CONSTRUCTION PROGRESS ACROSS SPR CITY SITE IS TAKING PLACE AT RECORD SPEED FIND OUT MORE E DIT IO N - 0 09 | F EB R U A RY 2 0 1 9

01


PROJECT PROGRESS REPORT

TOWER A

Construction work is currently in the above terrace crown area. Flat and lobby finishing works are in progress. External painting, window and main door frame fixes have also been initiated. Waterproofing work upto 26th floor and fire safety work upto 10th floor have been completed. In addition, MEP 1st fix has been completed upto the 21st floor.

E DIT IO N - 0 09 | F EB R U A RY 2 0 1 9

02


PROJECT PROGRESS REPORT

TOWER B

Work in Tower-B is proceeding at a rapid rate. Work has been completed in the 26th floor and is in progress in the 27th floor. Waterproofing work has been completed upto the 10th floor and MEP 1st fix has been done until the 6th floor.

E DIT IO N - 0 09 | F EB R U A RY 2 0 1 9

03


PROJECT PROGRESS REPORT

TOWER H Construction work across the Tower-H site is being carried out in full swing. At present, work in the 16th floor has been completed and it is currently underway in the 17th floor.

E DIT IO N - 0 09 | F EB R U A RY 2 0 1 9

04


PROJECT PROGRESS REPORT

SHRI RAM UNIVERSAL SCHOOL There has been considerable progress in the construction work being carried out at the school site. 2nd floor work is in progress across Block A and 3rd floor work is in progress in Block B. In Block C and D, work is currently being carried out in the terrace floor. Ground floor work is being carried out in Block E and F.

E DIT IO N - 0 09 | F EB R U A RY 2 0 1 9

05


PROJECT PROGRESS REPORT

ORIGINE

At the bungalow site, construction work is proceeding at a rapid rate. Currently, in Zone 1 and 2, 3rd floor work and block work is in progress. In Zone 3 and 4, podium floor work is in progress. In Zone 5, raft work is in progress.

E DIT IO N - 0 09 | F EB R U A RY 2 0 1 9

06


PROJECT PROGRESS REPORT

MARKET OF INDIA

Work is in progress in full swing at the Market of India site. Excavation, raft work in basement 2 floor and basement 1 slab work are being carried out in Zone A and E. In Zone E, work in lower ground cellar is currently in progress. In the Central Plaza area, excavation work is in progress.

E DIT IO N - 0 09 | F EB R U A RY 2 0 1 9

07


PROJECT PROGRESS REPORT

NON TOWER

In the podium area, construction work is proceeding at a steady pace. Currently, P1 floor work is in progress.

MOI MOCK UP

Across the Market of India mockup site, construction work is taking place in full swing. Fabrication work has been completed and at present, external wall partition work is in progress.

E DIT IO N - 0 09 | F EB R U A RY 2 0 1 9

08


SITE INFRASTRUCTURE DETAILS New batching plant for Market of India has been completed Tower crane for Zone-A of Market of India is ready for operation. In Zone-E, crane set up is currently in progress.

E DIT IO N - 0 09 | F EB R U A RY 2 0 1 9

09


E DIT IO N - 0 09 | F EB R U A RY 2 0 1 9

10