safety-critical workers, bridge safety, roadway worker protection regulation updates, roadway maintenance machine operating rules, rail integrity testing, rail safety technology in dark territory, Positive Train Control implementation and track safety standards. Safety Committee member and Board Director David Armstrong of Commercial Insurance Associates takes the lead for the NRC on organizing the very competitive “NRC Safe Contractor of the Year” award contest. RT&S also sponsors this contest and helps to publicize the winners, which is much appreciated. There are many excellent safety programs among our membership and this award is a valued acknowledgement of the hard work and dedication of the leadership and safety managers of our member companies. There were a record number of entries in the 2012 contest and the winners were announced at the conference in Januwww.rtands.com
state of the nrc ary, published in the March issue of RT&S and appear again in the NRC Membership Directory. The submittals of the winning firms, including a comprehensive outline of their successful safety programs, were available for viewing at the conference. The NRC also offers a Roadway Worker Protection (RWP) training program, which has been developed by railroad safety professionals with feedback from FRA staff. The RWP training program, which is complimentary to NRC members and is available on the NRC website, includes a training presentation, complete with descriptions of the 49 CFR Part 214 RWP regulations, a training examination, an answer key and training completion cards. Additional safety resources offered by the NRC to our members include the newly updated “Tool Box Safety Talk” series, the Pocket Safety Manual for workers to reference in the field and a model company safety program. RT&S: Your annual conference took place in early January in Miami Beach, Fla., and set another NRC conference attendance record. To what do you attribute the success of your conference? Benton: Our guest speakers are a consistently impressive group of industry leaders who address pertinent and timely issues. These are the people conference attendees want to hear in order to be current with the industry. The sessions are well-attended and people are attentive and engaged. These speakers detailing railroad and transit capital spending plans are the core attraction of our conference. Bosch: In addition, several other industry associations and companies hold meetings in conjunction with our conference, such as the American Short Line and Regional Railroad Association’s Legislative Policy Committee, REMSA’s Board of Directors, the Railway Tie Association’s Executive Committee, the Association of Independent Passenger Rail Operators, GoRail, Nordco, Plasser American and RailWorks. Multiple seminars were offered at the conference, including a legal seminar by Burns White on “Avoiding Imputed Liability for FELA,” a contracting seminar on “Integrated Project Teams” by R&R Contracting, an RWP Train-the-Trainer seminar by Roadway Worker Training, Inc., and a passenger rail program seminar by the North Carolina Department of Transportation, including information on current timelines, prequalification requirements, bidding and Buy America rules. Baker: This brings a new group of executives to the NRC conference, adding to 38 Railway Track & Structures
May 2013
“The key to the NRC’s legislative success in D.C. is the active participation of our membership. Hearing frequently and forcefully from those constituents directly is by far the most effective way to get our messages across.” the appeal for NRC members. It also allows many attendees to attend the conference and deal with other important business issues in a single trip, making the most effective use of people’s limited time. This has worked well and we urge other rail associations, committees, railroads, transit agencies and state DOTs to consider coordinating their meetings and seminars with the NRC conference. The NRC Special Awards have become a highlight at the conference, as well. These awards give NRC members an opportunity to recognize their colleagues for exemplary work in the industry. The 2012 Railroad Construction Project of the Year was presented to Utah Transit Authority’s Frontrunner South project (see story on page 16), a Stacy & Witbeck/Herzog Contracting Corp. joint venture. The 2012 Field Employee of Year was presented to Dave Friehl of Herzog Contracting Corp. and the Hall of Fame Inductee was Jim Daloisio of Railroad Construction Co. of South Jersey. Finally, we had some high profile speakers this year, which helped draw the record crowd. Congressman Bill Shuster of Pennsylvania addressed the conference attendees in his first speech as chairman of the House Transportation & Infrastructure Committee, which was an important moment. RT&S: Your conferences are generally held in warm locales, which provides a nice break for those of us coming in from the frozen north. Benton: Glad to see you noticed! We hold our conferences in either south Florida or southern California in alternating years, just after the new year. It’s typically a slow time for resort properties, which allows us to get good hotel rates for our members and we feel this is a good time of year for rail contractors and suppliers to get away, due to it being a slow time of year for construction in the northern parts of the country. RT&S: Where will the next NRC conference be, in January 2014? Baker: We’re all set for January 5-8, 2014, at the J.W. Marriott Desert Springs in Palm Desert, Calif. We’ll notify members this sum-
mer via e-mail when conference and exhibit booth registrations are available and also when the hotel room block opens and, of course, we’ll advertise the event right here in RT&S. For more information, visit: www. nrcma.org/go/conference. RT&S: Aside from the annual conference, are there other NRC sponsored activities during the year? Benton: Yes, we have two major events, the equipment auction and Railroad Day on Capitol Hill. The NRC Rail Construction and Maintenance Equipment Auction occurs each spring. This year’s auction took place in conjunction with the Union Pacific auction at the Blackmon Auctions Facility in Little Rock, Ark., on April 16, and it was our biggest one ever. Blackmon Auctions was the host and auctioneer and did a fantastic job. Bosch: We were pleased with the quantity and quality of donated and consigned equipment. Most of the equipment at the auction is consigned by members and a portion of those proceeds go to the NRC Safety, Training and Education Fund. The fund benefits our membership and the industry as a whole and is the main source of funding for the Safety Training DVD program. And some of the equipment is actually donated by railroads or contractors to the NRC, with 100 percent of those proceeds going to the safety program. Balfour Beatty Rail, Railway Equipment Services, Delta Railroad Construction and Cahaba Truck and Equipment each donated significant pieces to the auction this year and we owe them a debt of gratitude. Baker: The auction committee has been doing great work on this event and at the previous auctions. The key committee members are Danny Brown of RailWorks Corporation, Mark Gaffney of Stacy & Witbeck, Jay Gowan of Harsco Rail, Paul Laurello of Delta Railroad Construction, Dean Mackey of Progress Rail Services and Greg Spilker of Progress Rail Equipment Leasing. Dan Samford of Herzog Contracting Corp. is also a past chairman of the committee and is always extraordinarily helpful. Blackmon Auctions is our auctioneer every year and they do a great job. The equipment at www.rtands.com
state of the nrc the auction typically includes air compressors, brush cutters, spikers, pickup trucks, hi-rail trucks, cranes, rail threaders, spike pullers, tie inserters and removers, tampers, crib consolidators, log loaders, adzers, pre-gaugers, speedswings, anchor and clip applicators, rollers, cribbers, swing loaders, etc. Benton: The NRC is also a major sponsor and organizer of the annual Railroad Day on Capitol Hill event in Washington, D.C., along with the AAR, ASLRRA, REMSA, RSI, RSSI and RTA. Each year, many of our member companies are represented at meetings with members of Congress and their staff in order to present our side of the story on major issues affecting the railroad industry. There are many issues in Washington, D.C., that directly affect our businesses, such as tax credits to incentivize railroad infrastructure investment, major grant programs, such as Transportation Investment Generating Economic Recovery (TIGER) and High Speed Intercity Passenger Rail programs, regulatory changes under consideration at the Surface Transportation Board and truck size and weight issues. It’s important to have the representation provided by Chuck Baker
40 Railway Track & Structures
May 2013
and the NRC’s government affairs staff, but it’s equally important for each of us contractors and suppliers to keep up on the issues and to directly contact our representatives and senators, to let them know that their constituents care deeply about these issues. It provides contractors and suppliers an excellent opportunity to spend time with their railroad customers. I encourage everybody to visit our website or contact the NRC’s office to learn how to participate and also to participate in Railroad Day on the Hill next year. Baker: This year’s Railroad Day on the Hill in March was a big success, and the next event is tentatively set for March 2014 in Washington, D.C. Please plan to join us in D.C. RT&S: Speaking of Congress, tell us more about the NRC’s Grassroots Program and why a railroad contractor or supplier would want to host their member of Congress? Baker: Because it’s more effective to “show and tell” than simply “tell,” the NRC’s Grassroots Program was created to invite members of Congress to visit NRC mem-
ber facilities and construction project sites. These visits give the members of Congress firsthand knowledge of the rail industry and demonstrate how rail contractors and suppliers are positively affecting the rail industry and the local and national economy. NRC member companies gain positive publicity, foster good relationships with their congressional members and build strong contacts for the NRC to utilize when advocating for rail industry issues on Capitol Hill. It’s a win-win. These congressional visits are coordinated and executed by the NRC staff with little work required by the host company. Contact Tabitha Layman in the NRC office at tlayman@nrcma.org or 202-715-1245 if your company is interested in hosting your member of Congress for a visit. RT&S: What are the NRC’s legislative priorities right now? Baker: We have been working hard to try to get an extension of the 45G shortline railroad rehabilitation tax credit, which will expire at the end of 2013. Two bills have been introduced in Congress, HR721 and S411, which would extend the credit through 2016 to provide the long-term
www.rtands.com
state of the nrc planning certainty necessary to maximize private-sector transportation infrastructure investment. This is a crucial piece of legislation to help maximize rehabilitation spending in the shortline industry. The credit provides a 50-percent tax credit to shortline railroads for investing in their infrastructure, capped at $3,500 per mile owned. This results in more than $300 million per year of additional capital investment by shortline railroads, much of which is contracted out to NRC members or spent on materials and equipment from NRC suppliers. The NRC’s contractor and supplier members have been crucial in helping the shortline railroads build up record cosponsorship numbers among representatives and senators. In the 112th Congress, well over half of the House (256 representatives) and more than half of the Senate (51 senators) co-sponsored the legislation, which is extraordinary. So far this year, we’re at 88 representatives and nine senators as co-sponsors, and counting. The NRC also continues to make the case to Congress against an increase in the size and weight of trucks that are allowed on the highways. We were pleased that the MAP-21 surface transportation reauthorization bill passed in 2012 directed the USDOT to study the issue before making any changes to these limits. Heavy trucks are already subsidized and increasing their weight and length would increase that subsidy and allow them to compete unfairly against the privately-financed freight railroads. Bigger and heavier trucks are unsafe and unwise – they’re bad for the roads and bad for the rail industry. The American public is solidly against them and Congress was wise to drop the idea. We are also actively supporting efforts by the freight railroads to maintain the existing reasonable and balanced economic regulation of their business and we will argue forcefully against legislation or regulation that would needlessly complicate rail service or cap rates. Reregulating the railroads is a sure-fire way to reduce much needed capital investment in the national railroad network. RT&S: How does the NRC attempt to accomplish its legislative goals on Capitol Hill? Baker: As Terry mentioned earlier, the key to the NRC’s legislative success in D.C. is the active participation of our membership. Congressmen only care what I have to say because I am representing their constituents. Hearing frequently and forcefully from those constituents directly is by far the most effec42 Railway Track & Structures
May 2013
tive way to get our messages across. Also, in addition to our own direct legislative efforts, the NRC is a member of the OneRail Coalition, with APTA, the AAR, ASLRRA, Amtrak, NARP, RSI, the States for Passenger Rail Coalition and other key rail industry groups. When all of those groups can agree and go to Congress with a coordinated message, we’re a powerful force, representing hundreds of thousands of workers and tens of billions of dollars of economic activity. RT&S: Beyond the immediate priorities of tax credits and guarding against increased truck size and weights and increased regulation of the freight railroads, what are the NRC’s other legislative and policy priorities? Baker: We are supportive of the TIGER grant program. Of the $3.1 billion in funding that has been distributed in TIGERs 1-4, almost $1.6 billion has gone to rail-related projects, including Class 1 projects, shortline system upgrades, port rail infrastructure projects, commuter rail extensions, light-rail lines, streetcar projects, transit stations and intermodal hubs. In 2012, 24 rail-related projects received more than $297 million out of the $500 million of available funding, which was great news for the rail construction and supply industry. A TIGER 5 program was funded at $474 million in the recently passed FY13 appropriations bill and that process will get underway shortly. The NRC will continue to aggressively back funding for these types of multi-modal merit-based discretionary grant programs, whether in the form of TIGER 6, or potentially a program of Projects of National and Regional Significance or an Infrastructure Bank in the next surface transportation reauthorization bill. The NRC is also advocating for improvements to the Railroad Rehabilitation & Improvement Financing (RRIF) loan program by subsidizing the interest rate and allowing payment deferrals similar to the Transportation Infrastructure Finance And Innovation Act program. Other improvements can be made by making the collateral rules more reasonable, enforcing the intent of the 90-day clock rules and allowing railroads to use the program for refinancing purposes as provided by law. RRIF is a $35-billion infrastructure loan program that is underutilized by the railroads, but we are seeing a recent pick-up in activity, at least on the application side. RRIF provides low interest (around 3.5 percent currently), 35-year loan money for railroad rehabilita-
tion and construction. Since 2002, the FRA has approved 33 RRIF loans for a combined total of approximately $1.7 billion. The NRC will work with our railroad customers to protect and expand the Section 130 Grade Crossing Program, which has a long record of success in improving public safety, but only funds a small fraction of the documented needs. The NRC will work with APTA and other rail transit advocacy support groups to make sure that Congress continues the meaningful rail transit investments of the past decade. More and more U.S. cities are realizing the economic and environmental benefits provided by constructing and expanding light rail and metro systems and we are seeing a shift in travel patterns across the country. However, this momentum is at risk as the funding for the mass transit account of the highway trust fund is no longer sufficient to expand and maintain the system. Simply put, more funding needs to be dedicated to rail transit investments and the NRC will work hard in D.C. every day to get that message across to Congress. And the NRC will continue work with passenger rail advocacy groups to aggressively support and fund a meaningful investment into the national intercity passenger rail network. RT&S: Any closing thoughts? Benton: I would like to thank my fellow board members and all the NRC member companies for supporting me in my position as chairman of the board. I am humbled to represent a great organization in a great industry. I believe the NRC has the proper priorities for our membership – leadership in safety initiatives and training materials, advocacy in legislative and regulatory matters, membership growth, a high-quality conference and maintaining a high level of interaction with the other key industry organizations. We are gaining membership, setting conference attendance records and getting unprecedented participation in our “Safe Contractor of the Year” contest – all signs pointing toward a healthy and active organization. Our committee members and directors of the board are active and engaged with a high level of support from their respective employers. I would like to thank the NRC member companies that support those who serve on the board and on the committees for allowing us to dedicate some of our time to this quality organization. The state of the National Railroad Construction and Maintenance Association is stronger than ever. www.rtands.com
AREMA NEWS Professional Development Upcoming seminars
track alignment design seminar June 11-12, 2013 Denver, CO
Please visit www.arema.org for more information and to register online.
Message from the President
Student chapters experience notable increase By Jim Carter When I took office last September, there were eight AREMA student
introduction to practical railway engineering June 16-17, 2013 Calgary, AB, Canada Please visit www.arema.org for more information and to register online.
Seven AREMA Seminars will be held in conjunction with the AREMA 2013 Annual Conference and Railway Interchange 2013 in Indianapolis, IN, September 29-October 2.
introduction to practical railway engineering September 27-29, 2013 FRA 214: Roadway worker on-track safety September 28, 2013 Rail bulk terminal design September 28, 2013
Jim Carter AREMA President 2012-2013
chapters: the University of Illinois at Urbana-Champaign, Michigan Tech, Oregon State, University of Tennessee, University of Nevada – Las Vegas, University of Kentucky, University of South Carolina and Virginia Tech. In a real growth story, there are now 14. In only six months chapters have been added at Penn State, Rose-Hulman Institute of Technology, University of Alberta, University of British Columbia, University of Manitoba and the University of Toledo. I would like to personally welcome all of the new chapters. To all of you students and faculty involved, those of us at AREMA are very excited about your interest in our organization, as well as our profession. I look forward to having the opportunity to meet and visit with many of you at Railway Interchange in Indianapolis, Ind., in September, and I know that many others do as well. Amazing as that is, I believe that we will continue to see more new student chapters. I had the opportunity to speak to Dr. George List’s railway engineering class at North Carolina State University in April. They are a great group of students and I spent a very engaging time with them. It was thoroughly enjoyable for me and I hope they gained some knowledge about our industry and some of the things going on now. I hope to see a student chapter there soon and I’ve heard that there are some others in the works. These are truly exciting times on that front. I would again like to mention the Student Speakers Initiative for AREMA members who are interested in volunteering to speak Continued on page 44
Environmental permitting issues in railroad construction projects September 29, 2013 intermodal terminal engineering October 2-3, 2013 FRA 213: Track Safety Standards October 2-4, 2013 track alignment design October 2-4, 2013
www.rtands.com
Nila Jackson pictured with Dr. Jerry Rose at the University of Kentucky. Railway Track & Structures
May 2013 43
AREMA NEWS
2013 Upcoming Committee Meetings May 14-16 May 20-21 May 21-22 June 14-15 June 19-20 August 7-8
Committee 5 - Track Dallas/Ft. Worth, TX Committee 18 - Light Density & Short Line Railways Manly, IA Committee 15 - Steel Structures Greensboro, NC Committee 24 - Education & Training Calgary, AB, Canada Committee 9 - Seismic Design for Railway Structures Seattle, WA Committee 7 - Timber Structures Denver, CO
Sept. 12-13 Committee 8 - Concrete Structures & Foundations
Kansas City, MO
Please see page 47 for a complete listing of committee meetings being held at the AREMA 2013 Annual Conference in conjunction with Railway Interchange 2013, September 28 – October 2, in Indianapolis, IN.
Negotiated airline discount information for AREMA Committee Meetings can be found online at http://www.arema.org/meetings/airlines.aspx.
FYI… New Team. Team 42 - Bridge Maintenance Steering Team. Team Leader: Steve Lloyd, assistant division engineer bridges, Norfolk Southern at Greenville, SC. “I think this would serve as perhaps the best venue for many young bridge supervisors coming into AREMA to become involved in a committee and Steve is an excellent person to lead this effort.” - James N. Carter, AREMA President. Register now for the AREMA 2013 Annual Conference being held as part of Railway Interchange 2013, September 29 - October 2, 2013 in Indianapolis, IN. All AREMA badges will be honored for full access into the exhibition halls during operating hours. To register online, please visit www.arema.org. Interested in sponsorship for the AREMA 2013 Annual Conference being held as part of Railway Interchange 2013? Please visit the NEW AREMA sponsorship website at www.arema.org/sponsorship or contact Lisa Hall at lhall@arema.org for more information. Call for entries for the 2013 Dr. William W. Hay Award for Excellence. Entries must be submitted by May 31, 2013. Please visit www.arema.org for more information. Book your 2014 AREMA exhibit booth NOW for the AREMA 2014 Annual Conference & Exposition in Chicago, IL, September 28October 1, 2014. Exhibit booth sales are now being accepted. Receive a 10% discount off your booth purchase between May 1 and October 11, 2013. For more information and to book your exhibit space, please contact Christy Thomas at cthomas@arema.org.
Presidents Column continued from page 43 about various topics in the rail industry at select universities or colleges nationwide. This is an opportunity to give back to the educational community and to interact with students eager to learn and expand their horizons about the rail industry. I assure you that you will do few things that are more fulfilling – one of my young colleagues, Nila Jackson, at Norfolk Southern recently spoke at the University of Kentucky and she thoroughly enjoyed her experience. If you are interested, contact Ashley Backhus at akbackhus@transystems.com. I am a bridge guy and it gives me a great deal of pleasure to announce the re-establishment of AREMA Team 42 – Bridge Maintenance Steering Team. Steve Lloyd of Norfolk Southern is the new Team Leader. This Team will work on developing best practices in bridge maintenance methods and materials. We hope to get a good mix of seasoned and young bridge maintenance professionals on the team. For you young supervisors and managers, this will be an excellent way to meet your peers from throughout the industry, network with them, build relationships that will make you better and more effective at what you do and help make this industry better while you are doing that. If you are interested, contact Steve at Steven.Lloyd@nscorp.com or apply online at http://www.arema. org/committees/commapp.aspx. The program for our annual conference should be on your desk by the time you read this. Please get your registration in early and reserve your hotel room. This is a Railway Interchange year and attendance will be higher than normal. The AREMA Headquarters hotel is the J W Marriott (there are a number of Marriott Hotels in Indianapolis...be sure to select the J W Marriott). Never forget that AREMA is your organization. If you have ideas about how we can make it better for you, whether you are a grizzled veteran like me, a young professional or one of our new student members, e-mail me at james.carterjr@nscorp.com. I would sincerely like to hear any ideas that you have. Be careful and have fun out there.
Put your career on the right track with AREMA’s Railway
Careers Network. Services are free and include confidential resume posting, job search and e-mail notification when jobs match your criteria.
AREMA’s Official Facebook Page Become a fan of the official AREMA Facebook Page and stay up-to-date on the most recent AREMA information. The Official AREMA LinkedIn Group
Join the official AREMA LinkedIn Group by visiting www.linkedin.com and searching groups for “American Railway Engineering and Maintenanceof-Way Association.” 44 Railway Track & Structures
May 2013
American Railway Engineering and Maintenance-of-Way Association 10003 Derekwood Lane, Suite 210, Lanham, MD 20706-4362 Phone: +1.301.459.3200 / Fax: +1.301.459.8077 www.arema.org www.rtands.com
Getting to know Robert Matthews Each month, AREMA features one of our committee chairmen. We are pleased to announce that the May featured chairman is Robert Matthews, chair of Committee 9 Seismic Design for Railway Structures. AREMA: Why did you decide to choose a career in railway engineering? Matthews: My career is a conscious choice to do what I love and design various structures ranging from loading docks to power plants and utility Robert matthews str uctures to railroad Chair, Committee 9 - Seismic Design for Railway Structures bridges. I enjoy working Technical Director, AECOM o n p r o j e c t s t h at a r e tangible to me and useful to the public. When I go to the airport, I drive under a tunnel and pass by a control information to those interested in structures and I also write tower that I helped design. When I travel on the railroad computer software for structural analysis, which I distribute I pass over and under bridges that I have designed. It is a through my structware.com website. rewarding feeling to be involved in an industry that has been the backbone of our society for so many years. AREMA: Tell us about your family. Matthews: My wife, Vichuda, and I live in Southern AREMA: How did you get started? California where we enjoy the beautiful beaches and Matthews: I developed an interest in railroad engineering nice weather. Vichuda is a medical scientist and assistant through the projects I worked on in the early 1990s. At that professor. We travel to Thailand often to visit her parents time I was working for a firm named Holmes & Narver, who moved there after retirement. which was one of the original AECOM companies. I heard about AREA and wanted to join so I could contribute to the AREMA: If you could share one interesting fact about industry and learn more about railroads. yourself with the readers of RT&S, what would it be? Matthews: I have been a Christian for more than AREMA: How did you get involved in AREMA and 30 years and have been involved in various aspects of your committee? ministry from an usher at church to counselor for a global Matthews: In the early 1990s, I was involved in some evangelical organization. bridge design work for the Port of Los Angeles on the Alameda Corridor and was looking for seismic design AREMA: What is your biggest achievement? criteria. At that time, Committee 9 was just being formed Matthews: Finding an intelligent, playful and beautiful and the chapter was no more than an outline. I joined woman and marrying her. Committee 9 and have been a member since its inception to help develop the seismic design criteria that is now used for AREMA: What advice would you give to someone who is railroad bridges throughout North America. trying to pursue a career in the railway industry? Matthews: Join a railroad or consulting company that AREMA: Outside of your job and the hard work you put works on railway projects, find a good mentor and ask a lot into AREMA, what are your hobbies? of questions. Take the time to join AREMA and become Matthews: My wife and I like to go hiking and traveling. actively involved in a committee so you can meet interesting I author a website, structsource.com, which provides people and learn more about the industry. www.rtands.com
Railway Track & Structures
May 2013 45
AREMA NEWS
AREMA Publications Reflections on a Half Century of Railway Engineering and Some Related Subjects©
Railway Memoirs by William G. Byers, PE
2013 Manual for Railway Engineering© NOW AVAILABLE
There have been numerous updates to more than 5,000 pages of the Manual for Railway Engineering. The chapters are grouped into four general categories, each in a separate volume: • Track • Structures • Infrastructure & Passenger • Systems Management. The Manual is an annual publication, released every April. It is available in four-volume loose-leaf format, CD-ROM, revision set (loose-leaf only) and individual chapters (hard copy and downloadable formats). *NEW* Downloadable Chapters Now Avilable Online.
AREMA Bridge Inspection Handbook© The AREMA Bridge Inspection Handbook provides a comprehensive source of information and criteria for bridge inspections for engineers engaged in the assessment of railway bridges. This handbook is published as a guide to establishing policies and practices relative to bridge inspection. It covers such topics as confined spaces, site conditions, loads & forces, nomenclature, bridge decks, timber, concrete & steel bridges, movable bridges, tunnel and culvert inspections, and emergency & postearthquake inspections. Also included are many color photographed examples in several chapters, as well as a glossary in the back of the book. To order any of the AREMA publications, please visit www.arema.org or contact Beth Caruso at +1.301.459.3200, ext. 701, or bcaruso@arema.org.
46 Railway Track & Structures
May 2013
2013 Communications & Signals Manual of Recommended Practices© The Communications & Signals Manual is a manual of recommended practices written by AREMA technical committees in the interest of establishing uniformity, promoting safety or efficiency and economy. The Communications & Signals Manual of Recommended Practices is an annual publication released every October. *NEW* Downloadable Sections Avilable Online - Coming Soon!
Practical Guide to Railway Engineering© This guide provides a comprehensive overview and understanding of the railway system. Whether you are new to the rail industry or a long-time contributor wanting to learn more, this bound book and CD-ROM offer in-depth coverage of railway fundamentals and serve as an excellent reference. (Also available in a CD-ROM version only.)
2012 Portfolio of Trackwork Plans© The Portfolio of Trackwork Plans consists of plans and specifications that relate to the design, details, materials and workmanship for switches, frogs, turnouts and crossovers, crossings, rails and other special trackwork. This is a companion volume to the Manual for Railway Engineering.
Canadian National Funds AREMA Foundation Endowment CN has committed a US$50,000 endowment to the AREMA Educational Foundation. CN Vice President Engineering David W. Ferryman, PE, announced the grant at the recent AREMA Board of Governors Meeting. The endowment will fund a CN scholarship through the foundation in perpetuity. James N. Carter, Jr., PE, foundation president said, “We are very pleased that CN has decided to endow a scholarship. CN is the fourth Class 1 railroad to support the AREMA Foundation in this extraordinary way.” The AREMA Educational Foundation is a 501(c)(3) charitable organization. Contributions from companies or individuals are tax deductible to the extent allowed by law. To make a donation, please visit
www.aremafoundation.org.
www.rtands.com
www.rtands.com
Railway Track & Structures
May 2013 47
PRODUCTS
Telematics system
Harsco Rail released COMPASS™, a telematics system designed to monitor location awareness, asset analysis, productivity management and maintenance tracking. Since January 2013, Harsco has been beta testing COMPASS with railroads in the United States. The system provides a graphical representation of machine activity with daily alerts for required maintenance, engine faults and diagnostics. Using cellular or satellite communications, a machine’s condition and performance data are uploaded to a central location. COMPASS can be installed on a variety of industrial equipment types and connects directly to the machine’s control system. Phone: 1-800-723-3878.
Radio warning system
Grace Industries, Inc., offers its Track-Watch ® radio telemetry safety system, which is designed to give workers an advanced warning of approaching trains, vehicles or rail equipment. In addition to an advanced warning of oncoming rail traffic, a lone worker has the ability to summon assistance by automatically transmitting a “man-down” emergency distress signal, enhancing worker safety. Grace offers a full suite of SmartSignaling® radio telemetry products, including various other visual alerting and audio alarm safety products. Phone: 724-962-9231. 48 Railway Track & Structures
May 2013
www.rtands.com
Ad Index Company
Phone #
Fax#
e-mail address
Page #
Aldon Company, Inc. 847-623-8800 847-623-6139 e-rail@aldonco.com Ames Construction, Inc. 952-435-7106 msweeney@amesco.com Amtrac Railroad Contractors of MD, Inc. 301-797-3730 301-797-3740 cchaney@amtracmd.com AREMA Marketing Department 301-459-3200 301-459-8077 marketing@arema.org Atlantic Track & Turnout Co. 973-748-5885 973-748-4520 stacyw@atlantictrack.com Auto Truck Group eschoenfeld@autotruck.com 816-412-2131 816-412-2191 Ballast Tools Inc. 636-937-3326 636-937-3386 sales@ballasttools.com J.F. Brennan Co., Inc. 608-785-2090 markbinsfeld@jfbrennan.com 800-658-9027 ext.236 Colo Railroad Builders 309-944-4479 615-523-2180 terry@colorr.com Commercial Insurance Associates LLC 615-515-6048 615-515-6048 darmstrong@com-ins.com Danella Rental Systems, Inc. 610-828-6200 610-828-2260 pbarents@danella.com ESCO Equipment Service Co. 847-758-9860 847-758-9861 tgehresco@aol.com Georgetown Rail Equipment Co. 512-869-1542 ext.228 512-863-0405 karen@georgetownrail.com Hamilton Construction Company 541-746-2426 541-746-7635 bhirte@hamil.com Herzog Railroad Services, Inc. 816-233-9002 816-233-7757 tfrancis@hrsi.com Herzog Services, Inc. 816-233-9002 816-233-7757 rebersold@herzogservices.com gpodgorski@hollandco.com Holland L.P. 708-672-2300 ext.382 708-672-0119 866-245-3745 800-309-3299 info@trak-star.com Hougen Manufacturing, Inc. Industry-Railway Suppliers, Inc. 630-766-5708 cslater@industryrailway.com ISCO Snap-Tite 800-CULVERT 502-238-8102 www.culvert-rehab.com L.B. Foster Co. 412-928-3506 412-928-3512 glippard@lbfosterco.com L.B. Foster Co. - Friction Management 412-928-3506 412-928-3512 glippard@lbfosterco.com Lanier Steel Products, Inc. 706-335-7200 706-335-3410 rlgillespie@windstream.net Lewis Bolt & Nut Co. 800-328-3480 952-449-9607 dbarry@lewisbolt.com Loram Maintenance of Way, Inc. 763-478-6014 763-478-2221 sales@loram.com North American Rail Products Inc. 604-946-7272 888-692-1150 cerhart@narailproducts.com National Compressor Exchange Inc. 800-225-7381 natnlcompressor@aol.com Neel Company, The 703-913-7858 703-913-7859 btemple@neelco.com New York Air Brake 607-257-7000 607-257-2389 paula@onlinesms.com OMNI Products, Inc. 815-344-3100 815-344-5086 bcigrang@omnirail.com dostby@osmose.com Osmose Railroad Services, Inc. 800-356-5952 608-221-0618 Plasser American Corp. 757-543-3526 757-494-7186 plasseramerican@plausa.com Progress Rail Services Corp. 800-476-8769 256-593-1249 info@progressrail.com Ragnar Benson Construction LLC 847-698-4900 847-692-9320 christine.caponigri@rbic.com RAILCET 866-724-5238 217-522-6588 grif1020@yahoo.com Railroad Construction Co. of South Jersey, Inc. 856-423-9385 856-423-9389 dluvara@railnj.com 973-763-4320 973-763-2585 rails@railso.com Rails Company Railway Tie Association 770-460-5553 770-460-5573 ties@rta.org 866-905-7245 952-469-1926 jrhansen@railworks.com RailWorks Corporation Railway Educational Bureau, The 402-346-4300 402-346-1783 bbrundige@sb-reb.com S&C Distribution Company 708-396-1755 708-396-1754 info@sandcco.com Unitrac Railroad Materials, Inc. 412-298-0915 865-693-9162 ppietrandrea@unitracrail.com voestalpine Nortrak Inc. 307-778-8700 307-778-8777 gord.weatherly@voestalpine.com Willamette Valley Company 541-484-9621 541-284-2096 03alishab@wilvaco.com
20 NRC 13 NRC 12 Cover 3 NRC Cover 2 15 5, 8 14 11 NRC 13 6 NRC 40 33 NRC 40 NRC 15 30 32 22 NRC 12 27 NRC Cover 4 4 NRC 14 18 25 6 NRC 16 7 2 40 Cover 2 29 39 NRC 15 34 NRC 14 9 19 37 48, 50 9 17 31 Cover 4
Reader Referral Service This section has been created solely for the convenience of our readers to facilitate immediate contact with the RAILWAY TRACK & STRUCTURES advertisers in this issue. The Advertisers Index is an editorial feature maintained for the convenience of readers. It is not part of the advertiser contract and RT&S assumes no responsibility for the correctness.
Advertising Sales Jonathan Chalon, Publisher, jchalon@sbpub.com; Emily Guill, eguill@sbpub.com; Mark Connolly, mconnolly@sbpub.com; Heather Disabato, hdisabato@sbpub.com; Steven Barnes, sales@railjournal. co.uk; Louise Cooper, lc@railjournal.co.uk; Dr. Fabio Potesta, info@mediapointsrl.it; Katsuhiro Ishii, amkatsu@dream.com; Jeanine Acquart, jacquart@sbpub.com (classified) www.rtands.com
Railway Track & Structures
May 2013 49
CALENDAR MAY 22-24. Timber and Steel RailRoad Bridges. University of Tennessee. Knoxville, Tenn. Contact: Diana Webb. Phone: 865-974-5255. Fax: 865-974-3889. Website: http://www.ctr. utk.edu/ttap. 29-31. North American Rail Shippers 2013 Annual Meeting. Hilton Inner Harbor Hotel. Baltimore, Md. Phone: 972-690-4740. Fax: 972-644-8208. E-mail: nars@ railshippers.com. Website: www.railshippers.com. JUNE 2-5. American Railway Development Association 2013 Annual Meeting. Marines’ Memorial Club and Hotel. San Francisco, Calif. Website: www.amraildev.com. 2-5. APTA Rail Conference. Philadelphia Marriott Downtown. Philadelphia, Pa. Contact: Marcus Eng. Phone: 202-496-4874. E-mail: meng@apta.com. Website: www.apta.com. JULY 7-13. Rail and Intermodal Summer Youth Program. Michigan Technological University. Houghton, Mich. Contact: Pam Hannon. Phone: 906-487-3065. E-mail: prhannon@mtu.edu. Website: http://www.rail.mtu.edu/ summer_youth2013.html. 30-Aug. 1. Railway Tie Association Tie Grading Seminar. Courtyard by Marriott-Bossier City/Louisiana Boardwalk. Shreveport, La. Phone: 770-460-5553. Fax: 770-460-5573. E-mail: ties@rta.org. Website: www.rta.org. SEPTEMBER 29-Oct. 2. Railway Interchange 2013. Indianapolis, Ind. Phone: 301-459-3200. Fax: 301-459-8077. Website: www. railwayinterchange.org. 29-Oct. 2. APTA Annual Meeting. Hilton Chicago. Chicago, Ill. Contact: Yvette Conley. Phone: 202-496-4868. E-mail: yconley@apta.com. Website: www.apta.com. OCTOBER 6-11. International Railway Safety Conference (IRSC 2013). Vancouver, BC, Canada. E-mail: irsc2013@nrc-cnrc. gc.ca. Website: www.irsc2013.org. 9-11. 95th Annual Railway Tie Association Symposium and Technical Conference. Hyatt Regency Lake Tahoe. Incline Village, Nev. Phone: 770-460-5553. Fax: 770-4605573. Website: www.rta.org. 15-16. Railway Age Passenger Trains on Freight Railroads. Washington Marriott. Washington, D.C. Contact: Jane Poterala. Phone: 212-620-7209. E-mail: jpoterala@sbpub.com. Website: www.railwayage.com. NOVEMBER 4-8. Railroad Track Inspection & Safety Standards. Chattanooga, Tenn. Contact: Diana Webb. Phone: 865974-5255. Fax: 865-974-3889. Website: http://ctr.utk.edu/ ttap/training/railinspect.php. 50 Railway Track & Structures
May 2013
www.rtands.com
Professional Directory
WEED & BRUSH SPRAYING Specialized fleet of computer operated sprayers
Tree Trimming/Brush Cutting
Line Clearance-Hazardous Trees-Whole tree chipping
POLE LINE REMOVAL
A variety of on/off track removal equipment
Road Crossing Site Safety Maintenance Re-cut & Herbicide Programs 800.822.9246 www.merciers.com
Mercier’s
Products and services
NEW & USED EQUIPMENT
R. E. L. A. M. INC.
E-Mail: RelamCFE@aol.com Tel: 440-439-7088 Fax: 440-439-9399
2012 NRC SAFETY AWARD WINNER NEW & USED EQUIPMENT
EQUIPMENT FOR SHORT OR LONG TERM LEASE HARSCO TAMPERS 6700S Switch and Production Tampers - 2012, 2011, 2010 & 2009 3300 Chase Tampers 3000 Tampers w/Raise & Line or Chase Tampers 2012 thru 2006 2400 Tampers w/Raise & Line, 900 Tampers w/Jacks TIE INSERTERS/EXTRACTORS Nordco TRIPPs - 2012 thru 2005 TR-10s & TKOs 925 S/Ss and Standards KNOX KERSHAW REGULATORS, KRIBBER/ADZERS, TIE CRANES & PLATE BROOMS KBR-850-925-940 Ballast Regulators & Snow Fighters - 2012 - 2008 KTC - 1200 Tie Cranes - 2012 thru 2006 KKA-1000s Kribber/Adzers – 2009, 2008 & 2007 KPB-200 Plate Brooms NORDCO ANCHOR APPLICATORS, SPIKERS & GRABBERS Models E & F Anchor Machines Models CX and SS Spikers - 2012 thru 2006 Model SP2R Dual Grabbers – 2008, 2007 & 2006 RACINE DUAL ANCHOR SPREADERS, SQUEEZERS, TPIs, DUAL CLIP APPLICATORS, OTM RECLAIMERS AND ANCHOR APPLICATORS HI-RAIL CRANES & SPEEDSWINGS Pettibone Model 445E Speedswings w/Multiple Attachments Geismar 360 Hi-Rail Excavators with Cold Air Blowers Badger 30 Ton Cranes HI-RAIL ROTARY DUMPS, GRAPPLE TRUCKS & EXCAVATORS Gradall XL3300 Series III w/Digging Buckets & Brush cutters - 2012 Badger 1085R with Brush Cutter and Ditch Cleaning Bucket
Brand new Western Star or Freightliner hi rail Grapple trucks for sale or rent
RT&S Classified Section
Brand new Ford F350 hi rail pickups for sale or rent
Craig Wilson 212-620-7211
(5) 2005 Ford F350 hi rail pickups for sale Contact Andy Wiskerchen for Pricing Omaha Track Equipment 715-570-8885 andy@omahatrackequipment.com www.rtands.com
cwilson@sbpub.com s r
r
TM
Railway Track & Structures
May 2013 51
NEW & USED EQUIPMENT
Some things never change. Quality, Service, and Dependability. Since 1910.
Hirail Crew Cab Grapple Truck
Rotary Dump
LEASE or BUY
Some things never change. Quality, Service, and Dependability. Since 1910. Hirail Service/Maintainers Truck
Hirail Gradall w/opt. Brush Cutter Crew Cab Boom Truck RAILROAD SERVICES
Est. 1910
Custom Build New or Used Chassies Also: Hirail Boom Dump Trucks Hirail Mechanics Trucks Hirail Section Trucks Hytracker for moving equipment Hudson Ballast Cars DMF & Harsco parts, service and installation
RAILROAD SERVICES
Phone: 315-455-0100 • Fax: 315-455-6008 • Syracuse, NY • Please visit our website www.franktartaglia.com Hi-Rail trucks engineered for your applications with nationwide deliveries and warranties...
RAILROAD SERVICES
Rail Scrap Retriever
Grapple Trucks Magnets & Self Propelled
4313 Southway St. SW Canton, OH 44706
(330) 479-2004 FAX: (330) 479-2006 www.sperlingrailway.com e-mail: info@sperlingrailway.com
Section Trucks Telescoping & Articulating Cranes
ALSO AVAILABLE Hi-Rail Pickup Trucks Hi-Rail Mechanics Trucks Hi-Rail Aerial Devices Hi-Rail Welder Trucks
and many more truck configurations...
EMPLOYMENT
Track Maintenance Trucks
877-888-9370
ASPENEQUIPMENT.COM/RAIL Premiere Contractor in for the Northeast is currently looking for Premiere RailroadRailroad Contractor in the Northeast is currently looking Qualified, Enthusiastic and Hard Working individuals for the following Qualified, Enthusiastic and Hard WorkingProject individuals for the following Premiere positions:Railroad Contractor in the Northeast is currently looking for Engineer Qualified, Enthusiastic and Hard Working individuals for the following positions: positions: Project Engineer
• Project Engineer • Project Manager Estimator • Estimator Project Manager
Please send inquiries and resumes to:
Please send inquiries and resumes to: Please send inquiries and resumes to: bsheehy@railnj.com bsheehy@railnj.com
bsheely@railnj.com
52 Railway Track & Structures
Project Manager Estimator
May 2013
RT&S2013revAd.indd 1
For Sale
2/12/13 2:57 PM
100 ea. 36” Gauge EBTRR Hoppers Joe Kovalchick 724-388-4500
www.rtands.com