Project Cycle Report: Infrastructure Project

Page 152

MUMBAI METRO LINE 3

Unit of measurement (BOQ),

KG

Unit of measurement in supply

KG

Approved make list

NEO JSW / TATA

Lead time for procurement

-APPROX 6-7 DAYS

.

34.6 Note*

tmt bars are prone to corrosion so they have to stored properly hence they are ordered only when activity to be started .reinforcement cages are not made on site. There is a reinforcement yard near World Trade Center (WTC), Cuffe Parade.

In the fig. given below, path shows the distance between the reinforcement yard (denoted as center one in figure) till station, So the reinforcement bars are procured at wtc cuffe parade and then transported to site as per need and requirement of activity

Figure 57: TMT Bars location

34.7 POLYMER SLURRY (BENT ONITE FOR PILE)

MORTH Specification Applicable IS Code Applicable

1115.2.3, Pg. 473 IS 2911 (Part 1/Sec 2): 2010

 The bentonite suspension used in bore holes is basically a clay of montmorillonite group having exchangeable sodium cations.  Bentonite suspension is used to maintain the stability of the borehole, it is essential that the properties of the material be carefully controlled at stages of mixing, supply to the borehole and immediately before concrete is placed.  Requirements  The liquid limit of bentonite when tested in accordance with IS 2720 (Part 5) shall be 400 percent or more.

SUBMITTED BY: BHUMIKA RAJ UC5316

147


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

Figure 83: Closure Of Project Flowchart

1min
page 194

Figure 81: Manpower Status0

0
page 190

Figure 72: Contents Of Mpr

5min
pages 183-185

Figure 71: Weekly Details

2min
page 182

Table 40: Characteristics Detail

1min
page 155

Figure 70: Billing Flowcart

1min
pages 180-181

Table 45: Format Of Snag List

1min
pages 178-179

Figure 62: Segments Location

1min
page 152

Figure 61: Tmt Bars Location

2min
pages 148-149

Figure 55: Codification Example

1min
page 135

Figure 40: Project Package Details

1min
page 74

Figure 31: Flow Chart For Labour License

4min
pages 86-87

Table 30: Cash Outflow

1min
page 78

Table 24: Cost Estimate

2min
page 71

Figure 54: Softwares Used

4min
pages 133-134

Table 32: Cash Outflow For Year 2016-2017

0
page 120

Figure 37: Work Schedule Format

2min
page 64

Table 14: International Protocols

1min
page 62

Figure 11:Mumbai Metro Network

1min
page 36

Table 2: List Of Projects

1min
page 21

Table 11: Funding Pattern Break Up

4min
pages 46-49

Figure 5: Alignment Of Passengers In Suburban Rail

3min
pages 28-29

Figure 13: Funding Breakup

1min
page 43

Figure 14:Flowchart Showing The Formation Of Insititutional Framework By Goi For Carrying Out Approvals

3min
pages 52-53

Figure 33: Bid Document Details

3min
pages 50-51
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.