Phase One Conceptual Cost Estimate
Designed For: Coastal Rivers Conservation Trust
The costs shown are conceptual and do not include additional costs such as equipment mobilization/demobilization, construction oversight, or engineering and permitting. Actual project costs will be determined by consultation with project engineers and contractors.
Phase One
Project Phasing plan
Arrival & Entry Landscaping
Pad Area Improvements New Driveway
The first phase of construction would include installing the new driveway and parking area, demolishing the old driveway and gravel areas, landscaping around the farmhouse and old ice cream stand, and the pad area improvements.
Not for construction. Part of a student project and not based on a legal survey.
3 Round Top Lane, Damariscotta, ME 04543
Round Top Farm Comprehensive Plan
accessible paths from old driveway
Spring 2022
The following sheets provide one potential plan that separates the project components into three construction phases that may be completed independently. Associated concept-level cost estimates are provided for each component. An estimate of total project cost is provided at the end of the following sheet.
Designed By: Veronica Chudik & Hope Matis
Due to the size of the proposed project, CRCT may wish to consider a phased approach to implementation. This would allow the organization to complete certain parts of the project as funds become available and reduce the amount of disruption to site operations at any given time. However, project management for phased construction will be more complex and total overall costs may increase due to longer timelines, changes in construction costs, and other factors.