Implementation
06
Table 6-10: Tyler Avenue Countermeasure Concept Costs COUNTERMEASURE
DESCRIPTION
UNIT COST
UM
QUANTITY LENGTH
WIDTH
COST
Concrete or Pavement Construction (low cost options use pavement markings) Corner Radius Reduction or Truck Apron
Concrete curbs and sidewalk
$15,000
EA
8
$120,000
Bulb Out / Turn Wedge
Pavement markings with ‘buttons’ and rubber turn wedges
$2,500
EA
7
$17,500
High Visibility Crosswalks
Continental spaced to avoid vehicle wheels
$5,500
EA
6
$33,000
Bicycle Priority Lanes
Bicycle lane centered in lane, filled with thermoplastic
$100
LF
1
Add NoRTOR sign / display
Sign attached to existing signal structure
$500
EA
4
$2,000
Electronic Feedback Signs
Speed reader board on post (solar)
$8,000
EA
2
$16,000
Street Lighting
Fixture and power lines as needed
$8,000
EA
10
$80,000
Adjust signal timing in Traffic Control Cabinet
$1,500
INT
3
$4,500
Pavement Markings 1,200
$120,000
Signs or Signal Infrastructure
Signal Timing Adjustments Signal Changes at Intersections
INT = Intersection, Qty = Quantity, L = Length, W = Width, EA = Each, SF = Square Feet, LF = Linear Feet
Existing roadway conditions along Tyler Avenue
Total
$393,000
Intersection of Tyler Avenue and Ramona Boulevard
95