Cranes and Lifting November 2021

Page 34

IN FOCUS / QUEENSLAND RIGGING HIRE

HEAVY DUTY RIGGING FOR LOAD TESTING GANTRY CRANE Queensland Rigging Hire recently solved a difficult lift test with heavy duty rigging, water load bags and over a quarter of a million litres of water. And all this happened in an operating power station. IT ALL SOUNDED FAIRLY STRAIGHT forward when the Gladstone Power Station’s management called Kris Pidgeon, owner and director NQCranes to ask for the stations gantry cranes to be load tested to full capacity in anticipation for the first generator changeover in 40 years. The realities of the project were far from straight forward. NQ Cranes manage the cranes and existing infrastructure throughout the power station. During a site visit NQCranes’ Central Queensland Area Manager Nicolaas Lee immediately recognised several challenges. The space and headroom available to complete the test were quite restrictive, the timeframe for testing to be completed was less than four weeks and the testing of equipment would be at an elevated risk as the station was live and operating. Complexities also included the utilisation of a custom designed and manufactured spreader bar which had been in storage since the generators were originally installed in the late 1970s. Pidgeon called Ben Fitzgerald from Queensland Rigging and Hire to discuss the project. “Kris called and explained the background to the project and I then spoke to Nicolaas and the service contract specialist and engineer Cameron Poole from NRG, at the power station. 34 / CAL November 2021

The quickest way to proceed was to fly up and visit the site and come up with a plan, which I did,” said Fitzgerald. During the initial visit, Fitzgerald was able to understand the height limitations for the lift, the space they would be working in and the close proximity of other plant and equipment. All this information would enable him to design a rigging solution to fit the environment and the requirements of the power station. To further complicate matters, Gladstone Power Station is active and was going to be working the whole time the gantry cranes were being tested and with tight tolerances, there was not much room to move in says Fitzgerald. “I calculated we were going to need 8 water load bags each with a 35t capacity which meant we would safely have the required capacity to be lifting 255,000 litres of water in the air. Working safety in a live power station, with huge volumes of water up in the air, was probably the greatest challenge,” he said. To make this happen, the planning was thorough and detailed and the results of the tests were dependant on this,” said Fitzgerald. The testing involved two gantry cranes which are permanently operating at the station. “The load test was designed to ensure the cranes are capable of managing the lift safely. For this to happen the testing

Eight water load bags each with a 35t capacity, meant lifting 255,000 litres of water in the air. www.cranesandlifting.com.au


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

Working at Heights Association

5min
pages 88-89

Lift of the month

1min
pages 90-92

Universal pressure lift

5min
pages 84-87

New Valla pick and carries arrive

5min
pages 82-83

Sany crawlers

3min
pages 80-81

New Kobelcos for piling work

5min
pages 77-79

Service and support from Altra Motion

7min
pages 70-72

Importance of the right insurance policy

11min
pages 73-76

Forensic testing extends life of wire rope

6min
pages 65-67

Liebherr delivers hammer head for infrastructure project

5min
pages 68-69

Townsville steps up in capacity

8min
pages 60-64

New Kato city crane to Pfeiffer Cranes

7min
pages 56-59

Keeping pace with sustainability

5min
pages 42-44

Australian technology built tough

3min
pages 54-55

Flexibility key to Franna’s success

6min
pages 45-47

Five axle Groves continue to deliver

5min
pages 51-53

Benefits of manufacturing locally

6min
pages 38-41

Ben Baden Services deliver quality truck mounted crane

7min
pages 48-50

Complex turbine lift test

7min
pages 34-37

Booming result

6min
pages 32-33

CICA President’s Report

5min
pages 14-15

CICA Tech Corner

5min
pages 20-21

Up Front

12min
pages 10-13

How safe is crane signage?

6min
pages 28-31

CICA Member Profile

7min
pages 16-19

Liebherr to serve ADF

3min
pages 26-27

Celebrating with Humma

7min
pages 22-25

Industry news

3min
pages 6-9
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.