1 minute read
ST. CHARLES COUNTY ROAD BOARD FUNDED PROJECTS
Guthrie Road Improvement Project
The design of this project began in 2019 and, after much consideration, the project scope was increased in 2021 to include reconstructing all of Guthrie Road between Flint Brook Drive to just North of Bluff Brook Drive with a sidewalk along the East side of the new road. The rest of the scope, including design, right-of-way acquisition, and construction is expected to be completed in 2023, after progressing in 2021 and 2022.
Sommers Road Widening
This project includes resurfacing Sommers Road in its entirety, widening the pavement where necessary to provide three full lanes throughout and constructing sidewalks where missing along the route. Design began this year; land acquisition will take place in 2023 with construction beginning in 2024.