Project Cycle Report: Infrastructure Project

Page 190

MUMBAI METRO LINE 3

Figure 70: tbm progress0

47.2 QA/QC Quality Procedure: We are operating based on the approved Project Quality Plan, Consisting of ISO 9001:2015. All the activities are being carried out after approval of Work Methodology which is adhering to Contract, code and technical specifications. • Quality Assurance: Material quality is being confirmed by testing as per approved ITP. • Quality Control: Approved WIR, Checklist system are in practice at field for effective control on product and productivity. 47.2.1 QUALITY CONTROL GRAP H FOR M50

SUBMITTED BY: BHUMIKA RAJ UC5316

186