Implementation
06
Table 6-9: Peck Road Countermeasure Concept Costs COUNTERMEASURE
DESCRIPTION
UNIT COST
UM
QUANTITY LENGTH
WIDTH
COST
$15,000
EA
2
Bicycle lane centered in lane, filled with thermoplastic
$100
LF
1
Add NoRTOR sign / display
Sign attached to existing signal structure
$500
EA
4
$2,000
Electronic Feedback Signs
Speed reader board on post (solar)
$8,000
EA
1
$8,000
Reflective border on signal heads
8 signal heads
$2,400
INT
2
$4,800
Street Lighting
Fixture and power lines as needed
$8,000
EA
2
$16,000
Concrete or Pavement Construction (low cost options use pavement markings) Corner Radius Reduction or Truck Apron
Concrete curbs and sidewalk
$30,000
Pavement Markings Bicycle Priority Lanes
800
$80,000
Signs or Signal Infrastructure
INT = Intersection, Qty = Quantity, L = Length, W = Width, EA = Each, SF = Square Feet, LF = Linear Feet
Existing roadway conditions along Peck Road and Lower Azusa Road
Total
$140,800
Crosswalks at Peck Road and Ranchito Street
93