Adept completes bore for Sunbury Line Adept Civil has completed another rail crossing out at Keilor Plains for Multiworks as part of the Sunbury Line upgrades.

A

dept Civil was contracted by Multiworks, who has partnered with Metro Trains Melbourne (MTM), to deliver major upgrade works at the Tottenham Substation as part of the Sunbury Line Upgrade and Metro Tunnel Projects. The scope of the project was to tunnel using a micro-tunnel boring machine (mTBM) under the Sunbury Line during an occupation for Multiworks. “Great results out at Keilor plains substation, delivering yet another complex and critical rail crossing,” microtunnelling supervisor Maddison Corrie says. Adept installed a 376 mm GRP sleeve to carry 2 x 100 mm conduits for the power upgrades, which are taking place in and adjacent to the rail corridor as part of works to boost electrical capacity along the Sunbury Line. As part of the upgrades, an electrical substation on Sydenham Rd Delahey is being built to provide essential power for bigger, more modern trains to run along the line. The Sunbury Line Upgrade includes power upgrades that will allow bigger, more modern trains to run on the Sunbury Line. An extension to the existing electrical substation at Tottenham station is required to improve the capacity, reliability and frequency of services for passengers. The new trains are a vital component to the expansion of Melbourne’s metropolitan rail network, and will greatly improve the capacity, reliability and frequency of Sunbury Line train services. Adept successfully completed the 15 m bore on-line and grade with the axis boring machine, using a 400mm tricone rock head in extremely hard basalt ground conditions. The $2.1 billion Sunbury Line Upgrade will see various upgrades within the rail corridor extending from Sunbury to Footscray. These enhancements are needed to take full advantage of the extra capacity created by the Metro Tunnel and for more modern trains to run on the Sunbury Line.

Adept Civil completed the 15 m bore on-line and grade with the axis boring machine for the Sunbury Line Upgrade project.

Adept installed a 376 mm GRP sleeve to carry 2 x 100 mm conduits for the power upgrades at the Tottenham Substation.

For more information visit www.adeptcivilgroup.com.au APRIL 2022 TRENCHLESS AUSTRALASIA 31


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

No-Dig Down Under

4min
pages 58-59

AI in the water sector: Safer, faster, better

2min
page 57

L&D purchases new high-power vac truck

3min
page 56

Providing cost-effective repair solutions

3min
pages 50-51

Wilmot Pipelining commits to customer service

1min
page 54

Thinking outside the box

5min
pages 52-53

A powerful drilling solution for tight, narrow job sites

4min
pages 46-47

Case study: Smart Lock restores badly damaged GWM Water network

4min
pages 48-49

S&Z Australia support North East Link early works

2min
pages 44-45

Larger and longer: TRACTO drill facilitates contractor’s biggest installation

5min
pages 42-43

Powerful pumps – the heart of HDD maxi-rig spreads

5min
pages 40-41

Vermeer HDD a fab addition for Irrifab

3min
pages 38-39

Ditch Witch CEA maximises profit and performance

2min
pages 34-35

kwik-ZIP gets the show on the road

2min
page 30

Sydney’s forgotten ghost tunnels all powered up with guided boring breakthrough

3min
pages 36-37

Adept completes bore for Sunbury Line

2min
page 31

Finding financing deals quickly and efficiently

3min
pages 32-33

Yarra Valley Water completes Doreen to Diamond Creek Sewerage Project

2min
pages 28-29

Carbon Calculator key to reducing trenchless industry emissions

5min
pages 20-21

From the President

2min
pages 10-11

From the ASTT Secretary

1min
pages 12-13

SECA promotes emissions reductions with the eCityJet electric jetting machine

3min
pages 26-27

The key to long-lasting plastic pipes and fittings

4min
pages 24-25

Rob Carr continues to take steps to reduce carbon footprint

4min
pages 22-23

Editor’s letter

3min
pages 8-9

Building for a better future

6min
pages 18-19
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.