Implementation
06
Table 6-12: Lower Azusa Road Countermeasure Concept Costs COUNTERMEASURE
DESCRIPTION
UNIT COST
UM
QUANTITY LENGTH
WIDTH
COST
Raised rubber centerline
$2,500
EA
1
$2,500
High Visibility Crosswalks
Continental spaced to avoid vehicle wheels
$5,500
EA
6
$33,000
Bicycle Priority Lanes
Bicycle lane centered in lane, filled with thermoplastic
$100
LF
1
$198,000
EA
1
$198,000
Concrete or Pavement Construction (low cost options use pavement markings) Hardened Centerlines
Pavement Markings 800
$80,000
Signs or Signal Infrastructure Pedestrian Signal - New
Mast, power, concrete median, crosswalk
Electronic Feedback Signs
Speed reader board on post (solar)
$8,000
EA
1
$8,000
Adjust signal timing in Traffic Control Cabinet
$1,500
INT
1
$1,500
Signal Timing Adjustments Signal Changes at Intersections
INT = Intersection, Qty = Quantity, L = Length, W = Width, EA = Each, SF = Square Feet, LF = Linear Feet
Bicyclist riding on the sidewalk
Total
$323,000
Intersection of Lower Azusa Road and Peck Road
99