Cranes and Lifting November 2021

Page 84

IN FOCUS / UNIVERSAL CRANES The two CO2 vessels weighed 125t each on the plan and were 34m long with a diameter of 4.5m

DUAL PRESSURE VESSEL LIFT, NO PROBLEM FOR UNIVERSAL In early October the Universal Cranes Brisbane team installed two CO2 vessels for Air Liquide at Incitec Pivot on Gibson Island. Universal Cranes deployed its Grove GMK 7450 and Demag AC350 – 6 for the dual lift. THE TWO CO2 VESSELS WEIGHED 125T each on the plan and were 34m long with a diameter of 4.5m. Each crane was set up to lift 77.8t with rigging and this allowed for the 20 percent dual lift factor. Robbie Glyde, Sales and Cranes Supervisor for Universal Cranes explains more. “Obviously, there was a high degree of planning conducted by all parties involved including Air Liquide, ILP, with Rex Andrews Transport R&N Contractors carrying out pre-lift works and implementing the transport arrangements. Universal Cranes conducted numerous site visits and preliminary lift plans before the final crane selection and lift plans were drawn up,” he said. “The configurations of the cranes meant the Grove GMK7450 had 25.7m of main boom with 120t of counterweight. The capacity on this crane was 86t and 84 / CAL November 2021

it was lifting at 90.6% of its charts with 77.9t at a radius 15m. “The Demag AC350 – 6 had 27.2m of main boom with 116.7t of counterweight. The total load was 77.5t. The capacity of this crane was 81t and it was lifting at 11m which meant it was running at 95.7% of its charts,” said Glyde. “Universal Cranes provided all our own rigging for the project. Generally speaking, we provide all our own rigging for projects. With these lifts we were using a S273 model Modulift spreader bars set at 6.5m which meant the slings didn’t come into contact with the vessels. “We were able to conduct the lifts with the outrigger pads we normally send out with the cranes, although some ground preparation was required so we could set up the pads properly for the Grove GMK7450,” he said. The project was completed over

four days. On day one, both cranes were mobilised to site and due to site constraints, the cranes were mobilised into position one at a time. Day two saw the first vessel lifted into place and following completion of this lift, the cranes were moved into to another position, ready for the second lift. Day three was a ‘lay day’ for the Universal Cranes team. “Because the vessels were so large, they could only be transported, under escort, during the early hours of the morning. Day three enabled the transport company to load the second vessel in preparation for delivery to site early on day four. “Day four was for the second lift. We lifted the second vessel into place and both cranes were then demobilised from site. As a result of the detailed and careful planning, the lifts went really smoothly and the client was very happy to see the vessels safely in position,” said Glyde. www.cranesandlifting.com.au


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

Working at Heights Association

5min
pages 88-89

Lift of the month

1min
pages 90-92

Universal pressure lift

5min
pages 84-87

New Valla pick and carries arrive

5min
pages 82-83

Sany crawlers

3min
pages 80-81

New Kobelcos for piling work

5min
pages 77-79

Service and support from Altra Motion

7min
pages 70-72

Importance of the right insurance policy

11min
pages 73-76

Forensic testing extends life of wire rope

6min
pages 65-67

Liebherr delivers hammer head for infrastructure project

5min
pages 68-69

Townsville steps up in capacity

8min
pages 60-64

New Kato city crane to Pfeiffer Cranes

7min
pages 56-59

Keeping pace with sustainability

5min
pages 42-44

Australian technology built tough

3min
pages 54-55

Flexibility key to Franna’s success

6min
pages 45-47

Five axle Groves continue to deliver

5min
pages 51-53

Benefits of manufacturing locally

6min
pages 38-41

Ben Baden Services deliver quality truck mounted crane

7min
pages 48-50

Complex turbine lift test

7min
pages 34-37

Booming result

6min
pages 32-33

CICA President’s Report

5min
pages 14-15

CICA Tech Corner

5min
pages 20-21

Up Front

12min
pages 10-13

How safe is crane signage?

6min
pages 28-31

CICA Member Profile

7min
pages 16-19

Liebherr to serve ADF

3min
pages 26-27

Celebrating with Humma

7min
pages 22-25

Industry news

3min
pages 6-9
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.