Projects with a value between R50 million and R250 milion

Xhora Off-channel Dam Project by Hatch for Amathole District Municipality, Eastern Cape

PROJECT TEAM

Client: Amathole District Municipality Consulting Engineer: Hatch Contractor: Stefanutti Stocks/Mfuraa Consortium

T

he Xhora Water Supply Scheme was identified in a feasibility study that was completed in 2002. The Xhora Off-channel

Storage Dam provides assurance of supply to the Xhora Water Supply Scheme, which is intended to provide potable water to 70 000 people in the Elliotdale District of Mbhashe Local Municipality, within the Amathole District Municipality. The Xhora Off-channel Dam is a 29.4 m high crest, 230 m long, zoned earth-fill embankment dam with a diversion culvert to allow for flood water during construction, outlet pipework, and a

25 m long ogee side-channel spillway on the right flank, with a 5 m wide trapezoidal spillway chute, widening to 9.5 m before entering the stilling basin. The stilling basin was designed and model tested by the University of Stellenbosch. project-specific density test method to

On completion of the dam, the river

of the dam, and the impact of siltation, it

be developed. Limited higher PI clay

diversion culvert was closed through the

was conceived as an off-channel storage

was imported.

installation of two sets of precast reinforced

To minimise the environmental impact

dam in a small section of the catchment.

The water stored in the dam is expensive,

concrete planks, with the void between

Water releases are provided to maintain

as a substantial portion is pumped from

the planks filled with mass concrete post-

the aquatic environment within the river

the Xhora River raw water abstraction weir

grouted through a tube manchette system.

channel downstream of the dam.

to the dam. It was therefore important to

The diversion culvert provides passage for

grout the rock below the dam to minimise

the two outlet pipes, a domestic supply

2 dam by the Department of Water and

leakage. In order to allow a higher first-

to the water treatment works, and for

Sanitation Dam Safety Office. The Stefanutti

stage grouting pressure, grouting was

emergency emptying of the dam, as well

Stocks/Mfuraa Consortium was appointed

undertaken through the imported clay

as making provision for environmental

as the contractor for the project.

cut-off. This allowed a significant increase

releases. A low-cost solution to abstract

in the pressure that could be specified for

water for domestic consumption was

the first stage of grouting.

implemented utilising a floating intake.

The dam is categorised as a category

Maximum use of the materials from the basin was made, which required a

C E S A A o n E n g i n e e r i n g E x c e l l e n c e Aw a r d s 2 0 2 1

13


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

Daveng Consulting Engineers

1min
page 26

Edward Archer | SMEC South Africa

2min
page 27

Bigen Group

2min
page 24

Koleko

1min
page 25

Amal Doorgapershad | Knight Piésold

2min
page 28

Xolani Mandidi | AECOM

1min
page 32

AECOM

2min
page 29

Koleko

1min
page 30

Knight Piésold

2min
page 23

BVi Consulting Engineers

1min
page 22

Kuils River Upgrade by Zutari for City of Cape Town, Western Cape

2min
page 18

Construction of Mgcobaneni Bus Route and Culvert by Nathoo Mbenyane Engineers for the City of Mbombela, Mpumalanga

2min
page 19

Engineering 4.0 Building by Spoormaker & Partners for the University of Pretoria, Tshwane

2min
page 20

Plankenbrug Main Outfall Sewer and Associated Works - Phases 2 & 3 by AECOM for Stellenbosch Municipality, Western Cape

2min
page 17

Xhora Off-channel Dam Project by Hatch for Amathole District Municipality, Eastern Cape

2min
pages 15-16

Design and Construction of the Emoyeni Reservoir by Knight Piésold for eThekwini Municipality, KwaZulu-Natal

2min
page 14

Vopak Terminal Lesedi Admin Building by Zutari for Vopak South Africa Developments in Joint Venture with Royal Vopak and Reatile Resources, Gauteng

2min
page 21

The UCL 175 TCH Factory Expansion Project by Bosch Projects for UCL Company, KwaZulu-Natal

2min
page 12

The Leonardo by RMCE for Legacy Group, Sandton, Gauteng

2min
page 8

16 on Bree by Zutari for FWJK Developments, Cape Town

1min
page 9

Upgrading of National Route 7, Section 1 between Atlantis South and Kalbaskraal by AECOM for SANRAL, Western Cape

1min
page 10

Trans African Concessions (TRAC

2min
page 7

Dr PD (Dempsey) Naidoo

2min
page 6

Mareesburg Tailings Storage Facility (Phase 2) by SRK Consulting for Anglo American Platinum, Limpopo

1min
page 11

Aon: An opportunity to build a ‘new better’

2min
page 5

CESA: Making engineering future-proof

2min
page 4
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.